Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Struct/Architectual  |
9/12/2019  |
9/19/2019  |
  |
9/19/2019  |
APPR  |
ITW  |
Apprv. by Struct/Architectural  |
9/12/2019  |
  |
  |
9/20/2019 9:42:09 AM  |
APPR  |
ITW  |
Route to Planning Zoning  |
9/12/2019  |
9/19/2019  |
  |
9/16/2019  |
APPR  |
EYT  |
Approved by Planning Zoning  |
9/12/2019  |
  |
  |
9/16/2019 3:00:10 PM  |
APPR  |
EYT  |
Approved by Addressing  |
9/12/2019  |
  |
  |
9/13/2019 10:09:30 AM  |
APPR  |
HXN  |
Route to Addressing  |
9/12/2019  |
9/19/2019  |
  |
9/13/2019  |
APPR  |
HXN  |
Route to Elec Engineering  |
9/12/2019  |
9/19/2019  |
  |
9/16/2019  |
APPR  |
JJB  |
Approved by Elec Engineering  |
9/12/2019  |
  |
  |
9/16/2019 10:12:30 AM  |
APPR  |
JJB  |
Approved by Fire Department  |
9/12/2019  |
  |
  |
9/17/2019 5:19:53 PM  |
APPR  |
EPO  |
Route to Fire Department  |
9/12/2019  |
9/19/2019  |
  |
9/17/2019  |
APPR  |
EPO  |
Approved by C&D Waste Mgmt  |
9/12/2019  |
  |
  |
9/25/2019  |
APPR  |
RGO  |
Route to C&D Waste Mgmt  |
9/12/2019  |
9/19/2019  |
  |
9/25/2019  |
APPR  |
RGO  |
Inspection by Fire Department  |
9/17/2019  |
9/24/2019  |
  |
10/10/2019  |
DONE  |
MGA  |
BLD - Framing Insp.  |
9/25/2019  |
9/26/2019  |
10 AM - 2 PM  |
9/26/2019  |
N  |
BEN  |
BLD - Framing Insp.  |
9/27/2019 1:01:14 PM  |
9/30/2019  |
8 AM - 12 PM  |
9/30/2019  |
A  |
PJJ  |
BLD - Drywall Inspection  |
10/1/2019 11:57:29 AM  |
10/2/2019  |
8 AM - 12 PM  |
10/2/2019  |
A  |
PJJ  |
Approved by Bus Lic (Sub List)  |
10/1/2019  |
10/1/2019  |
  |
10/2/2019  |
APPR  |
RHZ  |
BLD - Insulation Insp  |
10/7/2019  |
10/8/2019  |
8 AM - 12 PM  |
10/8/2019  |
C  |
PJJ  |
Building Final Insp Request  |
10/10/2019  |
10/11/2019  |
10 AM - 2 PM  |
10/11/2019  |
A  |
BEN  |
Building Final  |
  |
  |
  |
10/11/2019  |
  |
BEN  |