Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Approved by Electrical  |
11/8/2017  |
  |
  |
11/9/2017 7:24:57 AM  |
APPR  |
MCS  |
Route to Electrical  |
11/8/2017  |
11/16/2017  |
  |
11/9/2017  |
APPR  |
MCS  |
Approved by Elec Engineering  |
11/8/2017  |
  |
  |
11/15/2017 8:57:39 AM  |
APPR  |
JJB  |
Route to Elec Engineering  |
11/8/2017  |
11/22/2017  |
  |
11/15/2017  |
APPR  |
JJB  |
Route to Fire Department  |
11/8/2017  |
11/16/2017  |
  |
11/20/2017  |
NR  |
408  |
Approved by Fire Department  |
11/8/2017  |
  |
  |
11/20/2017 11:03:24 AM  |
NR  |
408  |
Route to Water Engineering  |
11/8/2017  |
11/22/2017  |
  |
11/21/2017  |
APPR  |
DRS  |
Approved by Water Engineering  |
11/8/2017  |
  |
  |
11/21/2017 3:30:12 PM  |
APPR  |
DRS  |
Route to Traffic Engineering  |
11/8/2017  |
11/22/2017  |
  |
12/1/2017  |
APPR  |
RXC  |
Approved by Traffic Eng.  |
11/8/2017  |
  |
  |
12/1/2017 11:25:08 AM  |
APPR  |
RXC  |
Route to Addressing  |
11/8/2017  |
11/16/2017  |
  |
11/8/2017  |
APPR  |
HXN  |
Approved by Addressing  |
11/8/2017  |
  |
  |
11/8/2017 12:20:02 PM  |
APPR  |
HXN  |
Approved by Plumbing  |
11/8/2017  |
  |
  |
11/16/2017 4:37:31 PM  |
APPR  |
GAQ  |
Route to Plumbing  |
11/8/2017  |
11/16/2017  |
  |
11/16/2017  |
APPR  |
GAQ  |
Apprv. by PW Develop. Services  |
11/8/2017  |
  |
  |
12/4/2017 5:47:11 PM  |
NR  |
SXA  |
Route to PW Develop. Services  |
11/8/2017  |
11/16/2017  |
  |
12/4/2017  |
NR  |
SXA  |
Apprv. by Struct/Architectural  |
11/8/2017  |
  |
  |
11/15/2017 8:27:12 AM  |
APPR  |
WCL  |
Route to Struct/Architectual  |
11/8/2017  |
11/16/2017  |
  |
11/15/2017  |
APPR  |
WCL  |
Approved by Planning Zoning  |
11/8/2017  |
  |
  |
11/27/2017 2:06:23 PM  |
APPR  |
EYT  |
Route to Planning Zoning  |
11/8/2017  |
11/16/2017  |
  |
11/27/2017  |
APPR  |
EYT  |
Route Revision Plumbing  |
3/30/2018  |
4/6/2018  |
  |
4/9/2018  |
NR  |
GAQ  |
Approved Revision Plumbing  |
3/30/2018  |
  |
  |
4/9/2018  |
NA  |
GAQ  |
Approved Revision Structural  |
3/30/2018  |
  |
  |
4/11/2018  |
APPR  |
WCL  |
Route Revision Structural  |
3/30/2018  |
4/6/2018  |
  |
4/4/2018  |
APPR  |
WCL  |
Approved Revision Electrical  |
3/30/2018  |
  |
  |
4/11/2018  |
DONE  |
MCS  |
Route Revision Electrical  |
3/30/2018  |
4/6/2018  |
  |
4/4/2018  |
APPR  |
MCS  |
Approved by Planning Zoning  |
3/30/2018  |
  |
  |
3/30/2018 10:02:44 AM  |
APPR  |
EYT  |
Route to Planning Zoning  |
3/30/2018  |
4/6/2018  |
  |
3/30/2018  |
APPR  |
EYT  |
Approved Revision Electrical  |
  |
  |
  |
5/8/2018  |
APPR  |
MCS  |
Route Revision Electrical  |
5/2/2018  |
5/9/2018  |
  |
5/8/2018  |
APPR  |
MCS  |
BLD - Reinforcing Insp  |
5/4/2018 7:49:42 AM  |
5/7/2018  |
  |
7/12/2018  |
NA  |
MMO  |
ELE - Underground conduit  |
5/7/2018  |
5/8/2018  |
8 AM - 12 PM  |
5/8/2018  |
P  |
GCT  |
BLD - Reinforcing Insp  |
5/8/2018 11:12:37 AM  |
5/9/2018  |
10 AM - 2 PM  |
5/9/2018  |
A  |
BEN  |
Approved Revision Electrical  |
  |
  |
  |
5/10/2018  |
APPR  |
MCS  |
Route Revision Electrical  |
5/10/2018  |
5/17/2018  |
  |
5/10/2018  |
APPR  |
MCS  |
Approved Revision Electrical  |
  |
  |
  |
5/10/2018  |
DONE  |
CMN  |
Route Revision Electrical  |
5/10/2018  |
5/17/2018  |
  |
5/10/2018  |
APPR  |
MCS  |
Building Final Insp Request  |
5/18/2018 11:55:50 AM  |
5/21/2018  |
10 AM - 2 PM  |
7/12/2018  |
N  |
MMO  |
Electrical Final Insp Request  |
5/18/2018 11:59:06 AM  |
5/21/2018  |
10 AM - 2 PM  |
5/21/2018  |
N  |
GCT  |
Electrical Final Insp Request  |
5/21/2018 3:02:15 PM  |
5/22/2018  |
10 AM - 2 PM  |
5/22/2018  |
C  |
BEN  |
Building Final Insp Request  |
5/21/2018 3:02:56 PM  |
5/22/2018  |
10 AM - 2 PM  |
5/22/2018  |
C  |
BEN  |
Electrical Final Insp Request  |
5/21/2018  |
5/22/2018  |
10 AM - 2 PM  |
5/22/2018  |
N  |
GCT  |
Electrical Final Insp Request  |
5/22/2018 3:17:38 PM  |
5/23/2018  |
12 PM - 3 PM  |
5/23/2018  |
C  |
MAT  |
Building Final Insp Request  |
5/22/2018 3:17:55 PM  |
5/23/2018  |
12 PM - 3 PM  |
5/23/2018  |
C  |
MAT  |
Building Final Insp Request  |
5/23/2018  |
5/23/2018  |
  |
5/23/2018  |
A  |
GCT  |
Electrical Final Insp Request  |
5/23/2018  |
5/23/2018  |
  |
5/23/2018  |
A  |
GCT  |
Approved by Bus Lic (Sub List)  |
5/25/2018  |
  |
  |
5/25/2018  |
APPR  |
CSL  |
Electrical Final  |
  |
  |
  |
5/25/2018  |
  |
GCT  |
Building Final  |
  |
  |
  |
5/25/2018  |
  |
GCT  |