Permit Number:  BLD2018-05318     Status:   Finaled     Map Info:   1313 S DISNEYLAND DR (Mickey and Friends Parking Structure)
Name:  BOMEL CONSTRUCTION COMPANY INC
Address: 1313 S DISNEYLAND
Received Date: 11/27/2018 
Parcel: 12931102 
Plan Check Date:  
Issue Date: 01/11/2019 
Expiration Date: 07/14/2020 
Finaled Date: 02/14/2020 
Description: Mickey and Friends - Non Residential Addtion: New 5 level elevator shaft total 1800 sq.ft of floor area, 450 sq.ft deck. 200 sq.ft machine room less, constructed within existing footprint. 

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Traffic Engineering  11/27/2018  12/11/2018    12/13/2018  NR  RXC 
Approved by Traffic Eng.  11/27/2018      12/13/2018 4:10:39 PM  NR  RXC 
Route to PW Develop. Services  11/27/2018  12/11/2018    12/20/2018  CORR  SXA 
Apprv. by PW Develop. Services  11/27/2018      1/3/2019 3:59:29 PM  APPR  SXA 
Route to Fire Department  11/27/2018  12/11/2018    12/13/2018  APPR  EPO 
Approved by Fire Department  11/27/2018      12/13/2018 10:42:45 AM  APPR  EPO 
Route to Elec Engineering  11/27/2018  12/11/2018    12/13/2018  APPR  JMC 
Approved by Elec Engineering  11/27/2018      12/13/2018 9:27:57 AM  APPR  JMC 
Route to Struct/Architectual  11/27/2018  12/11/2018    12/11/2018  APPR  BVD 
Apprv. by Struct/Architectural  11/27/2018      12/11/2018 4:45:38 PM  APPR  BVD 
Route to Planning Zoning  11/27/2018  12/11/2018    12/20/2018  APPR  EYT 
Approved by Planning Zoning  11/27/2018      12/20/2018 11:16:38 AM  APPR  EYT 
Route to Water Engineering  11/27/2018  12/11/2018    12/10/2018  APPR  DRS 
Approved by Water Engineering  11/27/2018      12/10/2018 12:36:13 PM  APPR  DRS 
Approved by Bus Lic (Sub List)  11/28/2018  2/13/2020    2/13/2020  APPR  RHZ 
Approved by Electrical  11/27/2018      12/11/2018 9:44:28 AM  APPR  MCS 
Route to Electrical  11/27/2018  12/11/2018    12/11/2018  APPR  MCS 
Approved by Mechanical  11/27/2018      1/3/2019 3:22:46 PM  APPR  GAQ 
Route to Mechanical  11/27/2018  12/11/2018    12/11/2018  CORR  GAQ 
Approved by Plumbing  11/27/2018      1/3/2019 3:22:13 PM  APPR  GAQ 
Route to Plumbing  11/27/2018  12/11/2018    12/11/2018  CORR  GAQ 
Approved: School Fees Due  11/27/2018      1/11/2019  APPR  CJE 
Inspection by Fire Department  12/13/2018  12/28/2018    2/13/2020  DONE  638 
Route to Mechanical  12/26/2018  1/3/2019    1/3/2019  APPR  GAQ 
Route to Plumbing  12/26/2018  1/3/2019    1/3/2019  APPR  GAQ 
Route to PW Develop. Services  12/26/2018  1/3/2019    1/3/2019  APPR  SXA 
Route to Struct/Architectual  12/26/2018  1/3/2018    1/3/2019  APPR  BVD 
BLD - Footings Insp  7/9/2019 3:02:49 PM  7/11/2019  12 PM - 3 PM  7/11/2019  BCJ 
BLD - Reinforcing Insp  7/9/2019 3:04:56 PM  7/10/2019  12 PM - 3 PM  7/10/2019  BCJ 
BLD - Reinforcing Insp  7/9/2019 3:05:38 PM  7/11/2019  12 PM - 3 PM  7/11/2019  BCJ 
BLD - Reinforcing Insp  7/15/2019 12:41:26 PM  7/17/2019  12 PM - 3 PM  7/17/2019  BCJ 
ELE - Underground conduit  7/15/2019 12:41:58 PM  7/17/2019  12 PM - 3 PM  7/17/2019  BCJ 
BLD - Pre-Slab Insp  7/24/2019 4:56:40 PM  7/25/2019  12 PM - 3 PM  7/25/2019  BCJ 
ELE - Underground conduit  7/24/2019 4:57:03 PM  7/25/2019  12 PM - 3 PM  7/25/2019  BCJ 
BLD - Reinforcing Insp  7/24/2019 5:04:55 PM  7/30/2019  12 PM - 3 PM  7/30/2019  BCJ 
ELE - Underground conduit  7/24/2019 5:05:25 PM  7/30/2019  12 PM - 3 PM  7/30/2019  BCJ 
BLD - Pre-Slab Insp  7/25/2019  7/26/2019  12 PM - 3 PM  7/26/2019  BCJ 
BLD - Pre-Slab Insp  7/26/2019 4:07:42 PM  7/31/2019  12 PM - 3 PM  7/31/2019  BCJ 
ELE - Underground conduit  7/26/2019 4:08:21 PM  7/31/2019  12 PM - 3 PM  7/31/2019  BCJ 
BLD - Reinforcing Insp  7/26/2019 4:10:03 PM  8/2/2019  12 PM - 3 PM  8/2/2019  BCJ 
ELE - Underground conduit  7/26/2019 4:10:42 PM  8/2/2019  12 PM - 3 PM  8/2/2019  BCJ 
BLD - Pre-Slab Insp  8/2/2019 2:19:50 PM  8/6/2019  12 PM - 3 PM  8/6/2019  BCJ 
ELE - Underground conduit  8/2/2019 2:20:27 PM  8/6/2019  12 PM - 3 PM  8/6/2019  BCJ 
BLD - Reinforcing Insp  8/2/2019 2:21:03 PM  8/6/2019  12 PM - 3 PM  8/6/2019  BCJ 
BLD - Reinforcing Insp  8/2/2019 2:22:19 PM  8/7/2019  12 PM - 3 PM  8/7/2019  BCJ 
ELE - Underground conduit  8/2/2019 2:22:53 PM  8/7/2019  12 PM - 3 PM  8/7/2019  BCJ 
BLD - Pre-Slab Insp  8/5/2019 10:32:29 AM  8/9/2019  12 PM - 3 PM  8/9/2019  BCJ 
ELE - Underground conduit  8/5/2019 10:33:01 AM  8/9/2019  12 PM - 3 PM  8/9/2019  BCJ 
BLD - Reinforcing Insp  8/5/2019 10:33:40 AM  8/9/2019  12 PM - 3 PM  8/9/2019  BCJ 
BLD - Reinforcing Insp  8/6/2019 2:42:33 PM  8/13/2019  12 PM - 3 PM  8/13/2019  BCJ 
ELE - Underground conduit  8/6/2019 2:43:05 PM  8/13/2019  12 PM - 3 PM  8/13/2019  BCJ 
BLD - Pre-Slab Insp  8/12/2019 4:18:36 PM  8/14/2019  12 PM - 3 PM  8/14/2019  BCJ 
ELE - Underground conduit  8/12/2019 4:19:03 PM  8/14/2019  12 PM - 3 PM  8/14/2019  BCJ 
BLD - Reinforcing Insp  8/12/2019 4:19:58 PM  8/14/2019  12 PM - 3 PM  8/14/2019  BCJ 
BLD - Reinforcing Insp  8/12/2019 4:20:35 PM  8/16/2019  12 PM - 3 PM  8/16/2019  BCJ 
ELE - Underground conduit  8/12/2019 4:21:15 PM  8/16/2019  12 PM - 3 PM  8/16/2019  BCJ 
BLD - Reinforcing Insp  8/14/2019 1:57:37 PM  8/15/2019  12 PM - 3 PM  8/15/2019  BCJ 
ELE - Underground conduit  8/14/2019 1:57:59 PM  8/15/2019  12 PM - 3 PM  8/15/2019  BCJ 
Approved Revision Structural  8/14/2019      8/29/2019  DONE  BVD 
Route Revision Structural  8/14/2019  8/21/2019    8/28/2019  APPR  BVD 
BLD - Pre-Slab Insp  8/19/2019 5:38:20 PM  8/20/2019  12 PM - 3 PM  8/20/2019  BCJ 
ELE - Underground conduit  8/19/2019 5:38:42 PM  8/20/2019  12 PM - 3 PM  8/20/2019  BCJ 
Apprv. by Struct/Architectural  8/22/2019      8/28/2019 5:04:14 PM  APPR  BVD 
Route to Struct/Architectual  8/22/2019  9/6/2019    8/28/2019  APPR  BVD 
BLD - Framing Insp.  9/9/2019 3:09:04 PM  9/10/2019  12 PM - 3 PM  9/10/2019  BCJ 
BLD - Framing Insp.  9/10/2019 6:05:59 PM  9/11/2019  12 PM - 3 PM  9/11/2019  BCJ 
PLM - Rough/Topout  9/11/2019 5:13:18 PM  9/12/2019  12 PM - 3 PM  9/12/2019  BCJ 
BLD - Drywall Inspection  9/11/2019 5:13:52 PM  9/12/2019  12 PM - 3 PM  9/12/2019  BCJ 
BLD - Framing Insp.  9/17/2019 2:46:11 PM  9/18/2019  12 PM - 3 PM  9/18/2019  BCJ 
BLD - Drywall Inspection  9/17/2019 2:47:57 PM  9/18/2019  12 PM - 3 PM  9/18/2019  BCJ 
BLD - Framing Insp.  9/18/2019 4:17:07 PM  9/19/2019  12 PM - 3 PM  9/19/2019  BCJ 
BLD - Drywall Inspection  9/18/2019 4:17:24 PM  9/19/2019  12 PM - 3 PM  9/19/2019  BCJ 
BLD - Framing Insp.  9/19/2019 2:55:57 PM  9/20/2019  12 PM - 3 PM  9/20/2019  BCJ 
BLD - Drywall Inspection  9/19/2019 2:56:31 PM  9/20/2019  12 PM - 3 PM  9/20/2019  BCJ 
PLM - Rough/Topout  9/19/2019 3:15:21 PM  9/20/2019  12 PM - 3 PM  9/20/2019  BCJ 
BLD - Roof Sheathing Insp.  9/23/2019 12:33:47 PM  9/24/2019  12 PM - 3 PM  9/24/2019  BCJ 
BLD - Framing Insp.  9/23/2019 12:34:06 PM  9/24/2019  12 PM - 3 PM  9/24/2019  BCJ 
BLD - Drywall Inspection  9/23/2019 12:34:16 PM  9/24/2019  12 PM - 3 PM  9/24/2019  BCJ 
ELE - Rough Electrical  9/23/2019 12:34:45 PM  9/24/2019  12 PM - 3 PM  9/24/2019  BCJ 
BLD - Framing Insp.  9/24/2019 3:17:58 PM  9/25/2019  12 PM - 3 PM  9/25/2019  BCJ 
BLD - Drywall Inspection  9/24/2019 3:18:23 PM  9/25/2019  12 PM - 3 PM  9/25/2019  BCJ 
ELE - Rough Electrical  9/24/2019 3:18:50 PM  9/25/2019  12 PM - 3 PM  9/25/2019  BCJ 
BLD - Drywall Inspection  9/25/2019 5:07:25 PM  9/26/2019  12 PM - 3 PM  9/26/2019  BCJ 
BLD - Drywall Inspection  9/26/2019 6:09:02 PM  9/27/2019  12 PM - 3 PM  9/27/2019  BCJ 
BLD - Exterior Lath Insp  9/26/2019 6:09:25 PM  9/27/2019  12 PM - 3 PM  9/27/2019  BCJ 
BLD - Drywall Inspection  10/1/2019 3:04:13 PM  10/2/2019  12 PM - 3 PM  10/2/2019  BCJ 
BLD - Exterior Brown Coat Insp  10/1/2019 3:05:15 PM  10/2/2019  12 PM - 3 PM  10/2/2019  BCJ 
Route to Planning Zoning  10/9/2019  10/23/2019    11/7/2019  APPR  EYT 
Approved by Planning Zoning  10/9/2019      11/7/2019 1:41:32 PM  APPR  EYT 
Approved Revision Structural  10/9/2019      1/14/2020  DONE  BVD 
Route Revision Structural  10/9/2019  10/23/2019    10/14/2019  CORR  BVD 
Approved Revision Mechanical        10/22/2019  APPR  EWC 
Route Revision Mechanical  10/9/2019  10/23/2019    10/22/2019  APPR  EWC 
Approved Revision Electrical        10/17/2019  APPR  MCS 
Route Revision Electrical  10/9/2019  10/23/2019    10/17/2019  APPR  MCS 
ELE - Rough Electrical  10/21/2019 4:24:08 PM  10/22/2019  12 PM - 3 PM  10/22/2019  BCJ 
ELE - Rough Electrical  10/22/2019  10/23/2019  12 PM - 3 PM  10/23/2019  BCJ 
BLD - Framing Insp.  11/14/2019 1:46:28 PM  11/15/2019  12 PM - 3 PM  11/15/2019  BCJ 
BLD - Drywall Inspection  11/18/2019 2:11:44 PM  11/19/2019  12 PM - 3 PM  11/19/2019  BCJ 
ELE - Rough Electrical  11/18/2019 2:13:28 PM  11/19/2019  12 PM - 3 PM  11/19/2019  BCJ 
BLD - Framing Insp.  11/19/2019 3:24:19 PM  11/20/2019  12 PM - 3 PM  11/20/2019  BCJ 
BLD - Drywall Inspection  11/19/2019 3:24:39 PM  11/20/2019  12 PM - 3 PM  11/20/2019  BCJ 
BLD - Drywall Inspection  12/4/2019 2:34:45 PM  12/5/2019  10 AM - 2 PM  12/5/2019  BCJ 
BLD - TCO App Consideration  1/7/2020  1/8/2020  12 PM - 3 PM  1/8/2020  BCJ 
Plumbing Final Insp Request  1/8/2020 3:53:27 PM  1/9/2020  10 AM - 2 PM  1/9/2020  BCJ 
BLD - Exterior Lath Insp  1/8/2020 3:55:16 PM  1/9/2020  10 AM - 2 PM  1/9/2020  BCJ 
Plumbing Final        1/9/2020    BCJ 
Route Revision Structural  1/14/2020  1/29/2020    1/14/2020  APPR  BVD 
BLD - Exterior Brown Coat Insp  1/30/2020 2:39:01 PM  1/31/2020  10 AM - 2 PM  1/31/2020  BCJ 
Electrical Final Insp Request  1/30/2020 2:39:37 PM  1/31/2020  10 AM - 2 PM  1/31/2020  BCJ 
Electrical Final        1/31/2020    BCJ 
Mechanical Final Insp Request  2/3/2020 9:36:48 AM  2/4/2020  12 PM - 3 PM  2/4/2020  BCJ 
Mechanical Final        2/4/2020    BCJ 
Building Final Insp Request  2/13/2020 3:17:06 PM  2/14/2020  12 PM - 3 PM  2/14/2020  BCJ 
Mechanical Final Insp Request  2/13/2020  2/14/2020  12 PM - 3 PM  2/14/2020  BCJ 
Building Final        2/14/2020    BCJ 
Planning GIS - Building Change  2/14/2020 3:27:36 PM      2/20/2020  DONE  MAR3 

 