Permit Number:  BLD2018-04056     Status:   Finaled     Map Info:   444 N LOARA ST (Meter)
Name:  ALPHA OMEGA CONSTRUCTORS INC
Address: 444 N LOARA
Received Date: 09/07/2018 
Parcel: 07211041 
Plan Check Date:  
Issue Date: 02/11/2019 
Expiration Date: 08/11/2020 
Finaled Date: 04/07/2020 
Description: Miscellaneous: Install (8) EV charging stations and (2) accessible EV charging stations, (1) transformers and (1) switchboard. Relocate (1) light pole. 8 ft high x 150 ln ft of Trex fence.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Addressing  9/7/2018  9/21/2018    9/7/2018  APPR  HXN 
Approved by Addressing  9/7/2018      9/7/2018 2:03:11 PM  APPR  HXN 
Route to Electrical  9/7/2018  9/21/2018    9/19/2018  APPR  MCS 
Approved by Electrical  9/7/2018      9/19/2018 10:45:25 AM  APPR  MCS 
Route to Elec Engineering  9/7/2018  9/21/2018    9/18/2018  CORR  NEG 
Approved by Elec Engineering  9/7/2018      11/27/2018 9:01:56 AM  APPR  JJB 
Route to Fire Department  9/7/2018  9/21/2018    9/24/2018  NR  EPO 
Approved by Fire Department  9/7/2018      9/24/2018 11:12:28 AM  NR  EPO 
Route to Planning Zoning  9/7/2018  9/21/2018    9/18/2018  CORR  LEO 
Approved by Planning Zoning  9/7/2018      12/24/2018 4:21:03 PM  APPR  LEO 
Route to PW Operations  9/7/2018  9/21/2018    9/13/2018  NR  LMM 
Approved by PW Operations  9/7/2018      9/13/2018 10:54:17 AM  NR  LMM 
Route to PW Develop. Services  9/7/2018  9/21/2018    9/26/2018  CORR  AVP 
Apprv. by PW Develop. Services  9/7/2018      11/21/2018 10:55:44 AM  APPR  AVP 
Route to Struct/Architectual  9/7/2018  9/21/2018    9/20/2018  CORR  WCL 
Apprv. by Struct/Architectural  9/7/2018      12/26/2018 10:48:43 AM  APPR  WCL 
Route to Traffic Engineering  9/7/2018  9/21/2018    9/21/2018  CORR  RXC 
Approved by Traffic Eng.  9/7/2018      1/18/2019 9:39:24 AM  APPR  AMI 
Route to Water Engineering  9/7/2018  9/21/2018    9/24/2018  APPR  DRS 
Approved by Water Engineering  9/7/2018      9/24/2018 1:06:49 PM  APPR  DRS 
Inspection by Fire Department  9/24/2018  10/1/2018    4/3/2020  DONE  638 
Route to Elec Engineering  11/14/2018  11/21/2018    11/27/2018  APPR  JJB 
Route to Planning Zoning  11/14/2018  11/21/2018    11/20/2018  CORR  LEO 
Route to Traffic Engineering  11/14/2018  11/21/2018    11/26/2018  CORR  RXC 
Route to PW Develop. Services  11/14/2018  11/21/2018    11/21/2018  APPR  AVP 
Route to Struct/Architectual  11/14/2018  11/21/2018    11/16/2018  CORR  WCL 
Route to Planning Zoning  12/19/2018  12/27/2018    12/24/2018  APPR  LEO 
Route to Traffic Engineering  12/19/2018  12/27/2018    12/27/2018  CORR  AMI 
Route to Struct/Architectual  12/19/2018  12/27/2018    12/26/2018  APPR  WCL 
Route to Traffic Engineering  1/8/2019  1/15/2019    1/15/2019  CORR  AMI 
Route to Struct/Architectual  1/17/2019  1/25/2019    1/17/2019  APPR  WCL 
Route to Traffic Engineering  1/17/2019  1/25/2019    1/18/2019  APPR  AMI 
Approved by Bus Lic (Sub List)  2/11/2019  4/1/2020    4/1/2020  APPR  RHZ 
ELE - Underground conduit  6/26/2019  6/27/2019  10 AM - 2 PM  6/27/2019  JSC 
BLD - Pre-Slab Insp  6/26/2019  6/27/2019  10 AM - 2 PM  6/27/2019  JSC 
BLD - Footings Insp  6/27/2019  6/27/2019    6/27/2019  JSC 
BLD - Pre-Slab Insp  7/2/2019  7/5/2019    7/2/2019  CANC   
BLD - Pre-Slab Insp  7/9/2019  7/10/2019  8 AM - 12 PM  7/10/2019  JSC 
BLD - Pre-Slab Insp  7/9/2019  7/10/2019  8 AM - 12 PM  7/10/2019  JSC 
BLD - Pre-Slab Insp  7/10/2019  7/11/2019  8 AM - 12 PM  7/11/2019  JSC 
ELE - Rough Electrical  7/23/2019  7/24/2019  8 AM - 12 PM  7/24/2019  JFR 
ELE - Rough Electrical  7/31/2019  8/1/2019  8 AM - 12 PM  8/1/2019  JSC 
ELE - Electrical Service/Meter  4/2/2020  4/3/2020  12 PM - 3 PM  4/3/2020  JSC 
Electrical Final Insp Request  4/2/2020  4/3/2020  12 PM - 3 PM  4/3/2020  JSC 
Electrical Final        4/3/2020    JSC 
Building Final Insp Request  4/6/2020  4/7/2020  8 AM - 12 PM  4/7/2020  JSC 
Building Final        4/7/2020    JSC 

 