Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Traffic Engineering  |
4/3/2019  |
4/19/2019  |
  |
4/22/2019  |
APPR  |
RXC  |
Approved by Traffic Eng.  |
4/3/2019  |
  |
  |
4/22/2019 6:06:28 PM  |
APPR  |
RXC  |
Route to PW Develop. Services  |
4/3/2019  |
4/19/2019  |
  |
4/22/2019  |
CORR  |
SXA  |
Apprv. by PW Develop. Services  |
4/3/2019  |
  |
  |
5/28/2019 5:14:46 PM  |
APPR  |
SXA  |
Route to Fire Department  |
4/3/2019  |
4/19/2019  |
  |
4/23/2019  |
APPR  |
EPO  |
Approved by Fire Department  |
4/3/2019  |
  |
  |
4/23/2019 2:41:32 PM  |
APPR  |
EPO  |
Route to Elec Engineering  |
4/3/2019  |
4/19/2019  |
  |
4/23/2019  |
APPR  |
JJB  |
Approved by Elec Engineering  |
4/3/2019  |
  |
  |
4/23/2019 8:57:38 AM  |
APPR  |
JJB  |
Route to Struct/Architectual  |
4/3/2019  |
4/19/2019  |
  |
4/22/2019  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
4/3/2019  |
  |
  |
5/28/2019 7:57:46 PM  |
APPR  |
ITW  |
Route to Planning Zoning  |
4/3/2019  |
4/19/2019  |
  |
4/29/2019  |
CORR  |
EYT  |
Approved by Planning Zoning  |
4/3/2019  |
  |
  |
6/5/2019 3:00:39 PM  |
APPR  |
EYT  |
Route to Water Engineering  |
4/3/2019  |
4/19/2019  |
  |
4/18/2019  |
APPR  |
DRS  |
Approved by Water Engineering  |
4/3/2019  |
  |
  |
4/18/2019 4:33:27 PM  |
APPR  |
DRS  |
Route to Electrical  |
4/3/2019  |
4/19/2019  |
  |
4/18/2019  |
APPR  |
MCS  |
Approved by Electrical  |
4/3/2019  |
  |
  |
4/18/2019 8:43:54 AM  |
APPR  |
MCS  |
Approved by Addressing  |
4/3/2019  |
  |
  |
4/5/2019 11:47:16 AM  |
APPR  |
HXN  |
Route to Addressing  |
4/3/2019  |
4/19/2019  |
  |
4/5/2019  |
APPR  |
HXN  |
Route to C&D Waste Mgmt  |
4/3/2019  |
4/19/2019  |
  |
6/5/2019  |
APPR  |
RGO  |
Approved by C&D Waste Mgmt  |
4/3/2019  |
  |
  |
6/5/2019  |
APPR  |
RGO  |
Approved by Mechanical  |
4/3/2019  |
  |
  |
4/19/2019 8:55:20 AM  |
APPR  |
ITW  |
Route to Mechanical  |
4/3/2019  |
4/19/2019  |
  |
4/19/2019  |
APPR  |
ITW  |
Approved by Plumbing  |
4/3/2019  |
  |
  |
4/19/2019 8:55:35 AM  |
APPR  |
ITW  |
Route to Plumbing  |
4/3/2019  |
4/19/2019  |
  |
4/19/2019  |
APPR  |
ITW  |
Route to Struct/Architectual  |
5/9/2019  |
5/27/2019  |
  |
5/24/2019  |
APPR  |
ITW  |
Route to PW Develop. Services  |
5/10/2019  |
5/28/2019  |
  |
5/28/2019  |
APPR  |
SXA  |
Route to Planning Zoning  |
5/10/2019  |
5/28/2019  |
  |
6/5/2019  |
APPR  |
EYT  |
Approved: School Fees Due  |
4/3/2019  |
  |
  |
6/6/2019  |
APPR  |
CMN  |
BLD - Footings Insp  |
8/5/2019 8:04:10 AM  |
8/6/2019  |
8 AM - 12 PM  |
8/6/2019  |
P  |
PJJ  |
BLD - Footings Insp  |
8/15/2019 9:06:27 AM  |
8/16/2019  |
  |
8/16/2019  |
P  |
BEN  |
BLD - Footings Insp  |
8/28/2019 9:48:31 AM  |
8/29/2019  |
8 AM - 12 PM  |
8/29/2019  |
P  |
PJJ  |
Approved Revision Electrical  |
  |
  |
  |
10/3/2019  |
DONE  |
SKD  |
Route Revision Electrical  |
9/13/2019  |
10/1/2019  |
  |
9/30/2019  |
APPR  |
MCS  |
Approved by Fire Department  |
9/13/2019  |
  |
  |
9/30/2019 2:18:55 PM  |
APPR  |
EPO  |
Route to Fire Department  |
9/13/2019  |
10/1/2019  |
  |
9/30/2019  |
APPR  |
EPO  |
Approved Revision Mechanical  |
  |
  |
  |
10/1/2019  |
APPR  |
EWC  |
Route Revision Mechanical  |
9/13/2019  |
10/1/2019  |
  |
10/1/2019  |
APPR  |
EWC  |
Approved by Planning Zoning  |
9/13/2019  |
  |
  |
10/3/2019 10:42:52 AM  |
APPR  |
EYT  |
Route to Planning Zoning  |
9/13/2019  |
10/1/2019  |
  |
10/3/2019  |
APPR  |
EYT  |
Approved Revision Plumbing  |
  |
  |
  |
10/1/2019  |
DONE  |
EWC  |
Route Revision Plumbing  |
9/13/2019  |
10/1/2019  |
  |
10/1/2019  |
NR  |
EWC  |
Approved Revision Structural  |
9/13/2019  |
  |
  |
9/26/2019  |
APPR  |
ITW  |
Route Revision Structural  |
9/13/2019  |
10/1/2019  |
  |
9/26/2019  |
APPR  |
ITW  |
BLD - Footings Insp  |
9/16/2019 6:52:40 AM  |
9/17/2019  |
12 PM - 3 PM  |
9/17/2019  |
P  |
BEN  |
BLD - Reinforcing Insp  |
10/17/2019 1:33:46 PM  |
10/18/2019  |
12 PM - 3 PM  |
10/18/2019  |
N  |
BEN  |
BLD - Footings Insp  |
10/18/2019  |
10/19/2019  |
  |
10/23/2019  |
P  |
BEN  |
BLD - Pre-Slab Insp  |
10/23/2019 2:01:57 PM  |
10/24/2019  |
  |
10/24/2019  |
P  |
BEN  |
BLD - Pre-Slab Insp  |
10/28/2019 7:36:21 AM  |
10/29/2019  |
10 AM - 2 PM  |
10/29/2019  |
P  |
BEN  |
BLD - Pre-Slab Insp  |
11/7/2019 5:51:17 AM  |
11/8/2019  |
12 PM - 3 PM  |
11/8/2019  |
P  |
BEN  |
BLD - Reinforcing Insp  |
11/14/2019 9:38:57 AM  |
11/15/2019  |
  |
11/15/2019  |
P  |
BEN  |
BLD - Reinforcing Insp  |
11/21/2019 11:16:34 AM  |
11/22/2019  |
10 AM - 2 PM  |
11/22/2019  |
N  |
BEN  |
BLD - Reinforcing Insp  |
11/22/2019 11:36:10 AM  |
11/25/2019  |
10 AM - 2 PM  |
11/25/2019  |
C  |
PJJ  |
BLD - Pre-Slab Insp  |
11/25/2019 1:48:49 PM  |
11/26/2019  |
10 AM - 2 PM  |
11/26/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
12/13/2019 6:25:45 AM  |
12/16/2019  |
10 AM - 2 PM  |
12/16/2019  |
P  |
PJJ  |
BLD - Framing Insp.  |
12/17/2019 2:22:53 PM  |
12/18/2019  |
10 AM - 2 PM  |
12/18/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
12/18/2019 4:16:10 PM  |
12/20/2019  |
12 PM - 3 PM  |
12/20/2019  |
P  |
BEN  |
BLD - Reinforcing Insp  |
12/19/2019 9:08:43 AM  |
12/20/2019  |
12 PM - 3 PM  |
12/20/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
12/19/2019 9:48:01 AM  |
12/23/2019  |
8 AM - 12 PM  |
12/23/2019  |
P  |
PJJ  |
BLD - 2nd Floor Nailing  |
12/24/2019 6:26:12 AM  |
12/26/2019  |
8 AM - 12 PM  |
12/26/2019  |
C  |
BEN  |
BLD - 2nd Floor Nailing  |
1/2/2020 11:53:06 AM  |
1/3/2020  |
12 PM - 3 PM  |
1/3/2020  |
C  |
BEN  |
BLD - Drywall Inspection  |
1/3/2020 2:04:51 PM  |
1/7/2020  |
8 AM - 12 PM  |
1/7/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
1/8/2020 9:12:15 AM  |
1/9/2020  |
8 AM - 12 PM  |
1/9/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
1/9/2020 2:35:36 PM  |
1/10/2020  |
8 AM - 12 PM  |
1/10/2020  |
P  |
BEN  |
BLD - Drywall Inspection  |
1/20/2020 10:01:49 AM  |
1/21/2020  |
10 AM - 2 PM  |
1/21/2020  |
P  |
PJJ  |
BLD - Framing Insp.  |
1/20/2020 10:04:10 AM  |
1/21/2020  |
10 AM - 2 PM  |
1/21/2020  |
P  |
PJJ  |
BLD - Framing Insp.  |
1/24/2020 2:33:29 PM  |
1/27/2020  |
10 AM - 2 PM  |
1/27/2020  |
P  |
PJJ  |
Route to Fire Department  |
1/27/2020  |
2/3/2020  |
  |
1/29/2020  |
APPR  |
472  |
Approved by Fire Department  |
1/27/2020  |
  |
  |
1/29/2020 10:00:35 AM  |
APPR  |
472  |
Route to Planning Zoning  |
1/27/2020  |
2/3/2020  |
  |
1/30/2020  |
APPR  |
EYT  |
Approved by Planning Zoning  |
1/27/2020  |
  |
  |
1/30/2020 12:58:32 PM  |
APPR  |
EYT  |
Route to Struct/Architectual  |
1/27/2020  |
2/3/2020  |
  |
2/3/2020  |
APPR  |
ITW  |
Apprv. by Struct/Architectural  |
1/27/2020  |
  |
  |
2/3/2020 4:36:50 PM  |
APPR  |
ITW  |
BLD - Framing Insp.  |
1/28/2020 1:25:13 PM  |
1/29/2020  |
  |
1/29/2020  |
P  |
BEN  |
BLD - Insulation Insp  |
1/28/2020 1:25:39 PM  |
1/29/2020  |
  |
1/29/2020  |
C  |
BEN  |
BLD - Drywall Inspection  |
1/28/2020 1:25:54 PM  |
1/29/2020  |
  |
1/29/2020  |
P  |
BEN  |
BLD - Penetrations -Fire Rated  |
1/28/2020 2:04:33 PM  |
1/29/2020  |
  |
1/29/2020  |
P  |
BEN  |
Inspection by Fire Department  |
1/29/2020  |
2/14/2020  |
  |
12/4/2020  |
DONE  |
638  |
BLD - Framing Insp.  |
2/6/2020 1:20:31 PM  |
2/7/2020  |
12 PM - 3 PM  |
2/7/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
2/19/2020 2:03:12 PM  |
2/20/2020  |
8 AM - 12 PM  |
2/20/2020  |
P  |
BEN  |
BLD - Drywall Inspection  |
2/26/2020 12:29:07 PM  |
2/27/2020  |
10 AM - 2 PM  |
2/27/2020  |
P  |
PJJ  |
BLD - Exterior Lath Insp  |
2/27/2020 7:57:17 AM  |
2/28/2020  |
10 AM - 2 PM  |
2/28/2020  |
P  |
PJJ  |
BLD - Exterior Lath Insp  |
3/9/2020 9:45:56 AM  |
3/10/2020  |
8 AM - 12 PM  |
3/10/2020  |
P  |
PJJ  |
BLD - Footings Insp  |
3/9/2020 9:46:23 AM  |
3/10/2020  |
8 AM - 12 PM  |
3/10/2020  |
C  |
PJJ  |
Approved Revision Electrical  |
  |
  |
  |
3/12/2020  |
APPR  |
MCS  |
Approved Revision Electrical  |
  |
  |
  |
3/12/2020  |
DONE  |
MCS  |
Route Revision Electrical  |
3/12/2020  |
3/30/2020  |
  |
3/12/2020  |
APPR  |
MCS  |
BLD - Framing Insp.  |
3/18/2020 12:12:30 PM  |
3/19/2020  |
10 AM - 2 PM  |
3/19/2020  |
C  |
BEN  |
BLD - Reinforcing Insp  |
3/19/2020 5:18:10 PM  |
3/20/2020  |
12 PM - 3 PM  |
3/20/2020  |
P  |
BEN  |
Apprv. by Struct/Architectural  |
4/6/2020  |
  |
  |
4/22/2020 4:30:21 PM  |
APPR  |
ITW  |
Route to Struct/Architectual  |
4/6/2020  |
4/27/2020  |
  |
4/22/2020  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
4/14/2020  |
  |
  |
4/22/2020  |
APPR  |
ITW  |
Route to Struct/Architectual  |
4/14/2020  |
4/30/2020  |
  |
4/22/2020  |
APPR  |
ITW  |
Route to Struct/Architectual  |
5/18/2020  |
6/9/2020  |
  |
5/22/2020  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
5/18/2020  |
  |
  |
9/30/2020 5:50:47 PM  |
APPR  |
ITW  |
BLD - Exterior Lath Insp  |
6/5/2020  |
6/8/2020  |
8 AM - 12 PM  |
6/8/2020  |
P  |
PJJ  |
BLD - Reinforcing Insp  |
6/26/2020 6:53:56 AM  |
6/29/2020  |
10 AM - 2 PM  |
6/29/2020  |
P  |
JOS  |
Route to Struct/Architectual  |
6/30/2020  |
7/16/2020  |
  |
7/6/2020  |
CORR  |
ITW  |
BLD - Reinforcing Insp  |
8/20/2020 3:09:43 PM  |
8/21/2020  |
8 AM - 12 PM  |
8/21/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
8/24/2020 2:12:01 PM  |
8/25/2020  |
10 AM - 2 PM  |
8/25/2020  |
N  |
BEN  |
BLD - T-Bar (Structural) Insp  |
8/28/2020 12:02:36 PM  |
8/31/2020  |
8 AM - 12 PM  |
8/31/2020  |
P  |
PJJ  |
Route to Struct/Architectual  |
9/15/2020  |
9/30/2020  |
  |
9/30/2020  |
APPR  |
ITW  |
BLD - T-Bar (Structural) Insp  |
10/2/2020 6:24:44 AM  |
10/5/2020  |
8 AM - 12 PM  |
10/5/2020  |
P  |
PJJ  |
Route to Struct/Architectual  |
10/26/2020  |
11/12/2020  |
  |
11/13/2020  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
10/26/2020  |
  |
  |
11/25/2020 9:44:50 AM  |
APPR  |
ITW  |
Route to Struct/Architectual  |
10/27/2020  |
11/13/2020  |
  |
11/6/2020  |
APPR  |
ITW  |
Apprv. by Struct/Architectural  |
10/27/2020  |
  |
  |
11/6/2020 2:23:08 PM  |
APPR  |
ITW  |
Route to Struct/Architectual  |
10/28/2020  |
11/16/2020  |
  |
11/16/2020  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
10/28/2020  |
  |
  |
11/20/2020 2:27:54 PM  |
APPR  |
ITW  |
BLD - Reinforcing Insp  |
10/28/2020  |
11/3/2020  |
8 AM - 12 PM  |
11/3/2020  |
F  |
PJJ  |
BLD - Drywall Inspection  |
10/30/2020 12:27:06 PM  |
11/2/2020  |
8 AM - 12 PM  |
11/2/2020  |
P  |
PJJ  |
Route to Struct/Architectual  |
11/2/2020  |
11/19/2020  |
  |
11/6/2020  |
APPR  |
ITW  |
Apprv. by Struct/Architectural  |
11/2/2020  |
  |
  |
11/6/2020  |
APPR  |
ITW  |
Route to Struct/Architectual  |
11/2/2020  |
11/19/2020  |
  |
11/6/2020  |
CORR  |
ITW  |
Apprv. by Struct/Architectural  |
11/2/2020  |
  |
  |
11/20/2020  |
APPR  |
ITW  |
BLD - Framing Insp.  |
11/5/2020 2:25:43 PM  |
11/6/2020  |
8 AM - 12 PM  |
11/6/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
11/12/2020 2:51:23 PM  |
11/13/2020  |
8 AM - 12 PM  |
11/13/2020  |
P  |
BEN  |
Route to Struct/Architectual  |
11/16/2020  |
12/4/2020  |
  |
11/25/2020  |
APPR  |
ITW  |
Route to Struct/Architectual  |
11/17/2020  |
12/7/2020  |
  |
11/20/2020  |
APPR  |
ITW  |
Approved by Bus Lic (Sub List)  |
11/20/2020  |
11/20/2020  |
  |
11/20/2020  |
APPR  |
RHZ  |
Route to Struct/Architectual  |
11/24/2020  |
12/14/2020  |
  |
12/3/2020  |
APPR  |
ITW  |
BLD - Framing Insp.  |
11/25/2020 12:36:17 PM  |
12/1/2020  |
8 AM - 12 PM  |
12/1/2020  |
P  |
BEN  |
BLD - Framing Insp.  |
12/3/2020 3:31:17 PM  |
12/4/2020  |
10 AM - 2 PM  |
12/4/2020  |
A  |
BEN  |
Building Final Insp Request  |
12/4/2020  |
12/5/2020  |
  |
12/9/2020  |
A  |
BEN  |
Building Final  |
  |
  |
  |
12/9/2020  |
  |
BEN  |
Planning GIS - Building Change  |
12/9/2020 6:52:33 AM  |
  |
  |
12/18/2020  |
DONE  |
MAR3  |