Home Status Help

View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2018-00392     Status:   Finaled     Map Info:   1313 S HARBOR BLVD
Name:  BOMEL CONSTRUCTION CO INC
Address: 1313 S HARBOR
Received Date: 01/30/2018 
Parcel: 08219019 
Plan Check Date:  
Issue Date: 02/13/2018 
Expiration Date: 02/13/2019 
Finaled Date: 03/09/2018 
Description: Disney - BOH / Frontierland - Tenant Improvement: Install 8' x 18' poured in place pad for duplex 40 HP compressors, high pressure filtration, (1) direct fill post, (3) emergency shut down buttons, (2) 100a disconnect switches to fuel existing tram station.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Struct/Architectual  1/30/2018  2/6/2018    2/5/2018  CORR  BVD 
Apprv. by Struct/Architectural  1/30/2018      2/13/2018 10:15:14 AM  APPR  MCE 
Route to Planning Zoning  1/30/2018  2/6/2018    2/1/2018  APPR  EYT 
Approved by Planning Zoning  1/30/2018      2/1/2018 1:47:49 PM  APPR  EYT 
Approved by Addressing  1/30/2018      2/2/2018 9:58:37 AM  APPR  HXN 
Route to Addressing  1/30/2018  2/6/2018    2/2/2018  APPR  HXN 
Route to Elec Engineering  1/30/2018  2/6/2018    2/1/2018  APPR  NEG 
Approved by Fire Department  1/30/2018      2/6/2018 10:48:18 AM  APPR  408 
Route to Fire Department  1/30/2018  2/6/2018    2/6/2018  APPR  408 
Approved by Mechanical  1/30/2018      2/6/2018 11:39:43 AM  NR  GAQ 
Route to Mechanical  1/30/2018  2/6/2018    2/6/2018  NR  GAQ 
Approved by Plumbing  1/30/2018      2/6/2018 11:40:11 AM  NR  GAQ 
Route to Plumbing  1/30/2018  2/6/2018    2/6/2018  NR  GAQ 
Apprv. by PW Develop. Services  1/30/2018      2/5/2018 1:18:27 PM  APPR  SXA 
Route to PW Develop. Services  1/30/2018  2/6/2018    2/5/2018  APPR  SXA 
Approved by Water Engineering  1/30/2018      2/5/2018 4:16:29 PM  APPR  DRS 
Route to Water Engineering  1/30/2018  2/5/2018    2/5/2018  APPR  DRS 
Route to Electrical  1/30/2018  2/6/2018    2/6/2018  APPR  MCS 
Approved by Electrical  1/30/2018      2/6/2018 7:57:59 AM  APPR  MCS 
Inspection by Fire Department  2/6/2018  2/13/2018    3/8/2018  DONE  638 
Route to Struct/Architectual  2/8/2018  2/15/2018    2/13/2018  APPR  BVD 
BLD - Pre-Slab Insp  2/13/2018 1:07:48 PM  2/14/2018  10 AM - 2 PM  2/14/2018  BEN 
MEC - Gas Test  2/13/2018 1:10:53 PM  2/14/2018  10 AM - 2 PM  2/14/2018  BEN 
ELE - Rough Electrical  2/20/2018  2/20/2018  10 AM - 2 PM  2/20/2018  GCT 
MEC - Gas Test  2/21/2018 3:00:51 PM  2/22/2018  10 AM - 2 PM  2/22/2018  BEN 
ELE - Rough Electrical  2/21/2018 3:02:01 PM  2/22/2018  10 AM - 2 PM  2/22/2018  BEN 
MEC - Gas Test  2/27/2018 4:46:05 PM  2/28/2018    2/28/2018  BEN 
ELE - Ground Electrode/UFER  2/27/2018 4:47:32 PM  2/28/2018    2/28/2018  BEN 
ELE - Rough Electrical  2/27/2018 4:48:24 PM  2/28/2018    2/28/2018  BEN 
ELE - Rough Electrical  2/28/2018 2:44:16 PM  3/1/2018  8 AM - 12 PM  3/1/2018  BEN 
Gas Utility Release  3/1/2018  3/2/2018    3/1/2018  DONE  TJD 
Electrical Final Insp Request  3/6/2018 3:53:25 PM  3/9/2018    3/9/2018  BEN 
Mechanical Final Insp Request  3/6/2018 3:53:59 PM  3/9/2018    3/9/2018  BEN 
Approved Revision Electrical        3/8/2018  APPR  MCS 
Building Final Insp Request  3/8/2018 3:57:18 PM  3/9/2018    3/9/2018  BEN 
Electrical Final        3/9/2018    BEN 
Mechanical Final        3/9/2018    BEN 
Building Final        3/9/2018    BEN 

 


Back to Search
Help Top of Page