Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Approved by Bus Lic (Sub List)  |
9/27/2017  |
1/14/2019  |
  |
1/16/2019  |
APPR  |
CSL  |
Approved by Elec Engineering  |
9/27/2017  |
  |
  |
9/28/2017 9:28:17 AM  |
APPR  |
NEG  |
Route to Elec Engineering  |
9/27/2017  |
10/13/2017  |
  |
9/28/2017  |
APPR  |
NEG  |
Approved by Fire Department  |
9/27/2017  |
  |
  |
10/18/2017 11:24:44 AM  |
APPR  |
408  |
Route to Fire Department  |
9/27/2017  |
10/13/2017  |
  |
10/18/2017  |
APPR  |
408  |
Route to Mechanical  |
9/27/2017  |
10/13/2017  |
  |
10/13/2017  |
APPR  |
GAQ  |
Approved by Mechanical  |
9/27/2017  |
  |
  |
10/13/2017 4:34:28 PM  |
APPR  |
GAQ  |
Approved by Electrical  |
9/27/2017  |
  |
  |
10/11/2017 10:10:24 AM  |
APPR  |
MCS  |
Route to Electrical  |
9/27/2017  |
10/13/2017  |
  |
10/11/2017  |
APPR  |
MCS  |
Approved by Addressing  |
9/27/2017  |
  |
  |
9/29/2017 9:15:34 AM  |
APPR  |
HXN  |
Route to Addressing  |
9/27/2017  |
10/13/2017  |
  |
9/29/2017  |
APPR  |
HXN  |
Approved by Planning Zoning  |
9/27/2017  |
  |
  |
9/29/2017 9:35:36 AM  |
APPR  |
EYT  |
Route to Planning Zoning  |
9/27/2017  |
10/13/2017  |
  |
9/29/2017  |
APPR  |
EYT  |
Approved by Plumbing  |
9/27/2017  |
  |
  |
10/13/2017 4:34:16 PM  |
APPR  |
GAQ  |
Route to Plumbing  |
9/27/2017  |
10/13/2017  |
  |
10/13/2017  |
APPR  |
GAQ  |
Apprv. by Struct/Architectural  |
9/27/2017  |
  |
  |
10/16/2017 3:15:51 PM  |
APPR  |
CSG  |
Route to Struct/Architectual  |
9/27/2017  |
10/13/2017  |
  |
10/16/2017  |
APPR  |
CSG  |
Inspection by Fire Department  |
10/18/2017  |
11/3/2017  |
  |
3/4/2019  |
DONE  |
638  |
Route to Planning Zoning  |
3/14/2018  |
3/30/2018  |
  |
3/19/2018  |
APPR  |
EYT  |
Route to Struct/Architectual  |
3/14/2018  |
3/30/2018  |
  |
3/20/2018  |
CORR  |
CSG  |
Approved by Planning Zoning  |
3/14/2018  |
  |
  |
3/19/2018  |
APPR  |
EYT  |
Apprv. by Struct/Architectural  |
3/14/2018  |
  |
  |
4/19/2018  |
APPR  |
CSG  |
Route to Struct/Architectual  |
4/19/2018  |
5/7/2018  |
  |
4/19/2018  |
APPR  |
CSG  |
Route to Struct/Architectual  |
7/16/2018  |
8/1/2018  |
  |
7/18/2018  |
CORR  |
CSG  |
Route to Planning Zoning  |
7/16/2018  |
8/1/2018  |
  |
7/24/2018  |
APPR  |
EYT  |
Approved by Planning Zoning  |
7/16/2018  |
  |
  |
7/24/2018 9:04:15 AM  |
APPR  |
EYT  |
Route to Fire Department  |
7/16/2018  |
8/1/2018  |
  |
8/1/2018  |
NR  |
408  |
Approved by Fire Department  |
7/16/2018  |
  |
  |
8/1/2018 10:47:34 AM  |
NR  |
408  |
BLD - Framing Insp.  |
8/9/2018  |
8/10/2018  |
12 PM - 3 PM  |
8/10/2018  |
P  |
BEN  |
Route to Struct/Architectual  |
8/24/2018  |
9/12/2018  |
  |
8/24/2018  |
APPR  |
CSG  |
BLD - Framing Insp.  |
9/21/2018 7:20:43 AM  |
9/24/2018  |
8 AM - 12 PM  |
9/24/2018  |
P  |
PJJ  |
BLD - Framing Insp.  |
10/29/2018 7:32:06 AM  |
10/30/2018  |
12 PM - 3 PM  |
10/30/2018  |
C  |
BEN  |
BLD - Framing Insp.  |
10/30/2018 1:01:02 PM  |
10/31/2018  |
12 PM - 3 PM  |
10/31/2018  |
C  |
BEN  |
BLD - Framing Insp.  |
11/7/2018 2:01:04 PM  |
11/8/2018  |
8 AM - 12 PM  |
11/8/2018  |
P  |
PJJ  |
BLD - Framing Insp.  |
2/21/2019 1:56:46 PM  |
2/22/2019  |
8 AM - 12 PM  |
2/22/2019  |
C  |
BEN  |
BLD - Framing Insp.  |
2/24/2019 12:15:52 PM  |
2/25/2019  |
10 AM - 2 PM  |
2/25/2019  |
C  |
PJJ  |
BLD - Framing Insp.  |
2/25/2019 1:50:14 PM  |
2/26/2019  |
12 PM - 3 PM  |
2/26/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
2/26/2019 12:18:56 PM  |
2/27/2019  |
12 PM - 3 PM  |
2/27/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
3/3/2019 2:02:03 PM  |
3/4/2019  |
10 AM - 2 PM  |
3/4/2019  |
C  |
PJJ  |
Building Final Insp Request  |
3/4/2019 9:47:41 AM  |
3/5/2019  |
12 PM - 3 PM  |
3/5/2019  |
N  |
BEN  |
Building Final Insp Request  |
3/5/2019 12:19:40 PM  |
3/6/2019  |
12 PM - 3 PM  |
3/6/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/6/2019 11:27:23 AM  |
3/7/2019  |
12 PM - 3 PM  |
3/7/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/7/2019 1:24:51 PM  |
3/8/2019  |
10 AM - 2 PM  |
3/8/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/8/2019 10:08:41 AM  |
3/11/2019  |
8 AM - 12 PM  |
3/11/2019  |
C  |
PJJ  |
BLD - Framing Insp.  |
3/11/2019 2:49:16 PM  |
3/12/2019  |
12 PM - 3 PM  |
3/12/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/11/2019 2:49:27 PM  |
3/12/2019  |
12 PM - 3 PM  |
3/12/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/12/2019 2:11:04 PM  |
3/13/2019  |
12 PM - 3 PM  |
3/13/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/13/2019 1:15:54 PM  |
3/14/2019  |
8 AM - 12 PM  |
3/14/2019  |
C  |
BEN  |
Building Final Insp Request  |
3/14/2019 10:05:52 AM  |
3/15/2019  |
  |
3/15/2019  |
A  |
BEN  |
Building Final  |
  |
  |
  |
3/15/2019  |
  |
BEN  |