Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Approved by Elec Engineering  |
11/14/2017  |
  |
  |
11/30/2017 9:05:16 AM  |
APPR  |
NEG  |
Route to Elec Engineering  |
11/14/2017  |
11/30/2017  |
  |
11/30/2017  |
APPR  |
NEG  |
Approved by Fire Department  |
11/14/2017  |
  |
  |
12/5/2017 11:13:46 AM  |
APPR  |
408  |
Route to Fire Department  |
11/14/2017  |
11/30/2017  |
  |
12/5/2017  |
APPR  |
408  |
Route to Electrical  |
11/14/2017  |
11/30/2017  |
  |
11/28/2017  |
APPR  |
MCS  |
Approved by Planning Zoning  |
11/14/2017  |
  |
  |
11/27/2017 2:03:59 PM  |
APPR  |
EYT  |
Route to Planning Zoning  |
11/14/2017  |
11/30/2017  |
  |
11/27/2017  |
APPR  |
EYT  |
Approved by Plumbing  |
11/14/2017  |
  |
  |
11/30/2017  |
APPR  |
GAQ  |
Route to Plumbing  |
11/14/2017  |
11/30/2017  |
  |
11/30/2017  |
APPR  |
GAQ  |
Apprv. by PW Develop. Services  |
11/14/2017  |
  |
  |
1/10/2018 2:02:52 PM  |
APPR  |
SXA  |
Route to PW Develop. Services  |
11/14/2017  |
11/30/2017  |
  |
12/6/2017  |
CORR  |
SXA  |
Apprv. by Struct/Architectural  |
11/14/2017  |
  |
  |
12/21/2017 3:38:16 PM  |
APPR  |
BVD  |
Route to Struct/Architectual  |
11/14/2017  |
11/30/2017  |
  |
11/28/2017  |
CORR  |
BVD  |
Approved by Traffic Eng.  |
11/14/2017  |
  |
  |
12/1/2017 4:23:08 PM  |
APPR  |
RXC  |
Route to Traffic Engineering  |
11/14/2017  |
11/30/2017  |
  |
12/1/2017  |
APPR  |
RXC  |
Approved by Water Engineering  |
11/14/2017  |
  |
  |
11/30/2017 4:46:25 PM  |
APPR  |
DRS  |
Route to Water Engineering  |
11/14/2017  |
11/30/2017  |
  |
11/30/2017  |
APPR  |
DRS  |
Route To CalGreen  |
11/14/2017  |
11/30/2017  |
  |
11/28/2017  |
CORR  |
BVD  |
Approved By CalGreen  |
11/14/2017  |
  |
  |
12/21/2017  |
APPR  |
BVD  |
Route to Mechanical  |
11/14/2017  |
11/30/2017  |
  |
11/30/2017  |
APPR  |
GAQ  |
Approved by Mechanical  |
11/30/2017  |
  |
  |
11/30/2017  |
APPR  |
GAQ  |
Inspection by Fire Department  |
12/5/2017  |
12/19/2017  |
  |
3/5/2018  |
DONE  |
638  |
FIRE - Create BFP case  |
12/5/2017  |
  |
  |
12/5/2017  |
DONE  |
408  |
Route to Struct/Architectual  |
12/21/2017  |
1/8/2018  |
  |
12/21/2017  |
APPR  |
BVD  |
Route To CalGreen  |
12/21/2017  |
1/8/2018  |
  |
12/21/2017  |
APPR  |
BVD  |
Route to PW Develop. Services  |
12/21/2017  |
1/8/2018  |
  |
1/10/2018  |
APPR  |
SXA  |
Route to Planning Zoning  |
1/17/2018  |
1/31/2018  |
  |
1/26/2018  |
APPR  |
EYT  |
Approved by Planning Zoning  |
1/17/2018  |
  |
  |
1/26/2018 3:24:44 PM  |
APPR  |
EYT  |
Approved Revision Structural  |
1/17/2018  |
  |
  |
1/26/2018  |
APPR  |
BVD  |
Route Revision Structural  |
1/17/2018  |
1/31/2018  |
  |
1/23/2018  |
APPR  |
BVD  |
BLD - Reinforcing Insp  |
2/14/2018 7:46:31 AM  |
2/15/2018  |
10 AM - 2 PM  |
2/15/2018  |
P  |
BEN  |
BLD - Reinforcing Insp  |
2/19/2018  |
2/20/2018  |
  |
2/20/2018  |
P  |
GCT  |
BLD - Framing Insp.  |
2/21/2018 4:54:04 AM  |
2/22/2018  |
8 AM - 12 PM  |
2/22/2018  |
P  |
GCT  |
BLD - Reinforcing Insp  |
2/21/2018  |
2/21/2018  |
  |
2/21/2018  |
P  |
GCT  |
Approved by Bus Lic (Sub List)  |
2/22/2018  |
2/22/2018  |
  |
2/28/2018  |
APPR  |
RHZ  |
Building Final Insp Request  |
3/6/2018 12:01:11 PM  |
3/7/2018  |
10 AM - 2 PM  |
3/7/2018  |
NA  |
GCT  |
Building Final Insp Request  |
3/7/2018 2:34:37 PM  |
3/8/2018  |
8 AM - 12 PM  |
3/8/2018  |
N  |
GCT  |
Building Final Insp Request  |
3/8/2018 10:30:10 AM  |
3/9/2018  |
8 AM - 12 PM  |
3/9/2018  |
A  |
BEN  |
Building Final  |
  |
  |
  |
3/9/2018  |
  |
BEN  |