Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Approved by Bus Lic (Sub List)  |
9/19/2017  |
4/11/2018  |
  |
4/18/2018  |
APPR  |
RHZ  |
Route to Electrical  |
9/19/2017  |
9/26/2017  |
  |
9/20/2017  |
APPR  |
MCS  |
Approved by Electrical  |
9/19/2017  |
  |
  |
9/20/2017 11:50:23 AM  |
APPR  |
MCS  |
Approved by Elec Engineering  |
9/19/2017  |
  |
  |
9/21/2017 3:31:51 PM  |
APPR  |
CMK  |
Route to Elec Engineering  |
9/19/2017  |
9/26/2017  |
  |
9/21/2017  |
APPR  |
CMK  |
Approved by Fire Department  |
9/19/2017  |
  |
  |
9/27/2017 10:40:35 AM  |
NR  |
408  |
Route to Fire Department  |
9/19/2017  |
9/26/2017  |
  |
9/27/2017  |
NR  |
408  |
Approved by Planning Zoning  |
9/19/2017  |
  |
  |
9/29/2017  |
APPR  |
EYT  |
Route to Planning Zoning  |
9/19/2017  |
9/26/2017  |
  |
9/29/2017  |
APPR  |
EYT  |
Apprv. by PW Develop. Services  |
9/19/2017  |
  |
  |
9/28/2017 7:58:21 AM  |
APPR  |
SXA  |
Route to PW Develop. Services  |
9/19/2017  |
9/26/2017  |
  |
9/28/2017  |
APPR  |
SXA  |
Apprv. by Struct/Architectural  |
9/19/2017  |
  |
  |
10/12/2017 3:17:43 PM  |
APPR  |
CSG  |
Route to Struct/Architectual  |
9/19/2017  |
9/26/2017  |
  |
9/22/2017  |
CORR  |
CSG  |
Route to Traffic Engineering  |
9/19/2017  |
9/26/2017  |
  |
9/28/2017  |
NR  |
RXC  |
Approved by Traffic Eng.  |
9/19/2017  |
  |
  |
9/28/2017 1:16:03 PM  |
NR  |
RXC  |
Approved by Water Engineering  |
9/19/2017  |
  |
  |
9/27/2017 5:15:30 PM  |
APPR  |
DRS  |
Route to Water Engineering  |
9/19/2017  |
9/26/2017  |
  |
9/27/2017  |
APPR  |
DRS  |
Route to Struct/Architectual  |
10/9/2017  |
10/16/2017  |
  |
10/12/2017  |
APPR  |
CSG  |
BLD - Reinforcing Insp  |
12/28/2017 2:04:57 PM  |
12/29/2017  |
8 AM - 12 PM  |
12/29/2017  |
N  |
BEN  |
BLD - Footings Insp  |
12/28/2017 2:05:08 PM  |
12/29/2017  |
8 AM - 12 PM  |
12/29/2017  |
N  |
BEN  |
BLD - Pre-Slab Insp  |
12/28/2017 2:05:16 PM  |
12/29/2017  |
8 AM - 12 PM  |
12/29/2017  |
N  |
BEN  |
BLD - Footings Insp  |
12/29/2017 10:33:10 AM  |
1/2/2018  |
8 AM - 12 PM  |
1/2/2018  |
P  |
GCT  |
BLD - Reinforcing Insp  |
12/29/2017 10:33:25 AM  |
1/2/2018  |
8 AM - 12 PM  |
1/2/2018  |
P  |
GCT  |
BLD - Pre-Slab Insp  |
12/29/2017 10:33:41 AM  |
1/2/2018  |
8 AM - 12 PM  |
1/2/2018  |
P  |
GCT  |
Approved Revision Structural  |
2/14/2018  |
  |
  |
2/14/2018  |
APPR  |
CSG  |
Route Revision Structural  |
2/14/2018  |
2/22/2018  |
  |
2/14/2018  |
APPR  |
CSG  |
BLD - Reinforcing Insp  |
2/28/2018 1:42:23 PM  |
3/1/2018  |
8 AM - 12 PM  |
3/1/2018  |
P  |
BEN  |
BLD - Reinforcing Insp  |
4/10/2018 1:05:24 PM  |
4/11/2018  |
8 AM - 12 PM  |
4/11/2018  |
F  |
BEN  |
Electrical Final Insp Request  |
4/13/2018 1:25:37 PM  |
4/17/2018  |
8 AM - 12 PM  |
4/17/2018  |
A  |
BEN  |
Electrical Final  |
  |
  |
  |
4/17/2018  |
  |
BEN  |
Electrical Final Insp Request  |
4/20/2018 8:15:37 AM  |
4/23/2018  |
8 AM - 12 PM  |
4/23/2018  |
A  |
GCT  |
Building Final Insp Request  |
4/20/2018 8:15:52 AM  |
4/23/2018  |
8 AM - 12 PM  |
4/23/2018  |
A  |
GCT  |
Electrical Final  |
  |
  |
  |
4/23/2018  |
  |
GCT  |
Building Final  |
  |
  |
  |
4/23/2018  |
  |
GCT  |