View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2017-02927     Status:   Finaled     Map Info:   1570 S DISNEYLAND DR 101
Name:  THE HATCH GROUP INC
Address: 1570 S DISNEYLAND 101
Received Date: 07/13/2017 
Parcel: 08219027 
Plan Check Date:  
Issue Date: 09/01/2017 
Expiration Date: 09/01/2018 
Finaled Date: 11/30/2017 
Description: Downtown Disney - Building H/unit 101 - Sephora - Tenant Improvement: Exterior facade renovation stone veener s.ft 70, new awning, and new interior electrical. "Sephora" 

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Approved by Bus Lic (Sub List)  7/17/2017  11/27/2017    11/27/2017  APPR  AMJ 
Approved by Elec Engineering  7/17/2017      7/28/2017 11:22:29 AM  APPR  JJB 
Approved by Fire Department  7/17/2017      7/31/2017 2:11:04 PM  APPR  408 
Approved by Electrical  7/17/2017      8/9/2017  APPR  MCS 
Approved by Planning Zoning  7/17/2017      8/2/2017  APPR  EYT 
Apprv. by Struct/Architectural  7/17/2017      8/24/2017 3:29:50 PM  APPR  ZID 
Route to Elec Engineering  7/17/2017  7/31/2017    7/28/2017  APPR  JJB 
Route to Electrical  7/17/2017  7/24/2017    7/21/2017  CORR  MCS 
Route to Fire Department  7/17/2017  7/31/2017    7/31/2017  APPR  408 
Route to Planning Zoning  7/17/2017  7/31/2017    8/2/2017  APPR  EYT 
Route to Struct/Architectual  7/17/2017  7/24/2017    7/24/2017  CORR  ZID 
FIRE - Create BFP case  7/31/2017      7/31/2017  DONE  408 
Inspection by Fire Department  7/31/2017  8/7/2017    11/9/2017  DONE  638 
Route to Electrical  8/9/2017  8/16/2017    8/9/2017  APPR  MCS 
Route to Struct/Architectual  8/23/2017  8/30/2017    8/24/2017  APPR  ZID 
Route to Electrical  8/23/2017  8/30/2017    8/30/2017  APPR  MCS 
ELE - Underground conduit  9/11/2017  9/12/2017  10 AM - 2 PM  9/12/2017  BCJ 
ELE - Rough Electrical  9/14/2017  9/15/2017  10 AM - 2 PM  9/15/2017  RJC 
BLD - Framing Insp.  9/14/2017  9/15/2017  10 AM - 2 PM  9/15/2017  RJC 
BLD - Framing Insp.  9/15/2017  9/18/2017  8 AM - 12 PM  9/18/2017  EGA 
ELE - Rough Electrical  9/15/2017  9/18/2017  8 AM - 12 PM  9/18/2017  EGA 
BLD - Framing Insp.  9/18/2017  9/19/2017  10 AM - 2 PM  9/19/2017  BEN 
ELE - Rough Electrical  9/18/2017  9/19/2017  10 AM - 2 PM  9/19/2017  BEN 
ELE - Rough Electrical  9/19/2017  9/20/2017    9/20/2017  BEN 
ELE - Underground conduit  9/19/2017  9/20/2017    9/20/2017  BEN 
BLD - Framing Insp.  9/19/2017  9/20/2017    9/20/2017  BEN 
ELE - Underground conduit  9/20/2017  9/21/2017  10 AM - 2 PM  9/21/2017  BCJ 
BLD - Framing Insp.  9/20/2017  9/21/2017  10 AM - 2 PM  9/21/2017  BCJ 
BLD - Framing Insp.  9/21/2017  9/22/2017  8 AM - 12 PM  9/22/2017  WJJ 
BLD - Framing Insp.  9/22/2017  9/25/2017  10 AM - 2 PM  9/25/2017  JOS 
Route Revision Structural  9/28/2017  10/5/2017    10/2/2017  APPR  ZID 
Approved Revision Structural  9/28/2017      10/5/2017  APPR  ZID 
BLD - Framing Insp.  10/2/2017  10/3/2017  8 AM - 12 PM  10/3/2017  BCJ 
BLD - Drywall Inspection  10/2/2017  10/3/2017  8 AM - 12 PM  10/3/2017  BCJ 
BLD - Drywall Inspection  10/3/2017  10/4/2017  8 AM - 12 PM  10/4/2017  BCJ 
ELE - Rough Electrical  10/12/2017  10/13/2017  8 AM - 12 PM  10/13/2017  BCJ 
BLD - Framing Insp.  10/12/2017  10/13/2017  8 AM - 12 PM  10/13/2017  BCJ 
BLD - Framing Insp.  10/16/2017  10/17/2017  10 AM - 2 PM  10/17/2017  BCJ 
Route Revision Structural  10/18/2017  10/25/2017    10/23/2017  CORR  ZID 
ELE - Rough Electrical  10/19/2017  10/20/2017  10 AM - 2 PM  10/20/2017  BCJ 
ELE - Rough Electrical  10/23/2017  10/24/2017  10 AM - 2 PM  10/24/2017  BCJ 
Route Revision Structural  10/30/2017  11/6/2017    10/31/2017  APPR  ZID 
Approved Revision Structural  10/30/2017      11/29/2017  DONE  ZID 
Electrical Final Insp Request  11/9/2017  11/14/2017  8 AM - 12 PM  11/14/2017  BCJ 
Electrical Final Insp Request  11/9/2017  11/14/2017  8 AM - 12 PM  11/14/2017  BCJ 
Electrical Final        11/14/2017    BCJ 
Building Final Insp Request  11/29/2017  11/30/2017  8 AM - 12 PM  11/30/2017  BCJ 
Building Final        11/30/2017    BCJ 

 