View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2017-02850     Status:   Finaled     Map Info:   1313 S HARBOR BLVD
Name:  WALT DISNEY WORLD CO
Address: 1313 S HARBOR
Received Date: 07/10/2017 
Parcel: 08219019 
Plan Check Date:  
Issue Date: 08/31/2017 
Expiration Date: 09/04/2019 
Finaled Date: 07/26/2019 
Description: Disneyland - SW - DL Frontierland Expansion - Site Development includes items that encompass the area outside of the facility buildings. This includes 3,748 ln.ft x 6' high and 2,130 ln.ft x 10' high retaining walls and decorative walls, light poles, fan poles, covered queue of 1,571 s.ft. faux evaporators, 83 s,ft canopy for cardboard bailer, (2) free standing rockwork structures, (3) decorative faux tanks with 160 s.ft catwalks, (6) foundation only for show sets, (1) foundation only marque show set and landscape.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Struct/Architectual  7/10/2017  7/26/2017    7/25/2017  CORR  CSG 
Apprv. by Struct/Architectural  7/10/2017      8/30/2017 2:30:03 PM  APPR  CSG 
Route to Planning Zoning  7/10/2017  7/26/2017    8/25/2017  APPR  EYT 
Approved by Planning Zoning  7/10/2017      8/25/2017 2:28:08 PM  APPR  EYT 
Approved by Bus Lic (Sub List)  7/10/2017  4/4/2019    4/4/2019  APPR  RHZ 
Approved by Electrical  7/10/2017      7/25/2017 2:02:42 PM  APPR  MCS 
Route to Electrical  7/10/2017  7/26/2017    7/25/2017  APPR  MCS 
Approved by Elec Engineering  7/10/2017      7/28/2017 11:21:59 AM  APPR  JJB 
Route to Elec Engineering  7/12/2017  7/28/2017    7/28/2017  APPR  JJB 
Approved by Fire Department  7/10/2017      8/1/2017 2:38:52 PM  NR  408 
Route to Fire Department  7/10/2017  7/26/2017    8/1/2017  NR  408 
Approved by Mechanical  7/10/2017      7/26/2017  APPR  GAQ 
Route to Mechanical  7/10/2017  7/26/2017    7/26/2017  APPR  GAQ 
Approved by Plumbing  7/10/2017      7/26/2017  APPR  GAQ 
Route to Plumbing  7/10/2017  7/26/2017    7/26/2017  APPR  GAQ 
Apprv. by PW Develop. Services  7/10/2017      8/3/2017 2:44:02 PM  APPR  SXA 
Route to PW Develop. Services  7/11/2017  7/27/2017    8/3/2017  APPR  SXA 
Approved by Traffic Eng.  7/10/2017      7/28/2017 9:36:26 AM  APPR  RXC 
Route to Traffic Engineering  7/10/2017  7/26/2017    7/28/2017  APPR  RXC 
Route to Water Engineering  7/10/2017  7/26/2017    7/27/2017  APPR  HTQ 
Approved by Water Engineering  7/10/2017      7/27/2017 11:25:21 AM  APPR  HTQ 
Route to Struct/Architectual  8/30/2017  9/18/2017    8/30/2017  APPR  CSG 
BLD - Footings Insp  9/6/2017 3:14:48 PM  9/7/2017  8 AM - 12 PM  9/7/2017  BEN 
BLD - Underfloor Insulation   9/6/2017 3:16:24 PM  9/7/2017  8 AM - 12 PM  9/7/2017  BEN 
BLD - Footings Insp  9/10/2017 2:13:24 PM  9/11/2017    9/11/2017  JOS 
ELE - Underground conduit  9/20/2017 3:23:41 PM  9/21/2017  12 PM - 3 PM  9/21/2017  BEN 
ELE - Underground conduit  9/26/2017 2:26:34 PM  9/27/2017  8 AM - 12 PM  9/27/2017  BEN 
PLM - Gas Test  9/27/2017 1:41:18 PM  9/28/2017  8 AM - 12 PM  9/28/2017  JOS 
MEC - Gas Test  9/27/2017 1:41:29 PM  9/28/2017  8 AM - 12 PM  9/28/2017  JOS 
PLM - Underfloor Gas  9/28/2017 5:31:28 PM  9/29/2017  8 AM - 12 PM  9/29/2017  BEN 
PLM - Underground gas  9/29/2017 11:14:35 AM  10/2/2017  10 AM - 2 PM  10/2/2017  GCT 
Route to Elec Engineering  10/2/2017  10/18/2017    10/3/2017  APPR  JJB 
Approved by Fire Department  10/2/2017      10/23/2017 11:18:44 AM  APPR  408 
Route to Fire Department  10/2/2017  10/18/2017    10/23/2017  APPR  408 
Approved Revision Mechanical        10/19/2017  DONE  GAQ 
Route Revision Mechanical  10/2/2017  10/18/2017    10/19/2017  APPR  GAQ 
Approved by Planning Zoning  10/2/2017      10/20/2017 5:08:31 PM  APPR  EYT 
Route to Planning Zoning  10/2/2017  10/18/2017    10/20/2017  APPR  EYT 
BLD - Footings Insp  10/2/2017 3:27:34 PM  10/3/2017    10/3/2017  BEN 
Approved Revision Plumbing        10/19/2017  DONE  GAQ 
Route Revision Plumbing  10/2/2017  10/18/2017    10/19/2017  APPR  GAQ 
Apprv. by PW Develop. Services  10/2/2017      10/24/2017 9:53:09 AM  APPR  SXA 
Route to PW Develop. Services  10/2/2017  10/18/2017    10/24/2017  APPR  SXA 
Approved Revision Structural  10/2/2017      10/19/2017  APPR  CSG 
Route Revision Structural  10/2/2017  10/18/2017    10/19/2017  APPR  CSG 
Route to Traffic Engineering  10/2/2017  10/18/2017    10/23/2017  APPR  RXC 
Approved by Traffic Eng.  10/2/2017      10/23/2017 2:43:14 PM  APPR  RXC 
Approved by Water Engineering  10/2/2017      10/12/2017 3:21:40 PM  APPR  DRS 
Route to Water Engineering  10/2/2017  10/18/2017    10/12/2017  APPR  DRS 
Approved Revision Electrical        10/20/2017  APPR  MCS 
Route Revision Electrical  10/2/2017  10/18/2017    10/20/2017  APPR  MCS 
ELE - Underground conduit  10/2/2017 3:34:38 PM  10/3/2017    10/3/2017  BEN 
BLD - Footings Insp  10/3/2017 3:29:57 PM  10/4/2017    10/4/2017  BEN 
PLM - Water Service  10/4/2017 1:58:31 PM  10/5/2017    10/5/2017  BEN 
MEC - Underground Rough  10/4/2017 2:00:02 PM  10/5/2017    10/5/2017  BEN 
MEC - Underground Rough  10/5/2017 4:11:13 PM  10/6/2017  8 AM - 12 PM  10/6/2017  JOS 
PLM - Water Service  10/5/2017 4:11:44 PM  10/6/2017  8 AM - 12 PM  10/6/2017  JOS 
BLD - Footings Insp  10/5/2017 4:12:08 PM  10/6/2017  8 AM - 12 PM  10/6/2017  JOS 
ELE - Underground conduit  10/9/2017  10/9/2017    10/9/2017  GCT 
BLD - Footings Insp  10/9/2017 8:30:23 PM  10/10/2017    10/10/2017  BEN 
BLD - Footings Insp  10/10/2017 3:06:40 PM  10/11/2017    10/11/2017  BEN 
BLD - Footings Insp  10/11/2017 3:54:10 PM  10/12/2017    10/12/2017  BEN 
BLD - Footings Insp  10/13/2017 2:50:55 PM  10/16/2017  12 PM - 3 PM  10/16/2017  GCT 
ELE - Underground conduit  10/13/2017 2:51:09 PM  10/16/2017  12 PM - 3 PM  10/16/2017  GCT 
PLM - Sewer  10/16/2017 3:38:03 PM  10/17/2017  8 AM - 12 PM  10/17/2017  BCJ 
BLD - Footings Insp  10/16/2017 3:38:16 PM  10/17/2017  8 AM - 12 PM  10/17/2017  BCJ 
ELE - Underground conduit  10/16/2017 3:38:29 PM  10/17/2017  8 AM - 12 PM  10/17/2017  BCJ 
PLM - Ground/Underfloor waste  10/16/2017 4:05:32 PM  10/17/2017  8 AM - 12 PM  10/17/2017  BCJ 
PLM - Sewer  10/17/2017 6:24:06 PM  10/18/2017    10/18/2017  BEN 
PLM - Ground/Underfloor waste  10/17/2017 6:24:17 PM  10/18/2017    10/18/2017  BEN 
BLD - Footings Insp  10/17/2017 6:24:39 PM  10/18/2017    10/18/2017  BEN 
ELE - Underground conduit  10/17/2017 6:24:47 PM  10/18/2017    10/18/2017  BEN 
PLM - Sewer  10/18/2017 3:18:45 PM  10/19/2017  12 PM - 3 PM  10/19/2017  BEN 
ELE - Underground conduit  10/19/2017 1:02:53 PM  10/20/2017  12 PM - 3 PM  10/20/2017  BEN 
ELE - Ground Electrode/UFER  10/19/2017 1:03:27 PM  10/20/2017  12 PM - 3 PM  10/20/2017  BEN 
PLM - Sewer  10/19/2017 1:15:48 PM  10/20/2017  12 PM - 3 PM  10/20/2017  BEN 
BLD - Reinforcing Insp  10/20/2017 11:38:21 AM  10/23/2017  10 AM - 2 PM  10/23/2017  GCT 
ELE - Underground conduit  10/20/2017 11:39:37 AM  10/23/2017  10 AM - 2 PM  10/23/2017  GCT 
BLD - Reinforcing Insp  10/23/2017 1:48:49 PM  10/24/2017  12 PM - 3 PM  10/24/2017  GCT 
PLM - Sewer  10/23/2017 2:11:09 PM  10/24/2017  12 PM - 3 PM  10/24/2017  GCT 
BLD - Reinforcing Insp  10/24/2017 3:03:35 PM  10/25/2017    10/25/2017  BEN 
BLD - Reinforcing Insp  10/25/2017 12:42:42 PM  10/26/2017    10/26/2017  BEN 
ELE - Underground conduit  10/25/2017 12:42:51 PM  10/26/2017    10/26/2017  BEN 
BLD - Reinforcing Insp  10/26/2017 12:01:02 PM  10/27/2017    10/27/2017  BEN 
BLD - Reinforcing Insp  10/29/2017 2:15:03 PM  10/30/2017  12 PM - 3 PM  10/30/2017  GCT 
BLD - Reinforcing Insp  10/30/2017 1:03:32 PM  10/31/2017  12 PM - 3 PM  10/31/2017  BEN 
BLD - Reinforcing Insp  10/31/2017 1:56:56 PM  11/1/2017  12 PM - 3 PM  11/1/2017  BEN 
ELE - Underground conduit  10/31/2017 1:57:05 PM  11/1/2017  12 PM - 3 PM  11/1/2017  BEN 
BLD - Reinforcing Insp  11/1/2017 2:29:59 PM  11/2/2017    11/2/2017  BEN 
ELE - Underground conduit  11/1/2017 2:32:51 PM  11/2/2017    11/2/2017  BEN 
PLM - Water Service  11/2/2017 3:21:00 PM  11/3/2017    11/3/2017  BEN 
BLD - Reinforcing Insp  11/2/2017 3:21:55 PM  11/3/2017    11/3/2017  BEN 
PLM - Sewer  11/2/2017 3:54:09 PM  11/3/2017    11/3/2017  BEN 
BLD - Reinforcing Insp  11/5/2017 3:44:31 PM  11/6/2017  10 AM - 2 PM  11/6/2017  MMO 
ELE - Underground conduit  11/5/2017 3:44:49 PM  11/6/2017  10 AM - 2 PM  11/6/2017  MMO 
BLD - Reinforcing Insp  11/6/2017 2:12:35 PM  11/7/2017    11/7/2017  BEN 
PLM - Ground/Underfloor water  11/7/2017 11:01:12 AM  11/8/2017  8 AM - 12 PM  11/8/2017  BEN 
BLD - Reinforcing Insp  11/7/2017 11:02:09 AM  11/8/2017  8 AM - 12 PM  11/8/2017  BEN 
BLD - Footings Insp  11/7/2017 1:44:08 PM  11/8/2017  8 AM - 12 PM  11/8/2017  BEN 
BLD - Reinforcing Insp  11/8/2017 12:49:41 PM  11/9/2017  8 AM - 12 PM  11/9/2017  BEN 
ELE - Ground Electrode/UFER  11/8/2017 12:49:54 PM  11/9/2017  8 AM - 12 PM  11/9/2017  BEN 
ELE - Underground conduit  11/8/2017 2:50:34 PM  11/9/2017  8 AM - 12 PM  11/9/2017  BEN 
BLD - Footings Insp  11/12/2017 4:05:52 PM  11/13/2017  12 PM - 3 PM  11/13/2017  MMO 
BLD - Reinforcing Insp  11/12/2017 4:06:02 PM  11/13/2017  12 PM - 3 PM  11/13/2017  MMO 
ELE - Underground conduit  11/12/2017 4:06:12 PM  11/13/2017  12 PM - 3 PM  11/13/2017  MMO 
PLM - Ground/Underfloor waste  11/12/2017 4:06:44 PM  11/13/2017  12 PM - 3 PM  11/13/2017  MMO 
PLM - Sewer  11/12/2017 4:06:54 PM  11/13/2017  12 PM - 3 PM  11/13/2017  MMO 
BLD - Footings Insp  11/13/2017 3:54:35 PM  11/14/2017  10 AM - 2 PM  11/14/2017  MMO 
BLD - Reinforcing Insp  11/13/2017 3:54:42 PM  11/14/2017  10 AM - 2 PM  11/14/2017  MMO 
ELE - Underground conduit  11/13/2017 3:54:56 PM  11/14/2017  10 AM - 2 PM  11/14/2017  MMO 
PLM - Ground/Underfloor water  11/14/2017 3:17:56 PM  11/15/2017    11/15/2017  BEN 
MEC - Rough Mechanical  11/14/2017 3:18:04 PM  11/15/2017    11/15/2017  BEN 
BLD - Reinforcing Insp  11/14/2017 3:18:14 PM  11/15/2017    11/15/2017  BEN 
ELE - Underground conduit  11/14/2017 3:18:26 PM  11/15/2017    11/15/2017  BEN 
ELE - Rough Electrical  11/14/2017 3:18:35 PM  11/15/2017    11/15/2017  BEN 
BLD - Reinforcing Insp  11/15/2017 1:52:30 PM  11/16/2017  8 AM - 12 PM  11/16/2017  BEN 
PLM - Ground/Underfloor water  11/15/2017 1:52:43 PM  11/16/2017  8 AM - 12 PM  11/16/2017  BEN 
MEC - Underground Rough  11/15/2017 1:53:22 PM  11/16/2017  8 AM - 12 PM  11/16/2017  BEN 
PLM - Ground/Underfloor waste  11/15/2017 1:53:43 PM  11/16/2017  8 AM - 12 PM  11/16/2017  BEN 
PLM - Ground/Underfloor water  11/16/2017 2:54:07 PM  11/17/2017  8 AM - 12 PM  11/17/2017  BEN 
BLD - Reinforcing Insp  11/16/2017 2:54:21 PM  11/17/2017  8 AM - 12 PM  11/17/2017  BEN 
PLM - Underfloor Gas  11/19/2017 3:24:40 PM  11/20/2017  12 PM - 3 PM  11/20/2017  MMO 
BLD - Reinforcing Insp  11/19/2017 3:24:57 PM  11/20/2017  12 PM - 3 PM  11/20/2017  MMO 
ELE - Underground conduit  11/19/2017 3:25:18 PM  11/20/2017  12 PM - 3 PM  11/20/2017  MMO 
BLD - Reinforcing Insp  11/20/2017 2:38:01 PM  11/21/2017  8 AM - 12 PM  11/21/2017  BEN 
ELE - Underground conduit  11/20/2017 2:38:24 PM  11/21/2017  8 AM - 12 PM  11/21/2017  BEN 
BLD - Reinforcing Insp  11/21/2017 2:07:15 PM  11/22/2017  8 AM - 12 PM  11/22/2017  BEN 
ELE - Underground conduit  11/26/2017 7:16:15 PM  11/27/2017  8 AM - 12 PM  11/27/2017  GCT 
Route Revision Electrical  11/27/2017  12/13/2017    12/13/2017  APPR  MCS 
Approved Revision Electrical        12/13/2017  APPR  MCS 
Approved by Elec Engineering  11/27/2017      11/30/2017 9:06:04 AM  APPR  NEG 
Route to Elec Engineering  11/27/2017  12/13/2017    11/30/2017  APPR  NEG 
ELE - Underground conduit  11/27/2017 3:00:48 PM  11/28/2017  12 PM - 3 PM  11/28/2017  BEN 
BLD - Footings Insp  11/28/2017 4:22:04 PM  11/29/2017  8 AM - 12 PM  11/29/2017  BEN 
PLM - Underground gas  11/29/2017 3:46:59 PM  11/30/2017    11/30/2017  BEN 
BLD - Reinforcing Insp  11/29/2017 3:47:24 PM  11/30/2017    11/30/2017  BEN 
ELE - Underground conduit  11/29/2017 3:47:37 PM  11/30/2017    11/30/2017  BEN 
PLM - Underground gas  11/30/2017 2:55:53 PM  12/1/2017  8 AM - 12 PM  12/1/2017  BEN 
BLD - Reinforcing Insp  11/30/2017 2:56:05 PM  12/1/2017  8 AM - 12 PM  12/1/2017  BEN 
BLD - Pre-Slab Insp  11/30/2017 2:56:16 PM  12/1/2017  8 AM - 12 PM  12/1/2017  BEN 
PLM - Ground/Underfloor water  12/4/2017  12/4/2017  8 AM - 12 PM  12/4/2017  GCT 
PLM - Underground gas  12/4/2017 3:20:21 PM  12/5/2017    12/5/2017  BEN 
MEC - Underground Rough  12/4/2017 3:20:45 PM  12/5/2017    12/5/2017  BEN 
PLM - Ground/Underfloor water  12/4/2017 3:21:03 PM  12/5/2017    12/5/2017  BEN 
BLD - Reinforcing Insp  12/5/2017 2:23:23 PM  12/6/2017  8 AM - 12 PM  12/6/2017  BEN 
ELE - Underground conduit  12/5/2017 2:23:36 PM  12/6/2017  8 AM - 12 PM  12/6/2017  BEN 
PLM - Rough/Topout  12/6/2017 3:03:33 PM  12/7/2017  8 AM - 12 PM  12/7/2017  BEN 
BLD - Reinforcing Insp  12/6/2017 3:03:43 PM  12/7/2017  8 AM - 12 PM  12/7/2017  BEN 
MEC - Rough Mechanical  12/6/2017 3:07:57 PM  12/7/2017  8 AM - 12 PM  12/7/2017  BEN 
BLD - Reinforcing Insp  12/8/2017  12/8/2017  12 PM - 3 PM  12/8/2017  BEN 
ELE - Underground conduit  12/10/2017 2:39:28 PM  12/11/2017  12 PM - 3 PM  12/11/2017  GCT 
BLD - Footings Insp  12/11/2017 2:53:36 PM  12/12/2017    12/12/2017  BEN 
BLD - Reinforcing Insp  12/11/2017 2:53:44 PM  12/12/2017    12/12/2017  BEN 
PLM - Ground/Underfloor water  12/12/2017 2:30:55 PM  12/13/2017  12 PM - 3 PM  12/13/2017  BEN 
MEC - Underground Rough  12/12/2017 2:31:09 PM  12/13/2017  12 PM - 3 PM  12/13/2017  BEN 
BLD - Reinforcing Insp  12/12/2017 2:31:18 PM  12/13/2017  12 PM - 3 PM  12/13/2017  BEN 
BLD - Footings Insp  12/12/2017 2:31:25 PM  12/13/2017  12 PM - 3 PM  12/13/2017  BEN 
BLD - Footings Insp  12/13/2017 2:53:46 PM  12/14/2017  12 PM - 3 PM  12/14/2017  BEN 
BLD - Reinforcing Insp  12/13/2017 2:53:51 PM  12/14/2017  12 PM - 3 PM  12/14/2017  BEN 
ELE - Underground conduit  12/13/2017 2:53:58 PM  12/14/2017  12 PM - 3 PM  12/14/2017  BEN 
BLD - Footings Insp  12/14/2017 7:11:38 PM  12/15/2017  12 PM - 3 PM  12/15/2017  BEN 
BLD - Reinforcing Insp  12/14/2017 7:11:52 PM  12/15/2017  12 PM - 3 PM  12/15/2017  BEN 
MEC - Underground Rough  12/14/2017 7:12:31 PM  12/15/2017  12 PM - 3 PM  12/15/2017  BEN 
BLD - Reinforcing Insp  12/17/2017 4:03:18 PM  12/18/2017  8 AM - 12 PM  12/18/2017  GCT 
BLD - Pre-Slab Insp  12/17/2017 4:03:40 PM  12/18/2017  8 AM - 12 PM  12/18/2017  GCT 
ELE - Underground conduit  12/18/2017 2:59:40 PM  12/19/2017  12 PM - 3 PM  12/19/2017  BEN 
BLD - Reinforcing Insp  12/20/2017 2:40:09 PM  12/21/2017  12 PM - 3 PM  12/21/2017  BEN 
BLD - Reinforcing Insp  12/21/2017 1:43:37 PM  12/22/2017  8 AM - 12 PM  12/22/2017  BEN 
ELE - Underground conduit  12/21/2017 1:44:08 PM  12/22/2017  8 AM - 12 PM  12/22/2017  BEN 
BLD - Reinforcing Insp  12/25/2017 8:46:45 AM  12/26/2017  10 AM - 2 PM  12/26/2017  GCT 
PLM - Sewer  12/25/2017 2:16:15 PM  12/26/2017  10 AM - 2 PM  12/26/2017  GCT 
BLD - Reinforcing Insp  12/26/2017 3:38:06 PM  12/27/2017  12 PM - 3 PM  12/27/2017  BEN 
BLD - Footings Insp  12/26/2017 3:38:17 PM  12/27/2017  12 PM - 3 PM  12/27/2017  BEN 
PLM - Underfloor Gas  12/27/2017 2:51:48 PM  12/28/2017  12 PM - 3 PM  12/28/2017  BEN 
BLD - Reinforcing Insp  12/27/2017 2:52:34 PM  12/28/2017  12 PM - 3 PM  12/28/2017  BEN 
BLD - Footings Insp  12/27/2017 2:52:41 PM  12/28/2017  12 PM - 3 PM  12/28/2017  BEN 
ELE - Underground conduit  12/27/2017 2:52:57 PM  12/28/2017  12 PM - 3 PM  12/28/2017  BEN 
ELE - Rough Electrical  12/27/2017 2:53:22 PM  12/28/2017  12 PM - 3 PM  12/28/2017  BEN 
MEC - Underground Rough  12/28/2017 1:46:57 PM  12/29/2017  8 AM - 12 PM  12/29/2017  BEN 
BLD - Reinforcing Insp  12/28/2017 1:47:20 PM  12/29/2017  8 AM - 12 PM  12/29/2017  BEN 
BLD - Reinforcing Insp  12/29/2017 9:29:15 AM  1/2/2018  10 AM - 2 PM  1/2/2018  GCT 
ELE - Underground conduit  12/29/2017 9:29:26 AM  1/2/2018  10 AM - 2 PM  1/2/2018  GCT 
BLD - Footings Insp  12/29/2017 1:57:27 PM  1/2/2018  10 AM - 2 PM  1/2/2018  GCT 
MEC - Rough Mechanical  1/2/2018 2:28:20 PM  1/3/2018    1/3/2018  GCT 
BLD - Reinforcing Insp  1/2/2018 2:28:28 PM  1/3/2018    1/3/2018  GCT 
BLD - Footings Insp  1/3/2018 3:48:12 PM  1/4/2018  10 AM - 2 PM  1/4/2018  GCT 
BLD - Reinforcing Insp  1/3/2018 3:48:22 PM  1/4/2018  10 AM - 2 PM  1/4/2018  GCT 
ELE - Underground conduit  1/4/2018 3:20:52 PM  1/5/2018  8 AM - 12 PM  1/5/2018  MMO 
PLM - Ground/Underfloor waste  1/5/2018 2:12:01 PM  1/8/2018  8 AM - 12 PM  1/8/2018  GCT 
BLD - Reinforcing Insp  1/8/2018 3:06:32 PM  1/9/2018    1/9/2018  BEN 
BLD - Reinforcing Insp  1/9/2018 1:32:44 PM  1/10/2018  12 PM - 3 PM  1/10/2018  BEN 
BLD - Reinforcing Insp  1/10/2018 2:20:09 PM  1/11/2018  12 PM - 3 PM  1/11/2018  BEN 
PLM - Ground/Underfloor water  1/11/2018 4:17:32 PM  1/12/2018  12 PM - 3 PM  1/12/2018  BEN 
MEC - Underground Rough  1/11/2018 4:18:29 PM  1/12/2018  12 PM - 3 PM  1/12/2018  BEN 
BLD - Reinforcing Insp  1/15/2018 1:55:31 PM  1/16/2018  8 AM - 12 PM  1/16/2018  GCT 
BLD - Pre-Slab Insp  1/16/2018 2:36:30 PM  1/17/2018  12 PM - 3 PM  1/17/2018  BEN 
BLD - Footings Insp  1/16/2018 2:37:24 PM  1/17/2018  12 PM - 3 PM  1/17/2018  BEN 
BLD - Reinforcing Insp  1/16/2018 2:37:53 PM  1/17/2018  12 PM - 3 PM  1/17/2018  BEN 
BLD - Reinforcing Insp  1/17/2018 2:35:45 PM  1/18/2018  12 PM - 3 PM  1/18/2018  BEN 
BLD - Footings Insp  1/17/2018 2:35:55 PM  1/18/2018  12 PM - 3 PM  1/18/2018  BEN 
MEC - Underground Rough  1/18/2018 2:33:59 PM  1/19/2018  12 PM - 3 PM  1/19/2018  BEN 
BLD - Reinforcing Insp  1/18/2018 2:34:13 PM  1/19/2018  12 PM - 3 PM  1/19/2018  BEN 
BLD - Footings Insp  1/18/2018 2:35:06 PM  1/19/2018  12 PM - 3 PM  1/19/2018  BEN 
BLD - Pre-Slab Insp  1/22/2018  1/22/2018  8 AM - 12 PM  1/22/2018  GCT 
ELE - Underground conduit  1/22/2018 3:20:58 PM  1/23/2018  8 AM - 12 PM  1/23/2018  GCT 
BLD - Footings Insp  1/24/2018 2:26:45 PM  1/25/2018  12 PM - 3 PM  1/25/2018  BEN 
ELE - Underground conduit  1/24/2018 2:28:50 PM  1/25/2018  12 PM - 3 PM  1/25/2018  BEN 
BLD - Footings Insp  1/25/2018 2:45:38 PM  1/26/2018  12 PM - 3 PM  1/26/2018  BEN 
ELE - Underground conduit  1/25/2018 2:45:50 PM  1/26/2018  12 PM - 3 PM  1/26/2018  BEN 
BLD - Footings Insp  1/26/2018 12:39:01 PM  1/29/2018  8 AM - 12 PM  1/29/2018  BEN 
BLD - Reinforcing Insp  1/26/2018 12:39:40 PM  1/29/2018  8 AM - 12 PM  1/29/2018  BEN 
BLD - Reinforcing Insp  1/29/2018 3:05:48 PM  1/30/2018  8 AM - 12 PM  1/30/2018  GCT 
BLD - Footings Insp  1/29/2018 3:06:06 PM  1/30/2018  8 AM - 12 PM  1/30/2018  GCT 
BLD - Reinforcing Insp  1/30/2018 2:52:48 PM  1/31/2018  8 AM - 12 PM  1/31/2018  BEN 
BLD - Footings Insp  1/30/2018 2:52:55 PM  1/31/2018  8 AM - 12 PM  1/31/2018  BEN 
BLD - Footings Insp  1/31/2018 3:32:13 PM  2/1/2018  8 AM - 12 PM  2/1/2018  BEN 
BLD - Reinforcing Insp  1/31/2018 3:32:21 PM  2/1/2018  8 AM - 12 PM  2/1/2018  BEN 
ELE - Underground conduit  1/31/2018 3:32:28 PM  2/1/2018  8 AM - 12 PM  2/1/2018  BEN 
BLD - Reinforcing Insp  2/1/2018 3:09:28 PM  2/2/2018  8 AM - 12 PM  2/2/2018  BEN 
BLD - Footings Insp  2/1/2018 3:09:36 PM  2/2/2018  8 AM - 12 PM  2/2/2018  BEN 
BLD - Footings Insp  2/2/2018 2:10:01 PM  2/5/2018  8 AM - 12 PM  2/5/2018  BEN 
BLD - Reinforcing Insp  2/2/2018 2:10:08 PM  2/5/2018  8 AM - 12 PM  2/5/2018  BEN 
ELE - Underground conduit  2/5/2018 1:34:04 PM  2/6/2018  10 AM - 2 PM  2/6/2018  BCJ 
ELE - Ground Electrode/UFER  2/5/2018 2:18:04 PM  2/6/2018  10 AM - 2 PM  2/6/2018  BCJ 
BLD - Footings Insp  2/5/2018 2:18:13 PM  2/6/2018  10 AM - 2 PM  2/6/2018  BCJ 
BLD - Reinforcing Insp  2/5/2018 2:18:19 PM  2/6/2018  10 AM - 2 PM  2/6/2018  BCJ 
BLD - Reinforcing Insp  2/6/2018 2:48:10 PM  2/7/2018  8 AM - 12 PM  2/7/2018  BEN 
BLD - Footings Insp  2/6/2018 2:48:18 PM  2/7/2018  8 AM - 12 PM  2/7/2018  BEN 
ELE - Underground conduit  2/6/2018 2:48:31 PM  2/7/2018  8 AM - 12 PM  2/7/2018  BEN 
ELE - Ground Electrode/UFER  2/6/2018 2:48:54 PM  2/7/2018  8 AM - 12 PM  2/7/2018  BEN 
MEC - Underground Rough  2/7/2018 3:41:17 PM  2/8/2018  12 PM - 3 PM  2/8/2018  BEN 
PLM - Ground/Underfloor waste  2/7/2018 3:41:39 PM  2/8/2018  12 PM - 3 PM  2/8/2018  BEN 
BLD - Reinforcing Insp  2/7/2018 3:41:45 PM  2/8/2018  12 PM - 3 PM  2/8/2018  BEN 
BLD - Footings Insp  2/7/2018 3:42:16 PM  2/8/2018  12 PM - 3 PM  2/8/2018  BEN 
ELE - Underground conduit  2/7/2018 3:42:55 PM  2/8/2018  12 PM - 3 PM  2/8/2018  BEN 
MEC - Underground Rough  2/8/2018 3:23:58 PM  2/9/2018  12 PM - 3 PM  2/9/2018  BEN 
BLD - Reinforcing Insp  2/8/2018 3:24:04 PM  2/9/2018  12 PM - 3 PM  2/9/2018  BEN 
ELE - Underground conduit  2/8/2018 3:24:18 PM  2/9/2018  12 PM - 3 PM  2/9/2018  BEN 
PLM - Water Service  2/8/2018 7:42:08 PM  2/9/2018  12 PM - 3 PM  2/9/2018  BEN 
BLD - Reinforcing Insp  2/9/2018 12:34:43 PM  2/12/2018  12 PM - 3 PM  2/12/2018  GCT 
ELE - Underground conduit  2/9/2018 12:34:53 PM  2/12/2018  12 PM - 3 PM  2/12/2018  GCT 
BLD - Footings Insp  2/9/2018 2:32:33 PM  2/12/2018    2/12/2018  GCT 
MEC - Underground Rough  2/9/2018 2:43:40 PM  2/12/2018    2/12/2018  GCT 
ELE - Underground conduit  2/12/2018 2:58:29 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
ELE - Ground Electrode/UFER  2/12/2018 2:58:47 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
BLD - Footings Insp  2/12/2018 2:58:57 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
BLD - Reinforcing Insp  2/12/2018 2:59:05 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
PLM - Ground/Underfloor waste  2/12/2018 2:59:34 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
MEC - Underground Rough  2/12/2018 3:46:21 PM  2/13/2018  8 AM - 12 PM  2/13/2018  BEN 
BLD - Footings Insp  2/13/2018 3:14:04 PM  2/14/2018  12 PM - 3 PM  2/14/2018  BEN 
BLD - Reinforcing Insp  2/13/2018 3:14:13 PM  2/14/2018  12 PM - 3 PM  2/14/2018  BEN 
BLD - Footings Insp  2/14/2018 3:32:26 PM  2/15/2018  12 PM - 3 PM  2/15/2018  BEN 
BLD - Reinforcing Insp  2/14/2018 3:32:34 PM  2/15/2018  12 PM - 3 PM  2/15/2018  BEN 
ELE - Underground conduit  2/14/2018 3:32:45 PM  2/15/2018  12 PM - 3 PM  2/15/2018  BEN 
BLD - Reinforcing Insp  2/20/2018  2/20/2018  10 AM - 2 PM  2/20/2018  GCT 
BLD - Footings Insp  2/20/2018  2/20/2018  10 AM - 2 PM  2/20/2018  GCT 
BLD - Pre-Slab Insp  2/20/2018  2/21/2018  10 AM - 2 PM  2/21/2018  GCT 
BLD - Footings Insp  2/20/2018  2/21/2018  10 AM - 2 PM  2/21/2018  GCT 
BLD - Reinforcing Insp  2/21/2018 12:05:12 PM  2/22/2018  12 PM - 3 PM  2/22/2018  BEN 
BLD - Footings Insp  2/21/2018 3:10:38 PM  2/22/2018  12 PM - 3 PM  2/22/2018  BEN 
BLD - Reinforcing Insp  2/22/2018 11:28:00 AM  2/23/2018  12 PM - 3 PM  2/23/2018  BEN 
ELE - Underground conduit  2/22/2018 11:47:58 AM  2/23/2018  12 PM - 3 PM  2/23/2018  BEN 
BLD - Reinforcing Insp  2/23/2018 2:51:56 PM  2/26/2018  8 AM - 12 PM  2/26/2018  GCT 
ELE - Underground conduit  2/23/2018 2:59:03 PM  2/26/2018  8 AM - 12 PM  2/26/2018  GCT 
BLD - Reinforcing Insp  2/26/2018 10:41:20 AM  2/27/2018  10 AM - 2 PM  2/27/2018  BEN 
ELE - Underground conduit  2/26/2018 10:41:34 AM  2/27/2018  10 AM - 2 PM  2/27/2018  BEN 
PLM - Underground gas  2/26/2018 11:07:27 AM  2/27/2018  10 AM - 2 PM  2/27/2018  BEN 
BLD - Reinforcing Insp  2/27/2018 7:51:15 AM  2/28/2018  12 PM - 3 PM  2/28/2018  BEN 
ELE - Underground conduit  2/27/2018 7:51:32 AM  2/28/2018  12 PM - 3 PM  2/28/2018  BEN 
BLD - Reinforcing Insp  2/28/2018 7:21:30 AM  3/1/2018  12 PM - 3 PM  3/1/2018  BEN 
BLD - Footings Insp  2/28/2018 3:12:03 PM  3/1/2018  12 PM - 3 PM  3/1/2018  BEN 
BLD - Pre-Slab Insp  2/28/2018 3:12:10 PM  3/1/2018  12 PM - 3 PM  3/1/2018  BEN 
ELE - Underground conduit  2/28/2018 3:12:17 PM  3/1/2018  12 PM - 3 PM  3/1/2018  BEN 
BLD - Reinforcing Insp  3/1/2018 11:17:13 AM  3/2/2018  12 PM - 3 PM  3/2/2018  BEN 
ELE - Underground conduit  3/1/2018 11:17:28 AM  3/2/2018  12 PM - 3 PM  3/2/2018  BEN 
PLM - Gas Test  3/1/2018 2:29:44 PM  3/2/2018  12 PM - 3 PM  3/2/2018  BEN 
BLD - Footings Insp  3/1/2018 2:29:57 PM  3/2/2018  12 PM - 3 PM  3/2/2018  BEN 
BLD - Reinforcing Insp  3/2/2018 10:44:09 AM  3/5/2018  10 AM - 2 PM  3/5/2018  GCT 
BLD - Footings Insp  3/2/2018 10:44:16 AM  3/5/2018  10 AM - 2 PM  3/5/2018  GCT 
ELE - Underground conduit  3/2/2018 2:21:23 PM  3/5/2018    3/5/2018  GCT 
ELE - Underground conduit  3/5/2018 2:45:05 PM  3/6/2018    3/6/2018  BEN 
BLD - Footings Insp  3/5/2018 2:45:16 PM  3/6/2018    3/6/2018  BEN 
BLD - Reinforcing Insp  3/5/2018 2:45:23 PM  3/6/2018    3/6/2018  BEN 
BLD - Footings Insp  3/6/2018 11:07:46 AM  3/7/2018  12 PM - 3 PM  3/7/2018  BEN 
BLD - Reinforcing Insp  3/6/2018 11:07:54 AM  3/7/2018  12 PM - 3 PM  3/7/2018  BEN 
ELE - Underground conduit  3/6/2018 11:08:40 AM  3/7/2018  12 PM - 3 PM  3/7/2018  BEN 
BLD - Footings Insp  3/7/2018 1:06:43 PM  3/8/2018  12 PM - 3 PM  3/8/2018  BEN 
ELE - Underground conduit  3/8/2018 11:04:08 AM  3/9/2018  12 PM - 3 PM  3/9/2018  BEN 
ELE - Ground Electrode/UFER  3/8/2018 11:04:16 AM  3/9/2018  12 PM - 3 PM  3/9/2018  BEN 
BLD - Footings Insp  3/9/2018 1:52:10 PM  3/12/2018  10 AM - 2 PM  3/12/2018  GCT 
BLD - Reinforcing Insp  3/9/2018 1:52:18 PM  3/12/2018  10 AM - 2 PM  3/12/2018  GCT 
BLD - Reinforcing Insp  3/12/2018 1:52:27 PM  3/13/2018  8 AM - 12 PM  3/13/2018  BEN 
BLD - Footings Insp  3/12/2018 1:52:58 PM  3/13/2018  8 AM - 12 PM  3/13/2018  BEN 
ELE - Underground conduit  3/12/2018 1:53:16 PM  3/13/2018  8 AM - 12 PM  3/13/2018  BEN 
BLD - Reinforcing Insp  3/13/2018 2:19:36 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BEN 
ELE - Underground conduit  3/13/2018 2:19:46 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BEN 
BLD -Floor Joists/Girders Insp  3/13/2018 5:27:23 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BEN 
PLM - Sewer  3/13/2018 5:28:31 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BEN 
PLM - Underground gas  3/13/2018 5:29:08 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BEN 
BLD - Reinforcing Insp  3/14/2018 11:40:15 AM  3/15/2018  12 PM - 3 PM  3/15/2018  BEN 
ELE - Underground conduit  3/14/2018 11:40:21 AM  3/15/2018  12 PM - 3 PM  3/15/2018  BEN 
PLM - Sewer  3/15/2018 3:04:43 PM  3/16/2018  8 AM - 12 PM  3/16/2018  BEN 
PLM - Ground/Underfloor waste  3/15/2018 3:04:56 PM  3/16/2018  8 AM - 12 PM  3/16/2018  BEN 
BLD - Reinforcing Insp  3/15/2018 3:05:32 PM  3/16/2018  8 AM - 12 PM  3/16/2018  BEN 
ELE - Underground conduit  3/15/2018 3:05:43 PM  3/16/2018  8 AM - 12 PM  3/16/2018  BEN 
BLD - Reinforcing Insp  3/15/2018 3:06:08 PM  3/19/2018  10 AM - 2 PM  3/19/2018  GCT 
ELE - Underground conduit  3/15/2018 3:06:23 PM  3/19/2018  10 AM - 2 PM  3/19/2018  GCT 
BLD - Footings Insp  3/16/2018 12:18:43 PM  3/19/2018  10 AM - 2 PM  3/19/2018  GCT 
BLD - Footings Insp  3/19/2018 2:32:34 PM  3/20/2018  12 PM - 3 PM  3/20/2018  BEN 
BLD - Reinforcing Insp  3/19/2018 2:32:40 PM  3/20/2018  12 PM - 3 PM  3/20/2018  BEN 
ELE - Underground conduit  3/19/2018 2:32:48 PM  3/20/2018  12 PM - 3 PM  3/20/2018  BEN 
BLD - Footings Insp  3/20/2018 4:08:22 PM  3/21/2018  10 AM - 2 PM  3/21/2018  BEN 
BLD - Reinforcing Insp  3/20/2018 4:08:29 PM  3/21/2018  10 AM - 2 PM  3/21/2018  BEN 
ELE - Underground conduit  3/20/2018 4:08:37 PM  3/21/2018  10 AM - 2 PM  3/21/2018  BEN 
BLD -Floor Joists/Girders Insp  3/20/2018 4:09:15 PM  3/21/2018  10 AM - 2 PM  3/21/2018  BEN 
BLD - Footings Insp  3/21/2018 1:38:15 PM  3/22/2018  8 AM - 12 PM  3/22/2018  BEN 
BLD - Reinforcing Insp  3/21/2018 1:38:22 PM  3/22/2018  8 AM - 12 PM  3/22/2018  BEN 
ELE - Underground conduit  3/21/2018 1:38:28 PM  3/22/2018  8 AM - 12 PM  3/22/2018  BEN 
BLD -Floor Joists/Girders Insp  3/21/2018 1:38:42 PM  3/22/2018  8 AM - 12 PM  3/22/2018  BEN 
BLD - Reinforcing Insp  3/22/2018 2:17:21 PM  3/23/2018  10 AM - 2 PM  3/23/2018  BEN 
BLD -Floor Joists/Girders Insp  3/22/2018 2:18:47 PM  3/23/2018  10 AM - 2 PM  3/23/2018  BEN 
BLD - Reinforcing Insp  3/23/2018 2:52:09 PM  3/26/2018  10 AM - 2 PM  3/26/2018  GCT 
ELE - Underground conduit  3/23/2018 2:52:16 PM  3/26/2018  10 AM - 2 PM  3/26/2018  GCT 
BLD - Reinforcing Insp  3/26/2018 1:13:34 PM  3/27/2018  10 AM - 2 PM  3/27/2018  BEN 
ELE - Underground conduit  3/26/2018 1:13:57 PM  3/27/2018  10 AM - 2 PM  3/27/2018  BEN 
BLD -Floor Joists/Girders Insp  3/26/2018 1:58:00 PM  3/27/2018  10 AM - 2 PM  3/27/2018  BEN 
BLD - Footings Insp  3/26/2018 2:08:20 PM  3/27/2018  10 AM - 2 PM  3/27/2018  BEN 
PLM - Underground gas  3/26/2018 3:11:56 PM  3/27/2018  10 AM - 2 PM  3/27/2018  BEN 
PLM - Underground gas  3/27/2018 2:25:33 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
BLD - Footings Insp  3/27/2018 2:26:16 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
BLD - Reinforcing Insp  3/27/2018 2:26:20 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
ELE - Underground conduit  3/27/2018 2:26:28 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
ELE - Rough Electrical  3/27/2018 2:26:34 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
MEC - Underground Rough  3/27/2018 5:46:57 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BEN 
BLD - Reinforcing Insp  3/28/2018 2:14:14 PM  3/29/2018  10 AM - 2 PM  3/29/2018  BEN 
BLD - Footings Insp  3/28/2018 2:14:22 PM  3/29/2018  10 AM - 2 PM  3/29/2018  BEN 
ELE - Underground conduit  3/28/2018 2:14:47 PM  3/29/2018  10 AM - 2 PM  3/29/2018  BEN 
BLD - Reinforcing Insp  3/29/2018 1:42:33 PM  3/30/2018  12 PM - 3 PM  3/30/2018  BEN 
ELE - Underground conduit  3/29/2018 1:42:47 PM  3/30/2018  12 PM - 3 PM  3/30/2018  BEN 
BLD - Footings Insp  3/30/2018 11:22:45 AM  4/2/2018  8 AM - 12 PM  4/2/2018  JOS 
BLD - Reinforcing Insp  3/30/2018 11:23:19 AM  4/2/2018  8 AM - 12 PM  4/2/2018  JOS 
ELE - Underground conduit  3/30/2018 11:23:56 AM  4/2/2018  8 AM - 12 PM  4/2/2018  JOS 
BLD - Footings Insp  4/2/2018 3:24:52 PM  4/3/2018  10 AM - 2 PM  4/3/2018  BEN 
BLD - Reinforcing Insp  4/2/2018 3:25:18 PM  4/3/2018  10 AM - 2 PM  4/3/2018  BEN 
ELE - Underground conduit  4/2/2018 3:25:29 PM  4/3/2018  10 AM - 2 PM  4/3/2018  BEN 
BLD - Framing Insp.  4/2/2018 3:25:43 PM  4/3/2018  10 AM - 2 PM  4/3/2018  BEN 
PLM - Ground/Underfloor water  4/3/2018 3:08:36 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
BLD - Footings Insp  4/3/2018 3:08:45 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
BLD - Reinforcing Insp  4/3/2018 3:08:54 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
ELE - Underground conduit  4/3/2018 3:09:02 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
BLD - Framing Insp.  4/3/2018 3:09:08 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
PLM - Gas Test  4/3/2018 3:17:27 PM  4/4/2018  10 AM - 2 PM  4/4/2018  BEN 
BLD - Footings Insp  4/4/2018 2:10:13 PM  4/5/2018  8 AM - 12 PM  4/5/2018  BEN 
BLD - Reinforcing Insp  4/4/2018 2:10:19 PM  4/5/2018  8 AM - 12 PM  4/5/2018  BEN 
ELE - Underground conduit  4/4/2018 2:10:34 PM  4/5/2018  8 AM - 12 PM  4/5/2018  BEN 
PLM - Gas Test  4/4/2018 2:10:41 PM  4/5/2018  8 AM - 12 PM  4/5/2018  BEN 
PLM - Ground/Underfloor water  4/5/2018 2:57:45 PM  4/6/2018  12 PM - 3 PM  4/6/2018  BEN 
BLD - Reinforcing Insp  4/5/2018 2:57:51 PM  4/6/2018  12 PM - 3 PM  4/6/2018  BEN 
ELE - Underground conduit  4/5/2018 2:57:57 PM  4/6/2018  12 PM - 3 PM  4/6/2018  BEN 
BLD - Reinforcing Insp  4/6/2018 1:46:07 PM  4/9/2018  10 AM - 2 PM  4/9/2018  JOS 
ELE - Underground conduit  4/6/2018 1:46:17 PM  4/9/2018  10 AM - 2 PM  4/9/2018  JOS 
PLM - Ground/Underfloor water  4/6/2018 1:46:45 PM  4/9/2018  10 AM - 2 PM  4/9/2018  JOS 
BLD - Reinforcing Insp  4/9/2018 1:18:43 PM  4/10/2018  8 AM - 12 PM  4/10/2018  BEN 
ELE - Underground conduit  4/9/2018 1:18:53 PM  4/10/2018  8 AM - 12 PM  4/10/2018  BEN 
BLD - Framing Insp.  4/9/2018 2:26:49 PM  4/10/2018  8 AM - 12 PM  4/10/2018  BEN 
PLM - Underground gas  4/9/2018 2:57:32 PM  4/10/2018  8 AM - 12 PM  4/10/2018  BEN 
MEC - Underground Rough  4/10/2018 10:45:06 AM  4/11/2018  8 AM - 12 PM  4/11/2018  BEN 
BLD - Footings Insp  4/10/2018 10:48:59 AM  4/11/2018  8 AM - 12 PM  4/11/2018  BEN 
ELE - Underground conduit  4/10/2018 10:49:07 AM  4/11/2018  8 AM - 12 PM  4/11/2018  BEN 
BLD - Reinforcing Insp  4/10/2018 2:18:08 PM  4/11/2018  8 AM - 12 PM  4/11/2018  BEN 
PLM - Ground/Underfloor water  4/12/2018 11:51:34 AM  4/13/2018  8 AM - 12 PM  4/13/2018  BEN 
MEC - Underground Rough  4/12/2018 11:51:50 AM  4/13/2018  8 AM - 12 PM  4/13/2018  BEN 
ELE - Underground conduit  4/12/2018 11:51:56 AM  4/13/2018  8 AM - 12 PM  4/13/2018  BEN 
BLD - Footings Insp  4/12/2018 2:01:27 PM  4/13/2018  8 AM - 12 PM  4/13/2018  BEN 
BLD - Footings Insp  4/13/2018 11:54:41 AM  4/16/2018    4/16/2018  GCT 
ELE - Underground conduit  4/13/2018 11:54:50 AM  4/16/2018    4/16/2018  GCT 
BLD - Reinforcing Insp  4/16/2018 1:10:31 PM  4/17/2018  12 PM - 3 PM  4/17/2018  BEN 
BLD - Footings Insp  4/16/2018 1:10:40 PM  4/17/2018  12 PM - 3 PM  4/17/2018  BEN 
ELE - Underground conduit  4/16/2018 1:10:51 PM  4/17/2018  12 PM - 3 PM  4/17/2018  BEN 
BLD - Footings Insp  4/17/2018 2:35:13 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BEN 
BLD - Reinforcing Insp  4/17/2018 2:35:23 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BEN 
ELE - Underground conduit  4/17/2018 2:36:01 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BEN 
BLD - Footings Insp  4/18/2018 1:38:05 PM  4/19/2018  12 PM - 3 PM  4/19/2018  BEN 
BLD - Reinforcing Insp  4/18/2018 1:38:15 PM  4/19/2018  12 PM - 3 PM  4/19/2018  BEN 
ELE - Rough Electrical  4/18/2018 1:38:51 PM  4/19/2018  12 PM - 3 PM  4/19/2018  BEN 
ELE - Underground conduit  4/18/2018 1:39:28 PM  4/19/2018  12 PM - 3 PM  4/19/2018  BEN 
BLD - Footings Insp  4/19/2018 3:03:26 PM  4/20/2018  10 AM - 2 PM  4/20/2018  JOS 
BLD - Reinforcing Insp  4/19/2018 3:03:33 PM  4/20/2018  10 AM - 2 PM  4/20/2018  JOS 
ELE - Underground conduit  4/19/2018 3:03:58 PM  4/20/2018  10 AM - 2 PM  4/20/2018  JOS 
BLD -Floor Joists/Girders Insp  4/19/2018 3:04:29 PM  4/20/2018  10 AM - 2 PM  4/20/2018  JOS 
ELE - Underground conduit  4/20/2018 1:40:39 PM  4/23/2018  12 PM - 3 PM  4/23/2018  GCT 
ELE - Ground Electrode/UFER  4/20/2018 1:40:48 PM  4/23/2018  12 PM - 3 PM  4/23/2018  GCT 
BLD - Reinforcing Insp  4/20/2018 1:42:01 PM  4/23/2018  12 PM - 3 PM  4/23/2018  GCT 
BLD - Footings Insp  4/20/2018 1:42:09 PM  4/23/2018  12 PM - 3 PM  4/23/2018  GCT 
BLD - Footings Insp  4/23/2018 2:15:36 PM  4/24/2018  10 AM - 2 PM  4/24/2018  GCT 
BLD - Reinforcing Insp  4/23/2018 2:15:43 PM  4/24/2018  10 AM - 2 PM  4/24/2018  GCT 
ELE - Underground conduit  4/23/2018 2:15:56 PM  4/24/2018  10 AM - 2 PM  4/24/2018  GCT 
BLD - Footings Insp  4/24/2018 2:39:42 PM  4/25/2018  10 AM - 2 PM  4/25/2018  GCT 
BLD - Reinforcing Insp  4/24/2018 2:39:48 PM  4/25/2018  10 AM - 2 PM  4/25/2018  GCT 
ELE - Underground conduit  4/24/2018 2:40:03 PM  4/25/2018  10 AM - 2 PM  4/25/2018  GCT 
BLD - Footings Insp  4/25/2018 2:20:59 PM  4/26/2018  8 AM - 12 PM  4/26/2018  JOS 
BLD - Reinforcing Insp  4/25/2018 2:21:10 PM  4/26/2018  8 AM - 12 PM  4/26/2018  JOS 
ELE - Underground conduit  4/25/2018 2:21:18 PM  4/26/2018  8 AM - 12 PM  4/26/2018  JOS 
BLD - Footings Insp  4/26/2018 1:31:35 PM  4/27/2018  8 AM - 12 PM  4/27/2018  MMO 
BLD - Reinforcing Insp  4/26/2018 1:31:42 PM  4/27/2018  8 AM - 12 PM  4/27/2018  MMO 
ELE - Underground conduit  4/26/2018 1:31:56 PM  4/27/2018  8 AM - 12 PM  4/27/2018  MMO 
BLD - Footings Insp  4/27/2018 3:01:13 PM  4/30/2018  10 AM - 2 PM  4/30/2018  GCT 
BLD - Reinforcing Insp  4/27/2018 3:01:19 PM  4/30/2018  10 AM - 2 PM  4/30/2018  GCT 
ELE - Underground conduit  4/27/2018 3:01:45 PM  4/30/2018  10 AM - 2 PM  4/30/2018  GCT 
BLD - Footings Insp  4/30/2018 2:27:31 PM  5/1/2018  10 AM - 2 PM  5/1/2018  GCT 
BLD - Reinforcing Insp  4/30/2018 2:27:36 PM  5/1/2018  10 AM - 2 PM  5/1/2018  GCT 
ELE - Underground conduit  4/30/2018 2:27:44 PM  5/1/2018  10 AM - 2 PM  5/1/2018  GCT 
BLD - Footings Insp  5/1/2018 2:28:53 PM  5/2/2018  8 AM - 12 PM  5/2/2018  GCT 
BLD - Reinforcing Insp  5/1/2018 2:29:00 PM  5/2/2018  8 AM - 12 PM  5/2/2018  GCT 
ELE - Underground conduit  5/1/2018 2:29:27 PM  5/2/2018  8 AM - 12 PM  5/2/2018  GCT 
BLD - Footings Insp  5/2/2018 1:54:23 PM  5/3/2018  8 AM - 12 PM  5/3/2018  GCT 
BLD - Reinforcing Insp  5/2/2018 1:54:29 PM  5/3/2018  8 AM - 12 PM  5/3/2018  GCT 
ELE - Underground conduit  5/2/2018 1:54:39 PM  5/3/2018  8 AM - 12 PM  5/3/2018  GCT 
MEC - Underground Rough  5/2/2018 1:59:30 PM  5/3/2018  8 AM - 12 PM  5/3/2018  GCT 
PLM - Sewer  5/2/2018 2:20:15 PM  5/3/2018  8 AM - 12 PM  5/3/2018  GCT 
BLD - Footings Insp  5/3/2018 2:46:35 PM  5/4/2018  8 AM - 12 PM  5/4/2018  MMO 
BLD - Reinforcing Insp  5/3/2018 2:46:42 PM  5/4/2018  8 AM - 12 PM  5/4/2018  MMO 
ELE - Underground conduit  5/3/2018 2:46:52 PM  5/4/2018  8 AM - 12 PM  5/4/2018  MMO 
BLD - Framing Insp.  5/3/2018 2:47:00 PM  5/4/2018  8 AM - 12 PM  5/4/2018  MMO 
BLD - Footings Insp  5/4/2018 2:51:17 PM  5/7/2018  10 AM - 2 PM  5/7/2018  GCT 
BLD - Reinforcing Insp  5/4/2018 2:51:27 PM  5/7/2018  10 AM - 2 PM  5/7/2018  GCT 
ELE - Underground conduit  5/4/2018 2:51:35 PM  5/7/2018  10 AM - 2 PM  5/7/2018  GCT 
BLD - Footings Insp  5/7/2018 1:15:50 PM  5/8/2018    5/8/2018  BEN 
BLD - Reinforcing Insp  5/7/2018 1:15:59 PM  5/8/2018    5/8/2018  BEN 
ELE - Underground conduit  5/7/2018 1:16:09 PM  5/8/2018    5/8/2018  BEN 
BLD - Framing Insp.  5/7/2018 1:16:21 PM  5/8/2018    5/8/2018  BEN 
BLD -Floor Joists/Girders Insp  5/7/2018 1:16:38 PM  5/8/2018    5/8/2018  BEN 
BLD - Footings Insp  5/8/2018 12:46:11 PM  5/9/2018  12 PM - 3 PM  5/9/2018  BEN 
BLD - Reinforcing Insp  5/8/2018 12:46:21 PM  5/9/2018  12 PM - 3 PM  5/9/2018  BEN 
ELE - Underground conduit  5/8/2018 12:46:34 PM  5/9/2018  12 PM - 3 PM  5/9/2018  BEN 
BLD - Framing Insp.  5/8/2018 2:40:45 PM  5/9/2018  12 PM - 3 PM  5/9/2018  BEN 
BLD - Reinforcing Insp  5/9/2018 2:46:09 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BEN 
BLD - Footings Insp  5/9/2018 2:46:24 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BEN 
ELE - Underground conduit  5/9/2018 2:46:33 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BEN 
BLD - Framing Insp.  5/9/2018 2:46:50 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BEN 
BLD - Reinforcing Insp  5/10/2018 3:16:17 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BEN 
BLD - Footings Insp  5/10/2018 3:16:34 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BEN 
ELE - Underground conduit  5/10/2018 3:16:41 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BEN 
BLD - Reinforcing Insp  5/11/2018 1:18:47 PM  5/14/2018  8 AM - 12 PM  5/14/2018  GCT 
BLD - Footings Insp  5/11/2018 1:18:54 PM  5/14/2018  8 AM - 12 PM  5/14/2018  GCT 
ELE - Underground conduit  5/11/2018 1:19:01 PM  5/14/2018  8 AM - 12 PM  5/14/2018  GCT 
BLD - Footings Insp  5/14/2018 2:41:07 PM  5/15/2018  12 PM - 3 PM  5/15/2018  BEN 
BLD - Reinforcing Insp  5/14/2018 2:41:14 PM  5/15/2018  12 PM - 3 PM  5/15/2018  BEN 
ELE - Underground conduit  5/14/2018 2:41:24 PM  5/15/2018  12 PM - 3 PM  5/15/2018  BEN 
BLD - Reinforcing Insp  5/15/2018 1:55:55 PM  5/16/2018  12 PM - 3 PM  5/16/2018  BEN 
ELE - Underground conduit  5/15/2018 1:56:04 PM  5/16/2018  12 PM - 3 PM  5/16/2018  BEN 
BLD - Reinforcing Insp  5/16/2018 2:32:48 PM  5/17/2018  12 PM - 3 PM  5/17/2018  BEN 
ELE - Underground conduit  5/16/2018 2:33:59 PM  5/17/2018  12 PM - 3 PM  5/17/2018  BEN 
BLD - Framing Insp.  5/16/2018 2:34:10 PM  5/17/2018  12 PM - 3 PM  5/17/2018  BEN 
BLD -Floor Joists/Girders Insp  5/16/2018 2:34:33 PM  5/17/2018  12 PM - 3 PM  5/17/2018  BEN 
BLD - Reinforcing Insp  5/17/2018 2:33:39 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BEN 
BLD - Footings Insp  5/17/2018 2:33:47 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BEN 
ELE - Underground conduit  5/17/2018 2:33:56 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BEN 
BLD - Framing Insp.  5/17/2018 2:34:09 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BEN 
BLD - Reinforcing Insp  5/18/2018 1:20:57 PM  5/21/2018  8 AM - 12 PM  5/21/2018  GCT 
BLD - Footings Insp  5/18/2018 1:21:04 PM  5/21/2018  8 AM - 12 PM  5/21/2018  GCT 
ELE - Underground conduit  5/18/2018 1:21:24 PM  5/21/2018  8 AM - 12 PM  5/21/2018  GCT 
BLD - Exterior Lath Insp  5/18/2018 1:21:32 PM  5/21/2018  8 AM - 12 PM  5/21/2018  GCT 
PLM - Underground gas  5/18/2018 1:24:10 PM  5/21/2018  8 AM - 12 PM  5/21/2018  GCT 
BLD - Footings Insp  5/21/2018 2:01:10 PM  5/22/2018  12 PM - 3 PM  5/22/2018  BEN 
BLD - Reinforcing Insp  5/21/2018 2:01:17 PM  5/22/2018  12 PM - 3 PM  5/22/2018  BEN 
ELE - Underground conduit  5/21/2018 2:01:23 PM  5/22/2018  12 PM - 3 PM  5/22/2018  BEN 
BLD - Reinforcing Insp  5/22/2018 2:33:53 PM  5/23/2018  12 PM - 3 PM  5/24/2018  MMO 
BLD - Footings Insp  5/22/2018 2:34:02 PM  5/23/2018  12 PM - 3 PM  5/24/2018  MMO 
ELE - Underground conduit  5/22/2018 2:36:10 PM  5/23/2018  12 PM - 3 PM  5/24/2018  MMO 
BLD - Footings Insp  5/23/2018 5:40:10 AM  5/24/2018    5/24/2018  GCT 
BLD - Reinforcing Insp  5/23/2018 5:40:32 AM  5/24/2018    5/24/2018  GCT 
ELE - Underground conduit  5/23/2018 5:40:41 AM  5/24/2018    5/24/2018  GCT 
BLD - Footings Insp  5/24/2018 2:46:01 PM  5/25/2018  8 AM - 12 PM  5/25/2018  GCT 
ELE - Underground conduit  5/24/2018 2:46:16 PM  5/25/2018  8 AM - 12 PM  5/25/2018  GCT 
BLD -Floor Joists/Girders Insp  5/24/2018 2:46:38 PM  5/25/2018  8 AM - 12 PM  5/25/2018  GCT 
BLD - Footings Insp  5/25/2018 11:21:00 AM  5/29/2018  8 AM - 12 PM  5/29/2018  MMO 
BLD - Reinforcing Insp  5/25/2018 11:21:08 AM  5/29/2018  8 AM - 12 PM  5/29/2018  MMO 
ELE - Underground conduit  5/25/2018 11:21:15 AM  5/29/2018  8 AM - 12 PM  5/29/2018  MMO 
BLD -Floor Joists/Girders Insp  5/25/2018 11:21:28 AM  5/29/2018  8 AM - 12 PM  5/29/2018  MMO 
BLD - Reinforcing Insp  5/29/2018  5/30/2018    5/30/2018  GCT 
BLD -Floor Joists/Girders Insp  5/29/2018  5/30/2018    5/30/2018  GCT 
BLD - Reinforcing Insp  5/30/2018 10:11:35 AM  5/31/2018  8 AM - 12 PM  5/31/2018  GCT 
BLD - Footings Insp  5/30/2018 10:11:41 AM  5/31/2018  8 AM - 12 PM  5/31/2018  GCT 
ELE - Underground conduit  5/30/2018 10:11:51 AM  5/31/2018  8 AM - 12 PM  5/31/2018  GCT 
BLD - Reinforcing Insp  5/31/2018 2:26:17 PM  6/1/2018  8 AM - 12 PM  6/1/2018  BEN 
BLD - Footings Insp  5/31/2018 2:26:25 PM  6/1/2018  8 AM - 12 PM  6/1/2018  BEN 
ELE - Underground conduit  5/31/2018 2:26:33 PM  6/1/2018  8 AM - 12 PM  6/1/2018  BEN 
BLD - Footings Insp  6/1/2018 2:35:02 PM  6/4/2018    6/4/2018  GCT 
BLD - Reinforcing Insp  6/1/2018 2:35:11 PM  6/4/2018    6/4/2018  GCT 
ELE - Underground conduit  6/1/2018 2:35:18 PM  6/4/2018    6/4/2018  GCT 
Approved Revision Structural  6/4/2018      6/7/2018  DONE  CSG 
Route Revision Structural  6/4/2018  6/20/2018    6/7/2018  CORR  CSG 
ELE - Underground conduit  6/4/2018 2:24:40 PM  6/5/2018  10 AM - 2 PM  6/5/2018  BEN 
BLD - Footings Insp  6/4/2018 2:25:31 PM  6/5/2018  10 AM - 2 PM  6/5/2018  BEN 
BLD - Reinforcing Insp  6/4/2018 2:25:40 PM  6/5/2018  10 AM - 2 PM  6/5/2018  BEN 
BLD - Reinforcing Insp  6/5/2018 2:40:51 PM  6/6/2018  10 AM - 2 PM  6/6/2018  BEN 
ELE - Underground conduit  6/5/2018 2:40:58 PM  6/6/2018  10 AM - 2 PM  6/6/2018  BEN 
BLD - Footings Insp  6/6/2018 1:49:54 PM  6/7/2018  8 AM - 12 PM  6/7/2018  BEN 
BLD - Reinforcing Insp  6/6/2018 1:50:01 PM  6/7/2018  8 AM - 12 PM  6/7/2018  BEN 
ELE - Underground conduit  6/6/2018 1:50:11 PM  6/7/2018  8 AM - 12 PM  6/7/2018  BEN 
BLD - Footings Insp  6/7/2018 1:42:51 PM  6/8/2018  8 AM - 12 PM  6/8/2018  BEN 
Route Revision Structural  6/7/2018  6/25/2018    6/7/2018  APPR  CSG 
ELE - Underground conduit  6/7/2018 3:07:38 PM  6/8/2018  8 AM - 12 PM  6/8/2018  BEN 
BLD - Framing Insp.  6/7/2018 3:08:07 PM  6/8/2018  8 AM - 12 PM  6/8/2018  BEN 
BLD - Reinforcing Insp  6/7/2018 3:08:31 PM  6/8/2018  8 AM - 12 PM  6/8/2018  BEN 
BLD -Floor Joists/Girders Insp  6/7/2018 3:09:13 PM  6/8/2018  8 AM - 12 PM  6/8/2018  BEN 
BLD - Reinforcing Insp  6/8/2018 1:54:43 PM  6/11/2018    6/11/2018  GCT 
BLD - Footings Insp  6/8/2018 2:00:23 PM  6/11/2018    6/11/2018  GCT 
ELE - Rough Electrical  6/8/2018 2:00:33 PM  6/11/2018    6/11/2018  GCT 
BLD - Reinforcing Insp  6/11/2018 3:01:16 PM  6/12/2018  10 AM - 2 PM  6/12/2018  BEN 
ELE - Underground conduit  6/11/2018 3:01:23 PM  6/12/2018  10 AM - 2 PM  6/12/2018  BEN 
BLD - Reinforcing Insp  6/12/2018 2:14:43 PM  6/13/2018  8 AM - 12 PM  6/13/2018  BEN 
ELE - Underground conduit  6/12/2018 2:14:52 PM  6/13/2018  8 AM - 12 PM  6/13/2018  BEN 
BLD - Framing Insp.  6/12/2018 2:14:59 PM  6/13/2018  8 AM - 12 PM  6/13/2018  BEN 
BLD - Exterior Lath Insp  6/12/2018 2:15:07 PM  6/13/2018  8 AM - 12 PM  6/13/2018  BEN 
BLD - Footings Insp  6/12/2018 2:15:26 PM  6/13/2018  8 AM - 12 PM  6/13/2018  BEN 
BLD - Reinforcing Insp  6/13/2018 2:45:11 PM  6/14/2018  8 AM - 12 PM  6/14/2018  BEN 
ELE - Underground conduit  6/13/2018 2:45:30 PM  6/14/2018  8 AM - 12 PM  6/14/2018  BEN 
BLD - Framing Insp.  6/13/2018 2:45:40 PM  6/14/2018  8 AM - 12 PM  6/14/2018  BEN 
BLD - Exterior Lath Insp  6/13/2018 2:45:47 PM  6/14/2018  8 AM - 12 PM  6/14/2018  BEN 
BLD - Footings Insp  6/13/2018 2:46:07 PM  6/14/2018  8 AM - 12 PM  6/14/2018  BEN 
BLD - Reinforcing Insp  6/14/2018 3:58:03 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BEN 
ELE - Underground conduit  6/14/2018 3:58:24 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BEN 
BLD - Framing Insp.  6/14/2018 3:58:34 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BEN 
BLD - Exterior Lath Insp  6/14/2018 3:58:46 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BEN 
BLD - Reinforcing Insp  6/15/2018 10:45:53 AM  6/18/2018  8 AM - 12 PM  6/18/2018  GCT 
ELE - Underground conduit  6/15/2018 10:46:02 AM  6/18/2018  8 AM - 12 PM  6/18/2018  GCT 
BLD - Framing Insp.  6/15/2018 10:46:08 AM  6/18/2018  8 AM - 12 PM  6/18/2018  GCT 
BLD - Exterior Lath Insp  6/15/2018 10:46:25 AM  6/18/2018  8 AM - 12 PM  6/18/2018  GCT 
BLD -Floor Joists/Girders Insp  6/15/2018 11:48:01 AM  6/18/2018  8 AM - 12 PM  6/18/2018  GCT 
BLD - Framing Insp.  6/18/2018 2:16:18 PM  6/19/2018  10 AM - 2 PM  6/19/2018  BEN 
ELE - Rough Electrical  6/18/2018 2:16:27 PM  6/19/2018  10 AM - 2 PM  6/19/2018  BEN 
BLD - Footings Insp  6/18/2018 2:16:39 PM  6/19/2018  10 AM - 2 PM  6/19/2018  BEN 
ELE - Underground conduit  6/18/2018 2:16:46 PM  6/19/2018  10 AM - 2 PM  6/19/2018  BEN 
BLD -Floor Joists/Girders Insp  6/18/2018 2:17:05 PM  6/19/2018  10 AM - 2 PM  6/19/2018  BEN 
BLD - Reinforcing Insp  6/19/2018 2:27:06 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BEN 
ELE - Underground conduit  6/19/2018 2:27:20 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BEN 
BLD - Footings Insp  6/20/2018 1:21:03 PM  6/21/2018  12 PM - 3 PM  6/21/2018  BEN 
BLD - Pre-Slab Insp  6/20/2018 1:21:12 PM  6/21/2018  12 PM - 3 PM  6/21/2018  BEN 
ELE - Underground conduit  6/20/2018 1:21:29 PM  6/21/2018  12 PM - 3 PM  6/21/2018  BEN 
BLD - Pre-Slab Insp  6/21/2018 2:43:00 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
BLD - Reinforcing Insp  6/21/2018 2:43:09 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
ELE - Rough Electrical  6/21/2018 2:43:20 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
ELE - Underground conduit  6/21/2018 2:43:27 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
ELE - Ground Electrode/UFER  6/21/2018 2:43:41 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
BLD - Footings Insp  6/21/2018 4:43:23 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BEN 
BLD - Pre-Slab Insp  6/22/2018 11:28:48 AM  6/25/2018    6/25/2018  GCT 
BLD - Reinforcing Insp  6/22/2018 11:28:57 AM  6/25/2018    6/25/2018  GCT 
ELE - Underground conduit  6/22/2018 11:29:09 AM  6/25/2018    6/25/2018  GCT 
BLD - Reinforcing Insp  6/25/2018 1:40:32 PM  6/26/2018  12 PM - 3 PM  6/26/2018  BEN 
ELE - Underground conduit  6/25/2018 1:40:39 PM  6/26/2018  12 PM - 3 PM  6/26/2018  BEN 
BLD - Footings Insp  6/26/2018 2:41:31 PM  6/27/2018  12 PM - 3 PM  6/27/2018  BEN 
BLD - Reinforcing Insp  6/26/2018 2:41:43 PM  6/27/2018  12 PM - 3 PM  6/27/2018  BEN 
ELE - Underground conduit  6/26/2018 2:41:53 PM  6/27/2018  12 PM - 3 PM  6/27/2018  BEN 
BLD - Framing Insp.  6/26/2018 2:42:00 PM  6/27/2018  12 PM - 3 PM  6/27/2018  BEN 
BLD - Reinforcing Insp  6/27/2018 10:10:15 AM  6/28/2018  12 PM - 3 PM  6/28/2018  BEN 
BLD - Footings Insp  6/27/2018 10:10:23 AM  6/28/2018  12 PM - 3 PM  6/28/2018  BEN 
ELE - Underground conduit  6/27/2018 10:10:37 AM  6/28/2018  12 PM - 3 PM  6/28/2018  BEN 
BLD - Reinforcing Insp  6/27/2018 10:24:25 AM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
BLD - Footings Insp  6/27/2018 10:24:39 AM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
ELE - Underground conduit  6/27/2018 10:24:49 AM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
BLD - Framing Insp.  6/27/2018 2:31:53 PM  6/28/2018  12 PM - 3 PM  6/28/2018  BEN 
Approved Revision Structural  6/28/2018      7/3/2018  DONE  CSG 
Route Revision Structural  6/28/2018  7/17/2018    7/2/2018  APPR  CSG 
BLD - Framing Insp.  6/28/2018 11:38:53 AM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
BLD - Exterior Lath Insp  6/28/2018 11:39:01 AM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
BLD - Footings Insp  6/28/2018 11:40:13 AM  7/2/2018    7/2/2018  BEN 
BLD - Reinforcing Insp  6/28/2018 11:40:27 AM  7/2/2018    7/2/2018  BEN 
ELE - Underground conduit  6/28/2018 12:31:45 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BEN 
BLD - Exterior Lath Insp  6/28/2018 12:31:59 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BEN 
BLD - Framing Insp.  6/28/2018 12:32:08 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BEN 
ELE - Rough Electrical  6/28/2018 1:53:02 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BEN 
BLD - Footings Insp  7/2/2018 2:20:39 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
BLD - Reinforcing Insp  7/2/2018 2:20:45 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
ELE - Rough Electrical  7/2/2018 2:21:37 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
ELE - Underground conduit  7/2/2018 2:21:59 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
BLD - Framing Insp.  7/2/2018 2:22:11 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
BLD - Exterior Lath Insp  7/2/2018 2:22:18 PM  7/3/2018  8 AM - 12 PM  7/3/2018  BEN 
BLD - Reinforcing Insp  7/3/2018 1:04:47 PM  7/5/2018  12 PM - 3 PM  7/5/2018  BEN 
ELE - Underground conduit  7/3/2018 1:05:13 PM  7/5/2018  12 PM - 3 PM  7/5/2018  BEN 
BLD - Footings Insp  7/4/2018 10:13:32 PM  7/5/2018  12 PM - 3 PM  7/5/2018  BEN 
BLD - Pre-Slab Insp  7/4/2018 10:15:23 PM  7/5/2018  12 PM - 3 PM  7/5/2018  BEN 
BLD - Reinforcing Insp  7/5/2018 1:30:23 PM  7/6/2018  12 PM - 3 PM  7/6/2018  BEN 
ELE - Underground conduit  7/5/2018 1:30:35 PM  7/6/2018  12 PM - 3 PM  7/6/2018  BEN 
BLD - Exterior Lath Insp  7/5/2018 1:37:28 PM  7/6/2018  12 PM - 3 PM  7/6/2018  BEN 
BLD - Framing Insp.  7/5/2018 1:37:47 PM  7/6/2018  12 PM - 3 PM  7/6/2018  BEN 
BLD - Reinforcing Insp  7/6/2018 11:36:20 AM  7/9/2018    7/9/2018  GCT 
BLD - Footings Insp  7/6/2018 11:36:29 AM  7/9/2018    7/9/2018  GCT 
BLD - Pre-Slab Insp  7/6/2018 11:36:35 AM  7/9/2018    7/9/2018  GCT 
ELE - Underground conduit  7/6/2018 11:36:44 AM  7/9/2018    7/9/2018  GCT 
BLD - Footings Insp  7/9/2018 1:12:13 PM  7/10/2018  8 AM - 12 PM  7/10/2018  BEN 
BLD - Reinforcing Insp  7/9/2018 1:12:19 PM  7/10/2018  8 AM - 12 PM  7/10/2018  BEN 
ELE - Underground conduit  7/9/2018 1:12:27 PM  7/10/2018  8 AM - 12 PM  7/10/2018  BEN 
BLD - Reinforcing Insp  7/10/2018 2:14:09 PM  7/11/2018  12 PM - 3 PM  7/11/2018  BEN 
ELE - Underground conduit  7/10/2018 2:14:31 PM  7/11/2018  12 PM - 3 PM  7/11/2018  BEN 
BLD - Footings Insp  7/10/2018 2:14:44 PM  7/11/2018  12 PM - 3 PM  7/11/2018  BEN 
BLD - Reinforcing Insp  7/11/2018 2:27:55 PM  7/12/2018  12 PM - 3 PM  7/12/2018  BEN 
ELE - Underground conduit  7/11/2018 2:28:11 PM  7/12/2018  12 PM - 3 PM  7/12/2018  BEN 
BLD - Footings Insp  7/11/2018 2:44:17 PM  7/12/2018  12 PM - 3 PM  7/12/2018  BEN 
BLD - Reinforcing Insp  7/12/2018 2:38:52 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BEN 
BLD - Pre-Slab Insp  7/12/2018 2:41:39 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BEN 
ELE - Rough Electrical  7/12/2018 2:43:06 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BEN 
BLD - Framing Insp.  7/12/2018 2:43:38 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BEN 
BLD - Reinforcing Insp  7/13/2018 12:37:49 PM  7/16/2018  12 PM - 3 PM  7/16/2018  JOS 
ELE - Underground conduit  7/13/2018 12:38:03 PM  7/16/2018  12 PM - 3 PM  7/16/2018  JOS 
BLD - Footings Insp  7/16/2018 2:41:47 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BEN 
BLD - Reinforcing Insp  7/16/2018 2:42:03 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BEN 
ELE - Underground conduit  7/16/2018 2:42:28 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BEN 
BLD - Footings Insp  7/17/2018 1:35:17 PM  7/18/2018  12 PM - 3 PM  7/18/2018  BEN 
BLD - Reinforcing Insp  7/17/2018 1:35:33 PM  7/18/2018  12 PM - 3 PM  7/18/2018  BEN 
ELE - Underground conduit  7/17/2018 1:36:11 PM  7/18/2018  12 PM - 3 PM  7/18/2018  BEN 
BLD - Framing Insp.  7/17/2018 1:38:28 PM  7/18/2018  12 PM - 3 PM  7/18/2018  BEN 
BLD - Exterior Lath Insp  7/17/2018 1:38:35 PM  7/18/2018  12 PM - 3 PM  7/18/2018  BEN 
BLD - Footings Insp  7/18/2018 3:27:02 PM  7/19/2018  12 PM - 3 PM  7/19/2018  BEN 
BLD - Reinforcing Insp  7/18/2018 3:27:15 PM  7/19/2018  12 PM - 3 PM  7/19/2018  BEN 
ELE - Underground conduit  7/18/2018 3:27:23 PM  7/19/2018  12 PM - 3 PM  7/19/2018  BEN 
BLD - Framing Insp.  7/18/2018 3:27:31 PM  7/19/2018  12 PM - 3 PM  7/19/2018  BEN 
BLD - Exterior Lath Insp  7/18/2018 3:27:44 PM  7/19/2018  12 PM - 3 PM  7/19/2018  BEN 
BLD - Footings Insp  7/19/2018 2:21:27 PM  7/20/2018  8 AM - 12 PM  7/20/2018  BEN 
BLD - Reinforcing Insp  7/19/2018 2:21:42 PM  7/20/2018  8 AM - 12 PM  7/20/2018  BEN 
ELE - Underground conduit  7/19/2018 2:21:51 PM  7/20/2018  8 AM - 12 PM  7/20/2018  BEN 
BLD - Framing Insp.  7/19/2018 2:22:00 PM  7/20/2018  8 AM - 12 PM  7/20/2018  BEN 
BLD - Exterior Lath Insp  7/19/2018 2:23:48 PM  7/20/2018  8 AM - 12 PM  7/20/2018  BEN 
BLD - Footings Insp  7/20/2018 2:06:38 PM  7/23/2018  8 AM - 12 PM  7/23/2018  GCT 
BLD - Reinforcing Insp  7/20/2018 2:07:34 PM  7/23/2018  8 AM - 12 PM  7/23/2018  GCT 
BLD - Framing Insp.  7/20/2018 2:08:05 PM  7/23/2018  8 AM - 12 PM  7/23/2018  GCT 
BLD - Exterior Lath Insp  7/20/2018 2:08:10 PM  7/23/2018  8 AM - 12 PM  7/23/2018  GCT 
ELE - Underground conduit  7/20/2018 2:08:22 PM  7/23/2018  8 AM - 12 PM  7/23/2018  GCT 
BLD - Footings Insp  7/23/2018 10:54:49 AM  7/24/2018  12 PM - 3 PM  7/24/2018  BEN 
BLD - Reinforcing Insp  7/23/2018 10:54:56 AM  7/24/2018  12 PM - 3 PM  7/24/2018  BEN 
BLD - Framing Insp.  7/23/2018 10:55:07 AM  7/24/2018  12 PM - 3 PM  7/24/2018  BEN 
BLD - Exterior Lath Insp  7/23/2018 10:55:14 AM  7/24/2018  12 PM - 3 PM  7/24/2018  BEN 
ELE - Underground conduit  7/23/2018 10:55:23 AM  7/24/2018  12 PM - 3 PM  7/24/2018  BEN 
BLD - Footings Insp  7/24/2018 11:10:22 AM  7/25/2018  12 PM - 3 PM  7/25/2018  BEN 
BLD - Reinforcing Insp  7/24/2018 11:10:28 AM  7/25/2018  12 PM - 3 PM  7/25/2018  BEN 
ELE - Underground conduit  7/24/2018 11:10:58 AM  7/25/2018  12 PM - 3 PM  7/25/2018  BEN 
BLD - Framing Insp.  7/24/2018 11:11:04 AM  7/25/2018  12 PM - 3 PM  7/25/2018  BEN 
BLD - Exterior Lath Insp  7/24/2018 11:11:08 AM  7/25/2018  12 PM - 3 PM  7/25/2018  BEN 
BLD - Footings Insp  7/25/2018 12:01:29 PM  7/26/2018  8 AM - 12 PM  7/26/2018  BEN 
BLD - Reinforcing Insp  7/25/2018 12:01:42 PM  7/26/2018  8 AM - 12 PM  7/26/2018  BEN 
BLD - Framing Insp.  7/25/2018 12:01:53 PM  7/26/2018  8 AM - 12 PM  7/26/2018  BEN 
BLD - Exterior Lath Insp  7/25/2018 12:02:03 PM  7/26/2018  8 AM - 12 PM  7/26/2018  BEN 
ELE - Underground conduit  7/25/2018 12:02:12 PM  7/26/2018  8 AM - 12 PM  7/26/2018  BEN 
BLD - Footings Insp  7/26/2018 2:33:32 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BEN 
BLD - Reinforcing Insp  7/26/2018 2:33:42 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BEN 
ELE - Underground conduit  7/26/2018 2:33:56 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BEN 
BLD - Framing Insp.  7/26/2018 2:34:04 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BEN 
BLD - Exterior Lath Insp  7/26/2018 2:34:12 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BEN 
BLD - Footings Insp  7/27/2018 1:30:53 PM  7/30/2018    7/30/2018  GCT 
BLD - Reinforcing Insp  7/27/2018 1:31:01 PM  7/30/2018    7/30/2018  GCT 
ELE - Underground conduit  7/27/2018 1:31:31 PM  7/30/2018    7/30/2018  GCT 
BLD - Framing Insp.  7/27/2018 1:32:00 PM  7/30/2018    7/30/2018  GCT 
BLD - Drywall Inspection  7/27/2018 1:32:06 PM  7/30/2018    7/30/2018  GCT 
BLD - Exterior Lath Insp  7/27/2018 1:32:18 PM  7/30/2018    7/30/2018  GCT 
BLD - Footings Insp  7/30/2018 1:17:46 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
BLD - Reinforcing Insp  7/30/2018 1:17:55 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
BLD - Pre-Slab Insp  7/30/2018 1:18:02 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
ELE - Underground conduit  7/30/2018 1:19:20 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
BLD - Framing Insp.  7/30/2018 1:19:28 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
BLD - Exterior Lath Insp  7/30/2018 1:19:34 PM  7/31/2018  12 PM - 3 PM  7/31/2018  BEN 
BLD - Reinforcing Insp  7/31/2018 2:34:05 PM  8/1/2018  12 PM - 3 PM  8/1/2018  BEN 
ELE - Underground conduit  7/31/2018 2:34:16 PM  8/1/2018  12 PM - 3 PM  8/1/2018  BEN 
BLD - Footings Insp  8/1/2018 2:17:07 PM  8/2/2018  12 PM - 3 PM  8/2/2018  BEN 
BLD - Reinforcing Insp  8/1/2018 2:17:18 PM  8/2/2018  12 PM - 3 PM  8/2/2018  BEN 
ELE - Underground conduit  8/1/2018 2:17:32 PM  8/2/2018  12 PM - 3 PM  8/2/2018  BEN 
BLD - Framing Insp.  8/1/2018 2:35:23 PM  8/2/2018  12 PM - 3 PM  8/2/2018  BEN 
BLD - Exterior Lath Insp  8/1/2018 2:35:29 PM  8/2/2018  12 PM - 3 PM  8/2/2018  BEN 
BLD - Footings Insp  8/2/2018 1:39:27 PM  8/3/2018  8 AM - 12 PM  8/3/2018  BEN 
BLD - Reinforcing Insp  8/2/2018 1:39:37 PM  8/3/2018  8 AM - 12 PM  8/3/2018  BEN 
ELE - Underground conduit  8/2/2018 1:39:45 PM  8/3/2018  8 AM - 12 PM  8/3/2018  BEN 
BLD - Footings Insp  8/3/2018 2:45:54 PM  8/6/2018  8 AM - 12 PM  8/6/2018  GCT 
BLD - Reinforcing Insp  8/3/2018 2:46:02 PM  8/6/2018  8 AM - 12 PM  8/6/2018  GCT 
ELE - Underground conduit  8/3/2018 2:46:17 PM  8/6/2018  8 AM - 12 PM  8/6/2018  GCT 
BLD - Footings Insp  8/6/2018 12:05:16 PM  8/7/2018  8 AM - 12 PM  8/7/2018  BEN 
BLD - Reinforcing Insp  8/6/2018 12:05:22 PM  8/7/2018  8 AM - 12 PM  8/7/2018  BEN 
ELE - Underground conduit  8/6/2018 12:05:31 PM  8/7/2018  8 AM - 12 PM  8/7/2018  BEN 
BLD - Framing Insp.  8/6/2018 12:05:42 PM  8/7/2018  8 AM - 12 PM  8/7/2018  BEN 
BLD - Exterior Lath Insp  8/6/2018 12:05:51 PM  8/7/2018  8 AM - 12 PM  8/7/2018  BEN 
BLD - Footings Insp  8/7/2018 1:48:22 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BEN 
BLD - Reinforcing Insp  8/7/2018 1:48:31 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BEN 
ELE - Underground conduit  8/7/2018 1:48:39 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BEN 
BLD - Footings Insp  8/8/2018 3:32:11 PM  8/9/2018  12 PM - 3 PM  8/9/2018  BEN 
BLD - Reinforcing Insp  8/8/2018 3:32:21 PM  8/9/2018  12 PM - 3 PM  8/9/2018  BEN 
ELE - Underground conduit  8/8/2018 3:32:46 PM  8/9/2018  12 PM - 3 PM  8/9/2018  BEN 
BLD - Footings Insp  8/9/2018 12:10:11 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BEN 
BLD - Reinforcing Insp  8/9/2018 12:10:17 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BEN 
ELE - Underground conduit  8/9/2018 12:11:33 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BEN 
BLD - Footings Insp  8/10/2018 2:21:11 PM  8/13/2018  8 AM - 12 PM  8/13/2018  PJJ 
BLD - Reinforcing Insp  8/10/2018 2:21:19 PM  8/13/2018  8 AM - 12 PM  8/13/2018  PJJ 
ELE - Underground conduit  8/10/2018 2:21:26 PM  8/13/2018  8 AM - 12 PM  8/13/2018  PJJ 
BLD - Footings Insp  8/13/2018 9:52:29 AM  8/14/2018  12 PM - 3 PM  8/14/2018  BEN 
BLD - Reinforcing Insp  8/13/2018 9:52:35 AM  8/14/2018  12 PM - 3 PM  8/14/2018  BEN 
BLD - Framing Insp.  8/13/2018 9:52:43 AM  8/14/2018  12 PM - 3 PM  8/14/2018  BEN 
BLD - Exterior Lath Insp  8/13/2018 9:53:07 AM  8/14/2018  12 PM - 3 PM  8/14/2018  BEN 
ELE - Underground conduit  8/13/2018 9:53:51 AM  8/14/2018  12 PM - 3 PM  8/14/2018  BEN 
BLD - Framing Insp.  8/14/2018 2:24:08 PM  8/15/2018  12 PM - 3 PM  8/15/2018  BEN 
BLD - Exterior Lath Insp  8/14/2018 2:24:21 PM  8/15/2018  12 PM - 3 PM  8/15/2018  BEN 
BLD - Footings Insp  8/14/2018 2:24:33 PM  8/15/2018  12 PM - 3 PM  8/15/2018  BEN 
BLD - Reinforcing Insp  8/14/2018 2:24:40 PM  8/15/2018  12 PM - 3 PM  8/15/2018  BEN 
ELE - Underground conduit  8/14/2018 2:26:34 PM  8/15/2018  12 PM - 3 PM  8/15/2018  BEN 
BLD - Footings Insp  8/15/2018 11:12:29 AM  8/16/2018  12 PM - 3 PM  8/16/2018  BEN 
BLD - Reinforcing Insp  8/15/2018 11:12:37 AM  8/16/2018  12 PM - 3 PM  8/16/2018  BEN 
BLD - Framing Insp.  8/15/2018 11:13:05 AM  8/16/2018  12 PM - 3 PM  8/16/2018  BEN 
BLD - Exterior Lath Insp  8/15/2018 11:13:18 AM  8/16/2018  12 PM - 3 PM  8/16/2018  BEN 
ELE - Underground conduit  8/15/2018 11:13:32 AM  8/16/2018  12 PM - 3 PM  8/16/2018  BEN 
BLD - Framing Insp.  8/16/2018 1:28:49 PM  8/17/2018  12 PM - 3 PM  8/17/2018  BEN 
BLD - Exterior Lath Insp  8/16/2018 1:28:56 PM  8/17/2018  12 PM - 3 PM  8/17/2018  BEN 
ELE - Underground conduit  8/16/2018 1:29:03 PM  8/17/2018  12 PM - 3 PM  8/17/2018  BEN 
BLD - Footings Insp  8/16/2018 1:29:10 PM  8/17/2018  12 PM - 3 PM  8/17/2018  BEN 
BLD - Reinforcing Insp  8/16/2018 1:29:16 PM  8/17/2018  12 PM - 3 PM  8/17/2018  BEN 
BLD - Framing Insp.  8/16/2018 1:48:20 PM  8/20/2018    8/20/2018  PJJ 
BLD - Exterior Lath Insp  8/16/2018 1:48:30 PM  8/20/2018    8/20/2018  PJJ 
BLD - Footings Insp  8/16/2018 1:48:43 PM  8/20/2018    8/20/2018  PJJ 
BLD - Reinforcing Insp  8/16/2018 1:48:51 PM  8/20/2018    8/20/2018  PJJ 
ELE - Underground conduit  8/16/2018 1:49:00 PM  8/20/2018    8/20/2018  PJJ 
BLD - Footings Insp  8/20/2018 10:13:17 AM  8/21/2018  8 AM - 12 PM  8/21/2018  BEN 
BLD - Framing Insp.  8/20/2018 10:13:26 AM  8/21/2018  8 AM - 12 PM  8/21/2018  BEN 
BLD - Reinforcing Insp  8/20/2018 10:13:33 AM  8/21/2018  8 AM - 12 PM  8/21/2018  BEN 
BLD - Exterior Lath Insp  8/20/2018 10:13:39 AM  8/21/2018  8 AM - 12 PM  8/21/2018  BEN 
ELE - Underground conduit  8/20/2018 10:13:49 AM  8/21/2018  8 AM - 12 PM  8/21/2018  BEN 
BLD - Footings Insp  8/21/2018 8:28:03 AM  8/22/2018  8 AM - 12 PM  8/22/2018  BEN 
BLD - Reinforcing Insp  8/21/2018 8:28:20 AM  8/22/2018  8 AM - 12 PM  8/22/2018  BEN 
BLD - Framing Insp.  8/21/2018 8:28:29 AM  8/22/2018  8 AM - 12 PM  8/22/2018  BEN 
BLD - Exterior Lath Insp  8/21/2018 8:28:34 AM  8/22/2018  8 AM - 12 PM  8/22/2018  BEN 
ELE - Underground conduit  8/21/2018 8:29:04 AM  8/22/2018  8 AM - 12 PM  8/22/2018  BEN 
BLD - Footings Insp  8/22/2018 7:45:41 AM  8/23/2018  12 PM - 3 PM  8/23/2018  BEN 
BLD - Reinforcing Insp  8/22/2018 7:45:47 AM  8/23/2018  12 PM - 3 PM  8/23/2018  BEN 
ELE - Underground conduit  8/22/2018 7:45:56 AM  8/23/2018  12 PM - 3 PM  8/23/2018  BEN 
BLD - Exterior Lath Insp  8/22/2018 7:46:48 AM  8/23/2018  12 PM - 3 PM  8/23/2018  BEN 
BLD - Framing Insp.  8/22/2018 7:46:55 AM  8/23/2018  12 PM - 3 PM  8/23/2018  BEN 
BLD - Reinforcing Insp  8/23/2018 6:00:25 AM  8/24/2018  12 PM - 3 PM  8/24/2018  BEN 
BLD - Footings Insp  8/23/2018 6:00:33 AM  8/24/2018  12 PM - 3 PM  8/24/2018  BEN 
ELE - Underground conduit  8/23/2018 6:00:40 AM  8/24/2018  12 PM - 3 PM  8/24/2018  BEN 
BLD - Framing Insp.  8/23/2018 6:00:55 AM  8/24/2018  12 PM - 3 PM  8/24/2018  BEN 
BLD - Exterior Lath Insp  8/23/2018 6:01:02 AM  8/24/2018  12 PM - 3 PM  8/24/2018  BEN 
BLD - Footings Insp  8/26/2018 10:52:42 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
BLD - Reinforcing Insp  8/26/2018 10:52:55 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
ELE - Underground conduit  8/26/2018 10:53:10 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
BLD - Framing Insp.  8/26/2018 10:53:21 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
BLD - Exterior Lath Insp  8/26/2018 10:53:38 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
BLD -Floor Joists/Girders Insp  8/26/2018 10:57:33 AM  8/27/2018  8 AM - 12 PM  8/28/2018  GCT 
BLD - Reinforcing Insp  8/27/2018 9:57:45 AM  8/28/2018    8/28/2018  GCT 
BLD - Footings Insp  8/27/2018 9:57:53 AM  8/28/2018    8/28/2018  GCT 
ELE - Underground conduit  8/27/2018 9:58:07 AM  8/28/2018    8/28/2018  GCT 
BLD -Floor Joists/Girders Insp  8/27/2018 1:48:26 PM  8/28/2018    8/28/2018  GCT 
BLD - Reinforcing Insp  8/28/2018 2:48:25 PM  8/29/2018  12 PM - 3 PM  8/29/2018  BEN 
BLD - Footings Insp  8/28/2018 2:48:35 PM  8/29/2018  12 PM - 3 PM  8/29/2018  BEN 
ELE - Underground conduit  8/28/2018 2:48:45 PM  8/29/2018  12 PM - 3 PM  8/29/2018  BEN 
ELE - Underground conduit  8/29/2018 1:53:29 PM  8/30/2018  8 AM - 12 PM  8/30/2018  BEN 
BLD - Reinforcing Insp  8/29/2018 1:53:45 PM  8/30/2018  8 AM - 12 PM  8/30/2018  BEN 
BLD - Footings Insp  8/29/2018 1:53:53 PM  8/30/2018  8 AM - 12 PM  8/30/2018  BEN 
BLD - Exterior Lath Insp  8/29/2018 1:56:50 PM  8/30/2018  8 AM - 12 PM  8/30/2018  BEN 
ELE - Underground conduit  8/30/2018 10:15:29 AM  8/31/2018  8 AM - 12 PM  8/31/2018  BEN 
BLD - Reinforcing Insp  8/30/2018 10:15:43 AM  8/31/2018  8 AM - 12 PM  8/31/2018  BEN 
BLD - Footings Insp  8/30/2018 10:15:51 AM  8/31/2018  8 AM - 12 PM  8/31/2018  BEN 
BLD - Footings Insp  8/31/2018 10:37:33 AM  9/4/2018  8 AM - 12 PM  9/4/2018  PJJ 
BLD - Reinforcing Insp  8/31/2018 10:37:52 AM  9/4/2018  8 AM - 12 PM  9/4/2018  PJJ 
ELE - Underground conduit  8/31/2018 10:38:00 AM  9/4/2018  8 AM - 12 PM  9/4/2018  PJJ 
BLD - Footings Insp  9/4/2018 1:43:18 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BEN 
BLD - Reinforcing Insp  9/4/2018 1:43:26 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BEN 
ELE - Underground conduit  9/4/2018 1:43:32 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BEN 
BLD -Floor Joists/Girders Insp  9/4/2018 1:43:37 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BEN 
BLD - Footings Insp  9/5/2018 12:06:54 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BEN 
BLD - Reinforcing Insp  9/5/2018 12:07:01 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BEN 
ELE - Underground conduit  9/5/2018 12:07:12 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BEN 
BLD -Floor Joists/Girders Insp  9/5/2018 12:07:19 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BEN 
ELE - Underground conduit  9/6/2018 1:39:47 PM  9/7/2018  12 PM - 3 PM  9/7/2018  BEN 
BLD - Footings Insp  9/6/2018 1:49:27 PM  9/7/2018  12 PM - 3 PM  9/7/2018  BEN 
BLD - Reinforcing Insp  9/6/2018 1:50:13 PM  9/7/2018  12 PM - 3 PM  9/7/2018  BEN 
BLD -Floor Joists/Girders Insp  9/6/2018 1:50:48 PM  9/7/2018  12 PM - 3 PM  9/7/2018  BEN 
BLD - Footings Insp  9/7/2018 12:31:18 PM  9/10/2018  8 AM - 12 PM  9/10/2018  BEN 
BLD - Reinforcing Insp  9/7/2018 12:31:23 PM  9/10/2018  8 AM - 12 PM  9/10/2018  BEN 
ELE - Underground conduit  9/7/2018 12:31:31 PM  9/10/2018  8 AM - 12 PM  9/10/2018  BEN 
BLD - Framing Insp.  9/7/2018 1:11:01 PM  9/10/2018  8 AM - 12 PM  9/10/2018  BEN 
BLD - Exterior Lath Insp  9/7/2018 1:11:09 PM  9/10/2018  8 AM - 12 PM  9/10/2018  BEN 
BLD - Reinforcing Insp  9/10/2018 2:36:15 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BEN 
BLD - Footings Insp  9/10/2018 2:36:21 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BEN 
ELE - Underground conduit  9/10/2018 2:36:29 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BEN 
BLD - Framing Insp.  9/10/2018 2:36:38 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BEN 
BLD - Exterior Lath Insp  9/10/2018 2:36:47 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BEN 
BLD - Footings Insp  9/11/2018 3:29:30 PM  9/12/2018  8 AM - 12 PM  9/12/2018  BEN 
BLD - Pre-Slab Insp  9/11/2018 3:30:06 PM  9/12/2018  8 AM - 12 PM  9/12/2018  BEN 
BLD - Framing Insp.  9/11/2018 3:30:20 PM  9/12/2018  8 AM - 12 PM  9/12/2018  BEN 
BLD - Exterior Lath Insp  9/11/2018 3:30:35 PM  9/12/2018  8 AM - 12 PM  9/12/2018  BEN 
ELE - Underground conduit  9/11/2018 3:31:31 PM  9/12/2018  8 AM - 12 PM  9/12/2018  BEN 
BLD - Footings Insp  9/12/2018 2:33:08 PM  9/13/2018  12 PM - 3 PM  9/13/2018  BEN 
BLD - Pre-Slab Insp  9/12/2018 2:33:20 PM  9/13/2018  12 PM - 3 PM  9/13/2018  BEN 
ELE - Underground conduit  9/12/2018 2:33:27 PM  9/13/2018  12 PM - 3 PM  9/13/2018  BEN 
BLD - Framing Insp.  9/12/2018 2:33:42 PM  9/13/2018  12 PM - 3 PM  9/13/2018  BEN 
BLD - Exterior Lath Insp  9/12/2018 2:33:53 PM  9/13/2018  12 PM - 3 PM  9/13/2018  BEN 
MEC - Underground Rough  9/13/2018 10:05:23 AM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
PLM - Ground/Underfloor water  9/13/2018 10:05:34 AM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
ELE - Underground conduit  9/13/2018 10:06:04 AM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
BLD - Footings Insp  9/13/2018 10:06:12 AM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
BLD - Pre-Slab Insp  9/13/2018 10:06:20 AM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
BLD - Framing Insp.  9/13/2018 1:15:49 PM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
BLD - Exterior Lath Insp  9/13/2018 1:15:57 PM  9/14/2018  8 AM - 12 PM  9/14/2018  BEN 
BLD - Footings Insp  9/14/2018 12:34:07 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
BLD - Reinforcing Insp  9/14/2018 12:34:13 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
ELE - Underground conduit  9/14/2018 12:34:29 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
BLD - Framing Insp.  9/14/2018 12:40:49 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
BLD - Exterior Lath Insp  9/14/2018 12:40:57 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
BLD -Floor Joists/Girders Insp  9/16/2018 8:21:04 PM  9/17/2018  8 AM - 12 PM  9/17/2018  PJJ 
BLD - Reinforcing Insp  9/17/2018 11:05:59 AM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD - Footings Insp  9/17/2018 11:06:05 AM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
ELE - Underground conduit  9/17/2018 11:06:18 AM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD - Framing Insp.  9/17/2018 2:34:38 PM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD - Pre-Slab Insp  9/17/2018 2:35:54 PM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD - Exterior Lath Insp  9/17/2018 2:36:12 PM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD -Floor Joists/Girders Insp  9/17/2018 2:39:54 PM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
PLM - Ground/Underfloor waste  9/17/2018 2:42:53 PM  9/18/2018  8 AM - 12 PM  9/18/2018  BEN 
BLD - Reinforcing Insp  9/18/2018 3:42:25 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
BLD - Footings Insp  9/18/2018 3:42:51 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
BLD - Pre-Slab Insp  9/18/2018 3:43:04 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
ELE - Underground conduit  9/18/2018 3:43:19 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
BLD - Framing Insp.  9/18/2018 3:43:28 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
BLD - Exterior Lath Insp  9/18/2018 3:43:37 PM  9/19/2018  8 AM - 12 PM  9/19/2018  BEN 
BLD - Reinforcing Insp  9/19/2018 2:11:08 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
BLD - Footings Insp  9/19/2018 2:11:17 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
BLD - Pre-Slab Insp  9/19/2018 2:11:24 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
ELE - Rough Electrical  9/19/2018 2:11:33 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
BLD - Framing Insp.  9/19/2018 2:11:45 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
BLD - Exterior Lath Insp  9/19/2018 2:11:55 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BEN 
BLD - Footings Insp  9/20/2018 12:57:13 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
BLD - Pre-Slab Insp  9/20/2018 12:57:23 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
ELE - Underground conduit  9/20/2018 12:57:32 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
BLD - Framing Insp.  9/20/2018 2:55:02 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
BLD - Exterior Lath Insp  9/20/2018 2:55:09 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
BLD -Floor Joists/Girders Insp  9/20/2018 2:55:32 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
PLM - Ground/Underfloor waste  9/20/2018 2:56:18 PM  9/21/2018  8 AM - 12 PM  9/21/2018  BEN 
BLD - Footings Insp  9/23/2018 10:15:49 AM  9/24/2018  8 AM - 12 PM  9/24/2018  PJJ 
BLD - Pre-Slab Insp  9/23/2018 10:15:57 AM  9/24/2018  8 AM - 12 PM  9/24/2018  PJJ 
ELE - Underground conduit  9/23/2018 10:16:12 AM  9/24/2018  8 AM - 12 PM  9/24/2018  PJJ 
BLD - Framing Insp.  9/23/2018 10:16:24 AM  9/24/2018  8 AM - 12 PM  9/24/2018  PJJ 
BLD - Exterior Lath Insp  9/23/2018 10:16:33 AM  9/24/2018  8 AM - 12 PM  9/24/2018  PJJ 
PLM - Ground/Underfloor waste  9/24/2018 1:56:50 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Footings Insp  9/24/2018 1:56:59 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Pre-Slab Insp  9/24/2018 1:57:24 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
ELE - Underground conduit  9/24/2018 1:57:36 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Framing Insp.  9/24/2018 1:57:44 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Exterior Lath Insp  9/24/2018 1:57:51 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Reinforcing Insp  9/24/2018 1:58:19 PM  9/25/2018  12 PM - 3 PM  9/25/2018  BEN 
BLD - Footings Insp  9/25/2018 12:08:37 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
BLD - Pre-Slab Insp  9/25/2018 12:08:45 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
BLD - Reinforcing Insp  9/25/2018 12:08:52 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
ELE - Underground conduit  9/25/2018 12:09:03 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
BLD - Framing Insp.  9/25/2018 12:09:11 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
BLD - Exterior Lath Insp  9/25/2018 12:09:18 PM  9/26/2018  12 PM - 3 PM  9/26/2018  BEN 
BLD - Footings Insp  9/26/2018 2:14:40 PM  9/27/2018  12 PM - 3 PM  9/27/2018  BEN 
BLD - Reinforcing Insp  9/26/2018 2:14:48 PM  9/27/2018  12 PM - 3 PM  9/27/2018  BEN 
ELE - Underground conduit  9/26/2018 2:15:03 PM  9/27/2018  12 PM - 3 PM  9/27/2018  BEN 
BLD - Framing Insp.  9/26/2018 2:15:11 PM  9/27/2018  12 PM - 3 PM  9/27/2018  BEN 
BLD - Exterior Lath Insp  9/26/2018 2:15:20 PM  9/27/2018  12 PM - 3 PM  9/27/2018  BEN 
BLD - Footings Insp  9/27/2018 2:22:23 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
BLD - Pre-Slab Insp  9/27/2018 2:22:31 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
ELE - Underground conduit  9/27/2018 2:22:41 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
BLD - Framing Insp.  9/27/2018 2:23:21 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
BLD - Exterior Lath Insp  9/27/2018 2:23:34 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
BLD - Reinforcing Insp  9/27/2018 2:23:40 PM  9/28/2018  12 PM - 3 PM  9/28/2018  BEN 
BLD - Footings Insp  9/30/2018 8:41:47 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
BLD - Pre-Slab Insp  9/30/2018 8:41:58 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
BLD - Reinforcing Insp  9/30/2018 8:42:09 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
BLD - Framing Insp.  9/30/2018 8:42:18 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
BLD - Exterior Lath Insp  9/30/2018 8:42:31 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
ELE - Underground conduit  9/30/2018 8:43:14 AM  10/1/2018  8 AM - 12 PM  10/1/2018  PJJ 
BLD - Framing Insp.  10/1/2018 2:47:34 PM  10/2/2018    10/2/2018  GCT 
BLD - Exterior Lath Insp  10/1/2018 2:47:46 PM  10/2/2018    10/2/2018  GCT 
BLD - Pre-Slab Insp  10/1/2018 2:48:13 PM  10/2/2018    10/2/2018  GCT 
BLD - Reinforcing Insp  10/1/2018 2:48:21 PM  10/2/2018    10/2/2018  GCT 
ELE - Underground conduit  10/1/2018 2:48:46 PM  10/2/2018    10/2/2018  GCT 
BLD - Footings Insp  10/2/2018 3:18:28 PM  10/3/2018  8 AM - 12 PM  10/3/2018  PJJ 
BLD - Pre-Slab Insp  10/2/2018 3:18:43 PM  10/3/2018  8 AM - 12 PM  10/3/2018  PJJ 
ELE - Underground conduit  10/2/2018 3:19:08 PM  10/3/2018  8 AM - 12 PM  10/3/2018  PJJ 
BLD - Framing Insp.  10/2/2018 3:19:20 PM  10/3/2018  8 AM - 12 PM  10/3/2018  PJJ 
BLD - Exterior Lath Insp  10/2/2018 3:19:31 PM  10/3/2018  8 AM - 12 PM  10/3/2018  PJJ 
BLD - Footings Insp  10/3/2018 2:47:07 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
BLD - Reinforcing Insp  10/3/2018 2:47:50 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
BLD - Pre-Slab Insp  10/3/2018 2:47:57 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
ELE - Rough Electrical  10/3/2018 2:48:16 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
BLD - Framing Insp.  10/3/2018 2:48:24 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
BLD - Exterior Lath Insp  10/3/2018 2:48:33 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BEN 
BLD - Footings Insp  10/4/2018 10:59:50 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
BLD - Pre-Slab Insp  10/4/2018 11:00:01 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
BLD - Reinforcing Insp  10/4/2018 11:00:09 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
ELE - Underground conduit  10/4/2018 11:00:32 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
BLD - Framing Insp.  10/4/2018 11:00:43 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
BLD - Exterior Lath Insp  10/4/2018 11:00:48 AM  10/5/2018  12 PM - 3 PM  10/5/2018  BEN 
BLD - Footings Insp  10/5/2018 10:03:53 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Reinforcing Insp  10/5/2018 10:03:59 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Pre-Slab Insp  10/5/2018 10:04:06 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
ELE - Underground conduit  10/5/2018 10:04:14 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Framing Insp.  10/5/2018 10:04:45 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Exterior Lath Insp  10/5/2018 10:04:51 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
PLM - Sewer  10/7/2018 2:54:37 PM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Footings Insp  10/8/2018 1:40:18 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
BLD - Pre-Slab Insp  10/8/2018 1:40:50 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
BLD - Reinforcing Insp  10/8/2018 1:40:57 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
BLD - Framing Insp.  10/8/2018 1:41:07 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
BLD - Exterior Lath Insp  10/8/2018 1:41:13 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
ELE - Underground conduit  10/8/2018 1:41:21 PM  10/9/2018  8 AM - 12 PM  10/9/2018  BEN 
BLD - Footings Insp  10/9/2018 2:00:02 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
BLD - Pre-Slab Insp  10/9/2018 2:00:12 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
BLD - Reinforcing Insp  10/9/2018 2:00:21 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
ELE - Underground conduit  10/9/2018 2:00:30 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
BLD - Framing Insp.  10/9/2018 2:00:38 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
BLD - Exterior Lath Insp  10/9/2018 2:00:43 PM  10/10/2018  8 AM - 12 PM  10/10/2018  BEN 
BLD - Footings Insp  10/10/2018 2:28:17 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD - Pre-Slab Insp  10/10/2018 2:28:30 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD - Reinforcing Insp  10/10/2018 2:28:35 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
ELE - Underground conduit  10/10/2018 2:28:43 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD - Framing Insp.  10/10/2018 2:29:38 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD - Exterior Lath Insp  10/10/2018 2:29:46 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD -Floor Joists/Girders Insp  10/10/2018 2:30:10 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BEN 
BLD - Footings Insp  10/11/2018 11:35:22 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
BLD - Pre-Slab Insp  10/11/2018 11:35:29 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
BLD - Reinforcing Insp  10/11/2018 11:35:36 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
ELE - Underground conduit  10/11/2018 11:39:11 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
BLD - Framing Insp.  10/11/2018 11:39:21 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
BLD - Exterior Lath Insp  10/11/2018 11:39:28 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
PLM - Ground/Underfloor water  10/11/2018 11:39:41 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
MEC - Underground Rough  10/11/2018 11:39:48 AM  10/12/2018  12 PM - 3 PM  10/12/2018  BEN 
BLD - Footings Insp  10/14/2018 3:06:34 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
BLD - Pre-Slab Insp  10/14/2018 3:06:59 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
BLD - Reinforcing Insp  10/14/2018 3:07:40 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
ELE - Underground conduit  10/14/2018 3:09:28 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
BLD - Framing Insp.  10/14/2018 3:09:48 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
BLD - Exterior Lath Insp  10/14/2018 3:09:57 PM  10/15/2018  8 AM - 12 PM  10/15/2018  PJJ 
BLD - Footings Insp  10/15/2018 1:56:53 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
BLD - Reinforcing Insp  10/15/2018 1:57:01 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
BLD - Pre-Slab Insp  10/15/2018 1:57:07 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
ELE - Underground conduit  10/15/2018 1:57:21 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
BLD - Framing Insp.  10/15/2018 1:57:37 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
BLD - Exterior Lath Insp  10/15/2018 1:57:49 PM  10/16/2018  12 PM - 3 PM  10/16/2018  BEN 
BLD - Footings Insp  10/16/2018 11:41:32 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
BLD - Pre-Slab Insp  10/16/2018 11:41:39 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
BLD - Reinforcing Insp  10/16/2018 11:41:47 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
BLD - Framing Insp.  10/16/2018 11:41:53 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
BLD - Exterior Lath Insp  10/16/2018 11:42:02 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
ELE - Underground conduit  10/16/2018 11:42:13 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
PLM - Ground/Underfloor water  10/16/2018 2:33:36 PM  10/17/2018  12 PM - 3 PM  10/17/2018  BEN 
BLD - Footings Insp  10/17/2018 1:12:36 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
BLD - Pre-Slab Insp  10/17/2018 1:12:47 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
BLD - Reinforcing Insp  10/17/2018 1:12:55 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
BLD - Framing Insp.  10/17/2018 1:13:02 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
BLD - Exterior Lath Insp  10/17/2018 1:13:09 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
ELE - Underground conduit  10/17/2018 1:13:19 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BEN 
BLD - Footings Insp  10/18/2018 10:32:45 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
BLD - Reinforcing Insp  10/18/2018 10:33:40 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
BLD - Pre-Slab Insp  10/18/2018 10:33:46 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
ELE - Underground conduit  10/18/2018 10:33:53 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
BLD - Framing Insp.  10/18/2018 10:34:28 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
BLD - Exterior Lath Insp  10/18/2018 10:34:35 AM  10/19/2018  8 AM - 12 PM  10/19/2018  BEN 
BLD - Footings Insp  10/19/2018 12:55:55 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
BLD - Pre-Slab Insp  10/19/2018 12:56:03 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
BLD - Reinforcing Insp  10/19/2018 12:56:09 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
ELE - Rough Electrical  10/19/2018 12:56:51 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
BLD - Framing Insp.  10/21/2018 4:14:35 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
BLD - Exterior Lath Insp  10/21/2018 4:14:43 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
ELE - Underground conduit  10/21/2018 4:15:02 PM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
BLD - Footings Insp  10/22/2018 12:47:39 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
BLD - Pre-Slab Insp  10/22/2018 12:47:46 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
BLD - Reinforcing Insp  10/22/2018 12:47:51 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
ELE - Underground conduit  10/22/2018 12:47:59 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
BLD - Framing Insp.  10/22/2018 12:48:06 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
BLD - Exterior Lath Insp  10/22/2018 12:48:10 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
PLM - Sewer  10/22/2018 12:48:26 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
PLM - Ground/Underfloor waste  10/22/2018 12:48:33 PM  10/23/2018  12 PM - 3 PM  10/23/2018  BEN 
BLD - Footings Insp  10/23/2018 2:19:58 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
BLD - Reinforcing Insp  10/23/2018 2:20:05 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
BLD - Pre-Slab Insp  10/23/2018 2:20:12 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
ELE - Underground conduit  10/23/2018 2:22:20 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
BLD - Framing Insp.  10/23/2018 2:23:09 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
BLD - Exterior Lath Insp  10/23/2018 2:23:35 PM  10/24/2018  8 AM - 12 PM  10/24/2018  BEN 
BLD - Footings Insp  10/24/2018 1:41:50 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
BLD - Pre-Slab Insp  10/24/2018 1:41:57 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
BLD - Reinforcing Insp  10/24/2018 1:42:04 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
ELE - Underground conduit  10/24/2018 1:42:44 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
BLD - Framing Insp.  10/24/2018 1:42:52 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
BLD - Exterior Lath Insp  10/24/2018 1:42:59 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BEN 
BLD - Footings Insp  10/25/2018 1:31:00 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
BLD - Reinforcing Insp  10/25/2018 1:31:06 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
BLD - Pre-Slab Insp  10/25/2018 1:31:11 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
ELE - Underground conduit  10/25/2018 1:31:52 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
BLD - Framing Insp.  10/25/2018 1:32:27 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
BLD - Exterior Lath Insp  10/25/2018 1:32:37 PM  10/26/2018  8 AM - 12 PM  10/26/2018  BEN 
BLD - Footings Insp  10/26/2018 10:36:29 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Pre-Slab Insp  10/26/2018 10:36:35 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Reinforcing Insp  10/26/2018 10:36:41 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
ELE - Underground conduit  10/26/2018 10:36:49 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Framing Insp.  10/26/2018 10:38:36 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Exterior Lath Insp  10/26/2018 10:38:43 AM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Footings Insp  10/29/2018 1:43:50 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
BLD - Reinforcing Insp  10/29/2018 1:43:57 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
BLD - Pre-Slab Insp  10/29/2018 1:44:28 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
ELE - Underground conduit  10/29/2018 1:44:37 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
BLD - Framing Insp.  10/29/2018 1:44:44 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
BLD - Exterior Lath Insp  10/29/2018 1:44:50 PM  10/30/2018  8 AM - 12 PM  10/30/2018  BEN 
BLD - Pre-Slab Insp  10/30/2018 12:56:18 PM  10/31/2018  8 AM - 12 PM  10/31/2018  BEN 
BLD - Footings Insp  10/30/2018 12:56:29 PM  10/31/2018  8 AM - 12 PM  10/31/2018  BEN 
BLD - Reinforcing Insp  10/30/2018 12:56:42 PM  10/31/2018  8 AM - 12 PM  10/31/2018  BEN 
ELE - Underground conduit  10/30/2018 12:57:23 PM  10/31/2018  8 AM - 12 PM  10/31/2018  BEN 
BLD - Footings Insp  10/31/2018 1:33:01 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BEN 
BLD - Pre-Slab Insp  10/31/2018 1:33:29 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BEN 
BLD - Reinforcing Insp  10/31/2018 1:33:35 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BEN 
ELE - Underground conduit  10/31/2018 1:33:51 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BEN 
BLD - Footings Insp  11/1/2018 10:02:23 AM  11/2/2018  8 AM - 12 PM  11/2/2018  BEN 
BLD - Pre-Slab Insp  11/1/2018 10:02:31 AM  11/2/2018  8 AM - 12 PM  11/2/2018  BEN 
BLD - Reinforcing Insp  11/1/2018 10:02:37 AM  11/2/2018  8 AM - 12 PM  11/2/2018  BEN 
ELE - Underground conduit  11/1/2018 10:02:45 AM  11/2/2018  8 AM - 12 PM  11/2/2018  BEN 
ELE - Ground Electrode/UFER  11/1/2018 12:27:05 PM  11/2/2018  8 AM - 12 PM  11/2/2018  BEN 
BLD - Footings Insp  11/4/2018 12:56:38 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
BLD - Pre-Slab Insp  11/4/2018 12:56:50 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
BLD - Reinforcing Insp  11/4/2018 12:57:12 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
ELE - Underground conduit  11/4/2018 12:57:26 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
ELE - Ground Electrode/UFER  11/4/2018 12:58:48 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
PLM - Ground/Underfloor water  11/4/2018 2:48:54 PM  11/5/2018  8 AM - 12 PM  11/5/2018  PJJ 
BLD - Footings Insp  11/5/2018 1:32:22 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
BLD - Pre-Slab Insp  11/5/2018 1:32:28 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
ELE - Ground Electrode/UFER  11/5/2018 1:32:36 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
ELE - Underground conduit  11/5/2018 1:32:43 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
BLD - Reinforcing Insp  11/5/2018 1:32:49 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
PLM - Ground/Underfloor water  11/5/2018 1:32:59 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
BLD -Floor Joists/Girders Insp  11/5/2018 2:55:36 PM  11/6/2018  12 PM - 3 PM  11/6/2018  BEN 
BLD - Footings Insp  11/6/2018 2:17:32 PM  11/7/2018    11/7/2018  PJJ 
BLD - Reinforcing Insp  11/6/2018 2:17:40 PM  11/7/2018    11/7/2018  PJJ 
BLD - Pre-Slab Insp  11/6/2018 2:17:46 PM  11/7/2018    11/7/2018  PJJ 
ELE - Ground Electrode/UFER  11/6/2018 2:17:55 PM  11/7/2018    11/7/2018  PJJ 
ELE - Underground conduit  11/6/2018 2:18:04 PM  11/7/2018    11/7/2018  PJJ 
BLD - Framing Insp.  11/6/2018 2:18:29 PM  11/7/2018    11/7/2018  PJJ 
BLD - Exterior Lath Insp  11/6/2018 2:18:36 PM  11/7/2018    11/7/2018  PJJ 
BLD - Footings Insp  11/7/2018 1:57:24 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
BLD - Pre-Slab Insp  11/7/2018 1:57:37 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
BLD - Reinforcing Insp  11/7/2018 1:57:43 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
ELE - Underground conduit  11/7/2018 1:57:51 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
ELE - Ground Electrode/UFER  11/7/2018 1:58:05 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
BLD - Framing Insp.  11/7/2018 1:58:15 PM  11/8/2018  8 AM - 12 PM  11/8/2018  PJJ 
BLD - Footings Insp  11/8/2018 10:14:56 AM  11/9/2018  8 AM - 12 PM  11/9/2018  BEN 
BLD - Pre-Slab Insp  11/8/2018 10:15:03 AM  11/9/2018  8 AM - 12 PM  11/9/2018  BEN 
BLD - Reinforcing Insp  11/8/2018 10:15:13 AM  11/9/2018  8 AM - 12 PM  11/9/2018  BEN 
ELE - Ground Electrode/UFER  11/8/2018 10:15:23 AM  11/9/2018  8 AM - 12 PM  11/9/2018  BEN 
ELE - Underground conduit  11/8/2018 10:15:50 AM  11/9/2018  8 AM - 12 PM  11/9/2018  BEN 
BLD - Footings Insp  11/9/2018 10:03:48 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
BLD - Pre-Slab Insp  11/9/2018 10:03:54 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
BLD - Reinforcing Insp  11/9/2018 10:04:04 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
ELE - Ground Electrode/UFER  11/9/2018 10:04:15 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
ELE - Underground conduit  11/9/2018 10:04:26 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
BLD -Floor Joists/Girders Insp  11/9/2018 10:04:43 AM  11/13/2018  8 AM - 12 PM  11/13/2018  PJJ 
BLD - Footings Insp  11/13/2018 12:03:57 PM  11/14/2018  12 PM - 3 PM  11/14/2018  BEN 
BLD - Pre-Slab Insp  11/13/2018 12:04:04 PM  11/14/2018  12 PM - 3 PM  11/14/2018  BEN 
BLD - Reinforcing Insp  11/13/2018 12:04:10 PM  11/14/2018  12 PM - 3 PM  11/14/2018  BEN 
ELE - Underground conduit  11/13/2018 12:08:02 PM  11/14/2018  12 PM - 3 PM  11/14/2018  BEN 
ELE - Ground Electrode/UFER  11/13/2018 12:08:10 PM  11/14/2018  12 PM - 3 PM  11/14/2018  BEN 
BLD - Pre-Slab Insp  11/14/2018 2:58:35 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
BLD - Footings Insp  11/14/2018 2:58:48 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
BLD - Reinforcing Insp  11/14/2018 2:58:55 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
ELE - Ground Electrode/UFER  11/14/2018 2:59:14 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
ELE - Underground conduit  11/14/2018 2:59:26 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
BLD -Floor Joists/Girders Insp  11/14/2018 2:59:39 PM  11/15/2018  12 PM - 3 PM  11/15/2018  BEN 
BLD - Pre-Slab Insp  11/15/2018 1:30:59 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BEN 
BLD - Footings Insp  11/15/2018 1:31:12 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BEN 
BLD - Reinforcing Insp  11/15/2018 1:31:19 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BEN 
ELE - Underground conduit  11/15/2018 1:31:28 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BEN 
ELE - Ground Electrode/UFER  11/15/2018 1:32:08 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BEN 
BLD - Footings Insp  11/16/2018 11:20:31 AM  11/19/2018  10 AM - 2 PM  11/19/2018  GCT 
BLD - Pre-Slab Insp  11/16/2018 11:20:38 AM  11/19/2018  10 AM - 2 PM  11/19/2018  GCT 
BLD - Reinforcing Insp  11/16/2018 11:20:50 AM  11/19/2018  10 AM - 2 PM  11/19/2018  GCT 
ELE - Ground Electrode/UFER  11/16/2018 11:20:57 AM  11/19/2018  10 AM - 2 PM  11/19/2018  GCT 
ELE - Underground conduit  11/16/2018 11:21:13 AM  11/19/2018  10 AM - 2 PM  11/19/2018  GCT 
BLD - Footings Insp  11/19/2018 11:16:48 AM  11/20/2018    11/20/2018  BEN 
BLD - Pre-Slab Insp  11/19/2018 11:17:22 AM  11/20/2018    11/20/2018  BEN 
BLD - Reinforcing Insp  11/19/2018 11:17:34 AM  11/20/2018    11/20/2018  BEN 
ELE - Ground Electrode/UFER  11/19/2018 11:18:08 AM  11/20/2018    11/20/2018  BEN 
ELE - Underground conduit  11/19/2018 11:18:16 AM  11/20/2018    11/20/2018  BEN 
BLD -Floor Joists/Girders Insp  11/19/2018 11:18:37 AM  11/20/2018    11/20/2018  BEN 
BLD - Footings Insp  11/20/2018 5:58:11 AM  11/21/2018  8 AM - 12 PM  11/21/2018  BEN 
BLD - Pre-Slab Insp  11/20/2018 5:58:29 AM  11/21/2018  8 AM - 12 PM  11/21/2018  BEN 
BLD - Reinforcing Insp  11/20/2018 5:58:36 AM  11/21/2018  8 AM - 12 PM  11/21/2018  BEN 
ELE - Underground conduit  11/20/2018 5:58:48 AM  11/21/2018  8 AM - 12 PM  11/21/2018  BEN 
ELE - Ground Electrode/UFER  11/20/2018 5:58:56 AM  11/21/2018  8 AM - 12 PM  11/21/2018  BEN 
BLD - Footings Insp  11/21/2018 6:09:08 AM  11/26/2018    11/29/2018  PJJ 
BLD - Pre-Slab Insp  11/21/2018 6:09:15 AM  11/26/2018    11/29/2018  PJJ 
BLD - Reinforcing Insp  11/21/2018 6:09:22 AM  11/26/2018    11/29/2018  PJJ 
ELE - Ground Electrode/UFER  11/21/2018 6:09:30 AM  11/26/2018    11/29/2018  PJJ 
ELE - Underground conduit  11/21/2018 6:09:39 AM  11/26/2018    11/29/2018  PJJ 
BLD -Floor Joists/Girders Insp  11/21/2018 6:09:52 AM  11/26/2018    11/29/2018  PJJ 
BLD - Footings Insp  11/26/2018 12:28:15 PM  11/27/2018  8 AM - 12 PM  11/27/2018  BEN 
BLD - Pre-Slab Insp  11/26/2018 12:28:21 PM  11/27/2018  8 AM - 12 PM  11/27/2018  BEN 
BLD - Reinforcing Insp  11/26/2018 12:28:29 PM  11/27/2018  8 AM - 12 PM  11/27/2018  BEN 
ELE - Ground Electrode/UFER  11/26/2018 12:28:45 PM  11/27/2018  8 AM - 12 PM  11/27/2018  BEN 
ELE - Rough Electrical  11/26/2018 12:28:56 PM  11/27/2018  8 AM - 12 PM  11/27/2018  BEN 
BLD - Footings Insp  11/27/2018 11:16:47 AM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
BLD - Pre-Slab Insp  11/27/2018 11:17:01 AM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
BLD - Reinforcing Insp  11/27/2018 11:17:09 AM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
ELE - Ground Electrode/UFER  11/27/2018 11:17:17 AM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
ELE - Underground conduit  11/27/2018 11:17:27 AM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
ELE - Rough Electrical  11/27/2018 2:26:38 PM  11/28/2018  8 AM - 12 PM  11/28/2018  BEN 
BLD - Footings Insp  11/28/2018 11:31:04 AM  11/29/2018  8 AM - 12 PM  11/29/2018  BEN 
BLD - Reinforcing Insp  11/28/2018 11:31:18 AM  11/29/2018  8 AM - 12 PM  11/29/2018  BEN 
BLD - Pre-Slab Insp  11/28/2018 11:32:20 AM  11/29/2018  8 AM - 12 PM  11/29/2018  BEN 
ELE - Ground Electrode/UFER  11/28/2018 11:32:31 AM  11/29/2018  8 AM - 12 PM  11/29/2018  BEN 
ELE - Underground conduit  11/28/2018 11:32:39 AM  11/29/2018  8 AM - 12 PM  11/29/2018  BEN 
BLD - Footings Insp  11/29/2018 12:13:19 PM  11/30/2018  12 PM - 3 PM  11/30/2018  BEN 
BLD - Pre-Slab Insp  11/29/2018 12:13:26 PM  11/30/2018  12 PM - 3 PM  11/30/2018  BEN 
BLD - Reinforcing Insp  11/29/2018 12:14:16 PM  11/30/2018  12 PM - 3 PM  11/30/2018  BEN 
ELE - Ground Electrode/UFER  11/29/2018 12:14:54 PM  11/30/2018  12 PM - 3 PM  11/30/2018  BEN 
ELE - Rough Electrical  11/29/2018 12:15:06 PM  11/30/2018  12 PM - 3 PM  11/30/2018  BEN 
BLD - Footings Insp  11/30/2018 11:29:40 AM  12/3/2018  10 AM - 2 PM  12/3/2018  PJJ 
BLD - Pre-Slab Insp  11/30/2018 11:29:49 AM  12/3/2018  10 AM - 2 PM  12/3/2018  PJJ 
BLD - Reinforcing Insp  11/30/2018 11:29:55 AM  12/3/2018  10 AM - 2 PM  12/3/2018  PJJ 
ELE - Ground Electrode/UFER  11/30/2018 11:30:03 AM  12/3/2018  10 AM - 2 PM  12/3/2018  PJJ 
ELE - Underground conduit  11/30/2018 11:30:12 AM  12/3/2018  10 AM - 2 PM  12/3/2018  PJJ 
BLD - Footings Insp  12/3/2018 12:00:59 PM  12/4/2018  8 AM - 12 PM  12/4/2018  PJJ 
BLD - Pre-Slab Insp  12/3/2018 12:01:07 PM  12/4/2018  8 AM - 12 PM  12/4/2018  PJJ 
BLD - Reinforcing Insp  12/3/2018 12:01:13 PM  12/4/2018  8 AM - 12 PM  12/4/2018  PJJ 
ELE - Ground Electrode/UFER  12/3/2018 12:01:23 PM  12/4/2018  8 AM - 12 PM  12/4/2018  PJJ 
ELE - Underground conduit  12/3/2018 12:01:41 PM  12/4/2018  8 AM - 12 PM  12/4/2018  PJJ 
BLD - Footings Insp  12/4/2018 2:12:16 PM  12/5/2018  12 PM - 3 PM  12/5/2018  BEN 
BLD - Pre-Slab Insp  12/4/2018 2:12:23 PM  12/5/2018  12 PM - 3 PM  12/5/2018  BEN 
BLD - Reinforcing Insp  12/4/2018 2:12:32 PM  12/5/2018  12 PM - 3 PM  12/5/2018  BEN 
ELE - Ground Electrode/UFER  12/4/2018 2:12:40 PM  12/5/2018  12 PM - 3 PM  12/5/2018  BEN 
ELE - Underground conduit  12/4/2018 2:12:48 PM  12/5/2018  12 PM - 3 PM  12/5/2018  BEN 
BLD - Footings Insp  12/5/2018 2:23:18 PM  12/6/2018  12 PM - 3 PM  12/6/2018  BEN 
BLD - Reinforcing Insp  12/5/2018 2:23:25 PM  12/6/2018  12 PM - 3 PM  12/6/2018  BEN 
BLD - Pre-Slab Insp  12/5/2018 2:23:32 PM  12/6/2018  12 PM - 3 PM  12/6/2018  BEN 
ELE - Ground Electrode/UFER  12/5/2018 2:23:40 PM  12/6/2018  12 PM - 3 PM  12/6/2018  BEN 
ELE - Underground conduit  12/5/2018 2:23:47 PM  12/6/2018  12 PM - 3 PM  12/6/2018  BEN 
BLD - Footings Insp  12/6/2018 1:16:06 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BEN 
BLD - Pre-Slab Insp  12/6/2018 1:16:18 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BEN 
BLD - Reinforcing Insp  12/6/2018 1:16:25 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BEN 
ELE - Ground Electrode/UFER  12/6/2018 1:16:32 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BEN 
ELE - Underground conduit  12/6/2018 1:16:39 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BEN 
BLD - Footings Insp  12/9/2018 2:12:51 PM  12/10/2018  8 AM - 12 PM  12/10/2018  PJJ 
BLD - Pre-Slab Insp  12/9/2018 2:13:13 PM  12/10/2018  8 AM - 12 PM  12/10/2018  PJJ 
BLD - Reinforcing Insp  12/9/2018 2:13:21 PM  12/10/2018  8 AM - 12 PM  12/10/2018  PJJ 
ELE - Ground Electrode/UFER  12/9/2018 2:13:58 PM  12/10/2018  8 AM - 12 PM  12/10/2018  PJJ 
ELE - Underground conduit  12/9/2018 2:14:10 PM  12/10/2018  8 AM - 12 PM  12/10/2018  PJJ 
BLD - Footings Insp  12/10/2018 11:05:09 AM  12/11/2018  12 PM - 3 PM  12/11/2018  BEN 
BLD - Pre-Slab Insp  12/10/2018 11:05:23 AM  12/11/2018  12 PM - 3 PM  12/11/2018  BEN 
BLD - Reinforcing Insp  12/10/2018 11:05:36 AM  12/11/2018  12 PM - 3 PM  12/11/2018  BEN 
ELE - Ground Electrode/UFER  12/10/2018 11:05:54 AM  12/11/2018  12 PM - 3 PM  12/11/2018  BEN 
ELE - Underground conduit  12/10/2018 11:06:01 AM  12/11/2018  12 PM - 3 PM  12/11/2018  BEN 
BLD - Footings Insp  12/11/2018 10:37:09 AM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
BLD - Pre-Slab Insp  12/11/2018 12:57:52 PM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
BLD - Reinforcing Insp  12/11/2018 12:57:59 PM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
PLM - Ground/Underfloor water  12/11/2018 12:58:17 PM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
ELE - Ground Electrode/UFER  12/11/2018 12:58:35 PM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
ELE - Underground conduit  12/11/2018 12:58:43 PM  12/12/2018  12 PM - 3 PM  12/12/2018  BEN 
BLD - Footings Insp  12/12/2018 1:27:18 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
BLD - Pre-Slab Insp  12/12/2018 1:27:25 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
BLD - Reinforcing Insp  12/12/2018 1:27:34 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
ELE - Ground Electrode/UFER  12/12/2018 1:28:00 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
ELE - Underground conduit  12/12/2018 1:28:07 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
PLM - Ground/Underfloor water  12/12/2018 1:28:27 PM  12/13/2018  8 AM - 12 PM  12/13/2018  BEN 
BLD - Footings Insp  12/13/2018 7:54:32 AM  12/14/2018  8 AM - 12 PM  12/14/2018  BEN 
BLD - Pre-Slab Insp  12/13/2018 7:54:39 AM  12/14/2018  8 AM - 12 PM  12/14/2018  BEN 
BLD - Reinforcing Insp  12/13/2018 7:54:49 AM  12/14/2018  8 AM - 12 PM  12/14/2018  BEN 
ELE - Ground Electrode/UFER  12/13/2018 7:54:56 AM  12/14/2018  8 AM - 12 PM  12/14/2018  BEN 
ELE - Underground conduit  12/13/2018 7:55:29 AM  12/14/2018  8 AM - 12 PM  12/14/2018  BEN 
BLD - Footings Insp  12/14/2018 9:53:25 AM  12/17/2018  10 AM - 2 PM  12/17/2018  JOS 
BLD - Pre-Slab Insp  12/14/2018 9:53:35 AM  12/17/2018  10 AM - 2 PM  12/17/2018  JOS 
BLD - Reinforcing Insp  12/14/2018 9:53:41 AM  12/17/2018  10 AM - 2 PM  12/17/2018  JOS 
ELE - Ground Electrode/UFER  12/14/2018 9:53:58 AM  12/17/2018  10 AM - 2 PM  12/17/2018  JOS 
ELE - Underground conduit  12/14/2018 9:54:06 AM  12/17/2018  10 AM - 2 PM  12/17/2018  JOS 
BLD - Footings Insp  12/17/2018 11:47:13 AM  12/18/2018    12/18/2018  PJJ 
BLD - Reinforcing Insp  12/17/2018 11:47:23 AM  12/18/2018    12/18/2018  PJJ 
BLD - Pre-Slab Insp  12/17/2018 11:47:31 AM  12/18/2018    12/18/2018  PJJ 
PLM - Ground/Underfloor water  12/17/2018 11:47:45 AM  12/18/2018    12/18/2018  PJJ 
ELE - Ground Electrode/UFER  12/17/2018 2:45:43 PM  12/18/2018    12/18/2018  PJJ 
ELE - Underground conduit  12/17/2018 2:45:50 PM  12/18/2018    12/18/2018  PJJ 
BLD - Footings Insp  12/18/2018 10:17:13 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
BLD - Pre-Slab Insp  12/18/2018 10:17:22 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
BLD - Reinforcing Insp  12/18/2018 10:17:28 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
ELE - Ground Electrode/UFER  12/18/2018 10:17:38 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
ELE - Underground conduit  12/18/2018 10:17:46 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
PLM - Ground/Underfloor waste  12/18/2018 10:18:00 AM  12/19/2018  10 AM - 2 PM  12/19/2018  PJJ 
BLD - Footings Insp  12/19/2018 10:56:39 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
BLD - Pre-Slab Insp  12/19/2018 10:57:11 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
BLD - Reinforcing Insp  12/19/2018 11:05:06 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
ELE - Ground Electrode/UFER  12/19/2018 11:09:24 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
ELE - Rough Electrical  12/19/2018 11:09:36 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
BLD -Floor Joists/Girders Insp  12/19/2018 11:10:00 AM  12/20/2018  12 PM - 3 PM  12/20/2018  BEN 
BLD - Footings Insp  12/20/2018 2:06:23 PM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
BLD - Pre-Slab Insp  12/20/2018 2:06:32 PM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
BLD - Reinforcing Insp  12/20/2018 2:06:42 PM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
ELE - Ground Electrode/UFER  12/20/2018 2:06:49 PM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
ELE - Underground conduit  12/20/2018 2:07:00 PM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
BLD - Footings Insp  12/21/2018 10:27:20 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
BLD - Reinforcing Insp  12/21/2018 10:27:26 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
BLD - Pre-Slab Insp  12/21/2018 10:27:33 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
ELE - Rough Electrical  12/21/2018 10:27:49 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
ELE - Underground conduit  12/21/2018 10:27:56 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
ELE - Ground Electrode/UFER  12/21/2018 10:28:03 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
BLD - Framing Insp.  12/21/2018 10:28:29 AM  12/24/2018  8 AM - 12 PM  12/24/2018  PJJ 
BLD - Footings Insp  12/25/2018 4:59:26 AM  12/26/2018    12/26/2018  PJJ 
BLD - Pre-Slab Insp  12/25/2018 4:59:59 AM  12/26/2018    12/26/2018  PJJ 
BLD - Reinforcing Insp  12/25/2018 5:00:11 AM  12/26/2018    12/26/2018  PJJ 
ELE - Ground Electrode/UFER  12/25/2018 5:00:32 AM  12/26/2018    12/26/2018  PJJ 
ELE - Underground conduit  12/25/2018 5:00:47 AM  12/26/2018    12/26/2018  PJJ 
PLM - Ground/Underfloor waste  12/25/2018 5:01:18 AM  12/26/2018    12/26/2018  PJJ 
BLD - Footings Insp  12/26/2018 1:48:22 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
BLD - Pre-Slab Insp  12/26/2018 1:48:37 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
BLD - Reinforcing Insp  12/26/2018 1:49:25 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
BLD - Framing Insp.  12/26/2018 1:49:32 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
BLD - Exterior Lath Insp  12/26/2018 1:49:38 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
ELE - Underground conduit  12/26/2018 1:49:52 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
ELE - Ground Electrode/UFER  12/26/2018 1:50:05 PM  12/27/2018  10 AM - 2 PM  12/27/2018  PJJ 
BLD - Footings Insp  12/27/2018 12:43:36 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
BLD - Pre-Slab Insp  12/27/2018 12:43:43 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
BLD - Reinforcing Insp  12/27/2018 12:43:51 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
ELE - Underground conduit  12/27/2018 12:44:02 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
ELE - Ground Electrode/UFER  12/27/2018 12:44:11 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
BLD - Framing Insp.  12/27/2018 12:44:18 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
BLD - Exterior Lath Insp  12/27/2018 12:44:23 PM  12/28/2018  10 AM - 2 PM  12/28/2018  PJJ 
BLD - Footings Insp  12/28/2018 10:06:04 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
BLD - Pre-Slab Insp  12/28/2018 10:06:15 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
BLD - Reinforcing Insp  12/28/2018 10:06:20 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
BLD - Framing Insp.  12/28/2018 10:06:28 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
BLD - Exterior Lath Insp  12/28/2018 10:06:36 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
ELE - Underground conduit  12/28/2018 10:06:47 AM  12/31/2018  8 AM - 12 PM  12/31/2018  PJJ 
BLD - Footings Insp  12/28/2018 10:08:22 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
BLD - Pre-Slab Insp  12/28/2018 10:08:32 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
BLD - Reinforcing Insp  12/28/2018 10:08:42 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
ELE - Underground conduit  12/28/2018 10:08:51 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
ELE - Ground Electrode/UFER  12/28/2018 10:09:02 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
BLD - Framing Insp.  12/28/2018 10:10:33 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
BLD - Exterior Lath Insp  12/28/2018 10:10:43 AM  1/2/2019  12 PM - 3 PM  1/2/2019  BEN 
BLD - Framing Insp.  1/2/2019 1:32:52 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
BLD - Footings Insp  1/2/2019 1:32:58 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
BLD - Pre-Slab Insp  1/2/2019 1:33:30 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
BLD - Reinforcing Insp  1/2/2019 1:33:36 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
BLD - Exterior Lath Insp  1/2/2019 1:33:41 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
ELE - Ground Electrode/UFER  1/2/2019 1:33:49 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
ELE - Underground conduit  1/2/2019 1:33:57 PM  1/3/2019  12 PM - 3 PM  1/3/2019  BEN 
BLD - Pre-Slab Insp  1/3/2019 1:28:37 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
BLD - Framing Insp.  1/3/2019 1:28:43 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
BLD - Exterior Lath Insp  1/3/2019 1:28:49 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
BLD - Footings Insp  1/3/2019 1:28:57 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
BLD - Reinforcing Insp  1/3/2019 1:29:17 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
ELE - Ground Electrode/UFER  1/3/2019 1:29:54 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
ELE - Underground conduit  1/3/2019 1:30:04 PM  1/4/2019  8 AM - 12 PM  1/4/2019  BEN 
BLD - Footings Insp  1/4/2019 1:35:23 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
BLD - Pre-Slab Insp  1/4/2019 1:35:29 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
BLD - Reinforcing Insp  1/4/2019 1:35:35 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
ELE - Ground Electrode/UFER  1/4/2019 1:36:36 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
ELE - Underground conduit  1/4/2019 1:37:34 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
BLD - Framing Insp.  1/4/2019 1:38:48 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
BLD - Exterior Lath Insp  1/4/2019 1:39:03 PM  1/7/2019  10 AM - 2 PM  1/7/2019  PJJ 
BLD - Footings Insp  1/7/2019 12:58:17 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
BLD - Reinforcing Insp  1/7/2019 12:58:23 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
BLD - Pre-Slab Insp  1/7/2019 12:58:31 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
ELE - Underground conduit  1/7/2019 12:58:57 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
ELE - Ground Electrode/UFER  1/7/2019 12:59:04 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
BLD - Framing Insp.  1/7/2019 12:59:40 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
BLD - Exterior Lath Insp  1/7/2019 12:59:46 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
PLM - Ground/Underfloor waste  1/7/2019 2:49:28 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BEN 
BLD - Footings Insp  1/8/2019 1:31:20 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
BLD - Pre-Slab Insp  1/8/2019 1:31:27 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
BLD - Reinforcing Insp  1/8/2019 1:31:38 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
ELE - Underground conduit  1/8/2019 1:32:19 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
ELE - Ground Electrode/UFER  1/8/2019 1:32:29 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
BLD - Framing Insp.  1/8/2019 1:32:37 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
BLD - Exterior Lath Insp  1/8/2019 1:32:44 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BEN 
BLD - Footings Insp  1/9/2019 11:09:17 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
BLD - Pre-Slab Insp  1/9/2019 11:13:05 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
BLD - Reinforcing Insp  1/9/2019 11:13:52 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
ELE - Ground Electrode/UFER  1/9/2019 11:15:34 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
ELE - Underground conduit  1/9/2019 11:15:43 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
BLD - Framing Insp.  1/9/2019 11:19:23 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
BLD - Exterior Lath Insp  1/9/2019 11:20:08 AM  1/10/2019  8 AM - 12 PM  1/10/2019  BEN 
BLD - Footings Insp  1/10/2019 1:45:46 PM  1/11/2019  10 AM - 2 PM  1/11/2019  BEN 
BLD - Reinforcing Insp  1/10/2019 1:45:53 PM  1/11/2019  10 AM - 2 PM  1/11/2019  BEN 
BLD - Pre-Slab Insp  1/10/2019 1:45:58 PM  1/11/2019  10 AM - 2 PM  1/11/2019  BEN 
ELE - Ground Electrode/UFER  1/10/2019 1:46:10 PM  1/11/2019  10 AM - 2 PM  1/11/2019  BEN 
ELE - Underground conduit  1/10/2019 1:46:18 PM  1/11/2019  10 AM - 2 PM  1/11/2019  BEN 
BLD - Reinforcing Insp  1/11/2019  1/12/2019  10 AM - 2 PM  1/15/2019  BEN 
BLD - Footings Insp  1/13/2019 1:48:37 PM  1/14/2019  10 AM - 2 PM  1/14/2019  PJJ 
BLD - Pre-Slab Insp  1/13/2019 1:48:49 PM  1/14/2019  10 AM - 2 PM  1/14/2019  PJJ 
BLD - Reinforcing Insp  1/13/2019 1:49:03 PM  1/14/2019  10 AM - 2 PM  1/14/2019  PJJ 
ELE - Ground Electrode/UFER  1/13/2019 1:49:20 PM  1/14/2019  10 AM - 2 PM  1/14/2019  PJJ 
ELE - Underground conduit  1/13/2019 1:49:32 PM  1/14/2019  10 AM - 2 PM  1/14/2019  PJJ 
BLD - Footings Insp  1/14/2019 1:20:34 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
BLD - Pre-Slab Insp  1/14/2019 1:20:47 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
BLD - Reinforcing Insp  1/14/2019 1:20:53 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
ELE - Underground conduit  1/14/2019 1:21:02 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
ELE - Ground Electrode/UFER  1/14/2019 1:21:10 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
BLD - Framing Insp.  1/14/2019 1:22:24 PM  1/15/2019  12 PM - 3 PM  1/15/2019  BEN 
BLD - Footings Insp  1/15/2019 8:45:41 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
BLD - Pre-Slab Insp  1/15/2019 8:45:49 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
BLD - Reinforcing Insp  1/15/2019 8:45:55 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
ELE - Underground conduit  1/15/2019 8:46:03 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
ELE - Ground Electrode/UFER  1/15/2019 8:46:11 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
BLD - Framing Insp.  1/15/2019 8:46:22 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
BLD - Exterior Lath Insp  1/15/2019 8:46:28 AM  1/16/2019  10 AM - 2 PM  1/16/2019  BEN 
Route to Planning Zoning  1/15/2019  2/1/2019    1/16/2019  APPR  EYT 
Approved by Planning Zoning  1/15/2019      1/16/2019 9:10:01 AM  APPR  EYT 
Route to Struct/Architectual  1/15/2019  2/1/2019    1/22/2019  APPR  CSG 
Apprv. by Struct/Architectural  1/15/2019      1/22/2019 2:26:24 PM  APPR  CSG 
Route to Fire Department  1/15/2019  2/1/2019    1/16/2019  NR  EPO 
Approved by Fire Department  1/15/2019      1/16/2019 9:07:18 AM  NR  EPO 
BLD - Footings Insp  1/16/2019 11:00:55 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
BLD - Reinforcing Insp  1/16/2019 11:01:02 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
BLD - Pre-Slab Insp  1/16/2019 11:01:15 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
ELE - Underground conduit  1/16/2019 11:02:27 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
ELE - Ground Electrode/UFER  1/16/2019 11:02:48 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
BLD - Framing Insp.  1/16/2019 11:03:01 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
BLD - Exterior Lath Insp  1/16/2019 11:03:10 AM  1/17/2019  10 AM - 2 PM  1/17/2019  BEN 
BLD - Footings Insp  1/17/2019 8:10:01 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
BLD - Pre-Slab Insp  1/17/2019 8:10:09 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
BLD - Reinforcing Insp  1/17/2019 8:10:15 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
BLD - Framing Insp.  1/17/2019 8:10:21 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
BLD - Exterior Lath Insp  1/17/2019 8:10:45 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
ELE - Underground conduit  1/17/2019 8:10:56 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
ELE - Ground Electrode/UFER  1/17/2019 8:11:04 AM  1/18/2019  8 AM - 12 PM  1/18/2019  BEN 
BLD - Footings Insp  1/18/2019 10:36:53 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
BLD - Pre-Grout Insp  1/18/2019 10:37:14 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
BLD - Pre-Slab Insp  1/18/2019 10:37:23 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
ELE - Ground Electrode/UFER  1/18/2019 10:37:31 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
ELE - Underground conduit  1/18/2019 10:37:39 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
BLD - Framing Insp.  1/18/2019 10:38:09 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
BLD - Exterior Lath Insp  1/18/2019 10:38:16 AM  1/22/2019  10 AM - 2 PM  1/22/2019  PJJ 
BLD - Pre-Slab Insp  1/18/2019  1/19/2019  12 PM - 3 PM  1/23/2019  BEN 
BLD - Footings Insp  1/22/2019 9:36:58 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
BLD - Pre-Slab Insp  1/22/2019 9:37:22 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
BLD - Reinforcing Insp  1/22/2019 9:37:28 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
ELE - Underground conduit  1/22/2019 9:37:36 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
ELE - Ground Electrode/UFER  1/22/2019 9:37:41 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
BLD - Framing Insp.  1/22/2019 9:37:48 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
BLD - Exterior Lath Insp  1/22/2019 9:37:55 AM  1/23/2019  8 AM - 12 PM  1/23/2019  BEN 
BLD - Footings Insp  1/23/2019 11:10:04 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
BLD - Pre-Slab Insp  1/23/2019 11:10:11 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
BLD - Reinforcing Insp  1/23/2019 11:10:17 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
BLD - Framing Insp.  1/23/2019 11:10:23 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
BLD - Exterior Lath Insp  1/23/2019 11:10:29 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
ELE - Rough Electrical  1/23/2019 11:10:36 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
ELE - Ground Electrode/UFER  1/23/2019 11:11:08 AM  1/24/2019  12 PM - 3 PM  1/24/2019  BEN 
BLD - Footings Insp  1/24/2019 6:40:42 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD - Pre-Slab Insp  1/24/2019 6:40:49 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD - Framing Insp.  1/24/2019 6:41:00 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD - Exterior Lath Insp  1/24/2019 6:41:05 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
ELE - Rough Electrical  1/24/2019 6:41:12 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
ELE - Ground Electrode/UFER  1/24/2019 6:41:32 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD - Reinforcing Insp  1/24/2019 6:41:55 AM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD -Floor Joists/Girders Insp  1/24/2019 1:36:18 PM  1/25/2019  12 PM - 3 PM  1/25/2019  BEN 
BLD - Footings Insp  1/25/2019 10:00:17 AM  1/28/2019  8 AM - 12 PM  1/28/2019  PJJ 
BLD - Pre-Slab Insp  1/25/2019 10:01:05 AM  1/28/2019  8 AM - 12 PM  1/28/2019  PJJ 
BLD - Reinforcing Insp  1/25/2019 10:01:15 AM  1/28/2019  8 AM - 12 PM  1/28/2019  PJJ 
ELE - Ground Electrode/UFER  1/25/2019 10:01:29 AM  1/28/2019  8 AM - 12 PM  1/28/2019  PJJ 
ELE - Underground conduit  1/25/2019 10:01:38 AM  1/28/2019  8 AM - 12 PM  1/28/2019  PJJ 
BLD - Reinforcing Insp  1/25/2019  1/26/2019  10 AM - 2 PM  1/29/2019  BEN 
BLD - Footings Insp  1/28/2019 10:28:57 AM  1/29/2019  8 AM - 12 PM  1/29/2019  BEN 
BLD - Reinforcing Insp  1/28/2019 10:29:06 AM  1/29/2019  8 AM - 12 PM  1/29/2019  BEN 
BLD - Pre-Slab Insp  1/28/2019 10:29:12 AM  1/29/2019  8 AM - 12 PM  1/29/2019  BEN 
ELE - Underground conduit  1/28/2019 10:29:21 AM  1/29/2019  8 AM - 12 PM  1/29/2019  BEN 
ELE - Ground Electrode/UFER  1/28/2019 10:29:54 AM  1/29/2019  8 AM - 12 PM  1/29/2019  BEN 
BLD - Footings Insp  1/29/2019 9:34:47 AM  1/30/2019  12 PM - 3 PM  1/30/2019  BEN 
BLD - Pre-Slab Insp  1/29/2019 9:34:52 AM  1/30/2019  12 PM - 3 PM  1/30/2019  BEN 
BLD - Reinforcing Insp  1/29/2019 9:35:06 AM  1/30/2019  12 PM - 3 PM  1/30/2019  BEN 
ELE - Underground conduit  1/29/2019 9:35:15 AM  1/30/2019  12 PM - 3 PM  1/30/2019  BEN 
ELE - Ground Electrode/UFER  1/29/2019 9:35:22 AM  1/30/2019  12 PM - 3 PM  1/30/2019  BEN 
BLD - Pre-Slab Insp  1/30/2019 12:22:52 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BEN 
BLD - Footings Insp  1/30/2019 12:22:57 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BEN 
BLD - Reinforcing Insp  1/30/2019 12:23:08 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BEN 
ELE - Underground conduit  1/30/2019 12:23:33 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BEN 
ELE - Ground Electrode/UFER  1/30/2019 12:24:20 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BEN 
BLD - Footings Insp  1/31/2019 10:56:48 AM  2/1/2019  12 PM - 3 PM  2/1/2019  BEN 
BLD - Pre-Slab Insp  1/31/2019 10:56:56 AM  2/1/2019  12 PM - 3 PM  2/1/2019  BEN 
BLD - Reinforcing Insp  1/31/2019 10:57:11 AM  2/1/2019  12 PM - 3 PM  2/1/2019  BEN 
ELE - Underground conduit  1/31/2019 11:00:57 AM  2/1/2019  12 PM - 3 PM  2/1/2019  BEN 
ELE - Ground Electrode/UFER  1/31/2019 11:01:13 AM  2/1/2019  12 PM - 3 PM  2/1/2019  BEN 
BLD - Footings Insp  2/1/2019 10:53:32 AM  2/4/2019  8 AM - 12 PM  2/4/2019  PJJ 
BLD - Pre-Slab Insp  2/1/2019 10:53:39 AM  2/4/2019  8 AM - 12 PM  2/4/2019  PJJ 
BLD - Reinforcing Insp  2/1/2019 10:53:46 AM  2/4/2019  8 AM - 12 PM  2/4/2019  PJJ 
ELE - Underground conduit  2/1/2019 10:53:52 AM  2/4/2019  8 AM - 12 PM  2/4/2019  PJJ 
ELE - Ground Electrode/UFER  2/1/2019 10:53:59 AM  2/4/2019  8 AM - 12 PM  2/4/2019  PJJ 
BLD - Footings Insp  2/4/2019 1:27:25 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
BLD - Pre-Slab Insp  2/4/2019 1:27:31 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
BLD - Reinforcing Insp  2/4/2019 1:27:37 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
ELE - Underground conduit  2/4/2019 1:27:45 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
ELE - Ground Electrode/UFER  2/4/2019 1:27:53 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
BLD - Framing Insp.  2/4/2019 1:28:17 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
BLD - Exterior Lath Insp  2/4/2019 1:28:26 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BEN 
BLD - Footings Insp  2/5/2019 11:11:11 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
BLD - Pre-Slab Insp  2/5/2019 11:11:18 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
BLD - Reinforcing Insp  2/5/2019 11:11:24 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
ELE - Underground conduit  2/5/2019 11:11:34 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
ELE - Ground Electrode/UFER  2/5/2019 11:11:41 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
BLD - Framing Insp.  2/5/2019 11:11:52 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
BLD - Exterior Lath Insp  2/5/2019 11:11:58 AM  2/6/2019  10 AM - 2 PM  2/6/2019  BEN 
Route to Planning Zoning  2/6/2019  2/25/2019    2/21/2019  APPR  EYT 
Approved by Planning Zoning  2/6/2019      2/21/2019 12:40:41 PM  APPR  EYT 
Route to Struct/Architectual  2/6/2019  2/25/2019    2/14/2019  APPR  CSG 
Apprv. by Struct/Architectural  2/6/2019      2/14/2019 12:50:30 PM  APPR  CSG 
Approved by Fire Department  2/6/2019      2/21/2019 11:18:15 AM  APPR  EPO 
Route to Fire Department  2/6/2019  2/25/2019    2/21/2019  APPR  EPO 
BLD - Footings Insp  2/6/2019 10:57:23 AM  2/7/2019  12 PM - 3 PM  2/7/2019  BEN 
BLD - Pre-Slab Insp  2/6/2019 10:57:30 AM  2/7/2019  12 PM - 3 PM  2/7/2019  BEN 
BLD - Reinforcing Insp  2/6/2019 10:57:36 AM  2/7/2019  12 PM - 3 PM  2/7/2019  BEN 
ELE - Underground conduit  2/6/2019 10:57:42 AM  2/7/2019  12 PM - 3 PM  2/7/2019  BEN 
ELE - Ground Electrode/UFER  2/6/2019 10:57:49 AM  2/7/2019  12 PM - 3 PM  2/7/2019  BEN 
BLD - Footings Insp  2/7/2019 12:17:24 PM  2/8/2019  12 PM - 3 PM  2/8/2019  BEN 
BLD - Pre-Slab Insp  2/7/2019 12:17:31 PM  2/8/2019  12 PM - 3 PM  2/8/2019  BEN 
BLD - Reinforcing Insp  2/7/2019 12:17:38 PM  2/8/2019  12 PM - 3 PM  2/8/2019  BEN 
ELE - Underground conduit  2/7/2019 12:17:58 PM  2/8/2019  12 PM - 3 PM  2/8/2019  BEN 
ELE - Ground Electrode/UFER  2/7/2019 12:18:08 PM  2/8/2019  12 PM - 3 PM  2/8/2019  BEN 
BLD - Footings Insp  2/8/2019 7:49:15 AM  2/11/2019  8 AM - 12 PM  2/11/2019  PJJ 
BLD - Reinforcing Insp  2/8/2019 7:49:21 AM  2/11/2019  8 AM - 12 PM  2/11/2019  PJJ 
BLD - Pre-Slab Insp  2/8/2019 7:49:27 AM  2/11/2019  8 AM - 12 PM  2/11/2019  PJJ 
ELE - Underground conduit  2/8/2019 7:49:38 AM  2/11/2019  8 AM - 12 PM  2/11/2019  PJJ 
ELE - Ground Electrode/UFER  2/8/2019 7:49:44 AM  2/11/2019  8 AM - 12 PM  2/11/2019  PJJ 
BLD - Pre-Slab Insp  2/11/2019 11:48:24 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BEN 
BLD - Reinforcing Insp  2/11/2019 11:48:34 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BEN 
BLD - Footings Insp  2/11/2019 11:48:40 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BEN 
ELE - Underground conduit  2/11/2019 11:48:54 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BEN 
ELE - Ground Electrode/UFER  2/11/2019 11:49:03 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BEN 
BLD - Footings Insp  2/12/2019 1:24:13 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BEN 
BLD - Pre-Slab Insp  2/12/2019 1:24:21 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BEN 
BLD - Reinforcing Insp  2/12/2019 1:24:33 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BEN 
ELE - Underground conduit  2/12/2019 1:24:43 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BEN 
ELE - Ground Electrode/UFER  2/12/2019 1:24:51 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BEN 
BLD - Footings Insp  2/13/2019 10:51:39 AM  2/14/2019  8 AM - 12 PM  2/14/2019  BEN 
BLD - Reinforcing Insp  2/13/2019 10:51:46 AM  2/14/2019  8 AM - 12 PM  2/14/2019  BEN 
BLD - Pre-Slab Insp  2/13/2019 10:51:53 AM  2/14/2019  8 AM - 12 PM  2/14/2019  BEN 
ELE - Underground conduit  2/13/2019 10:52:01 AM  2/14/2019  8 AM - 12 PM  2/14/2019  BEN 
ELE - Ground Electrode/UFER  2/13/2019 10:52:07 AM  2/14/2019  8 AM - 12 PM  2/14/2019  BEN 
BLD - Footings Insp  2/14/2019 1:04:53 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
BLD - Pre-Slab Insp  2/14/2019 1:05:01 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
BLD - Reinforcing Insp  2/14/2019 1:05:15 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
ELE - Rough Electrical  2/14/2019 1:05:35 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
ELE - Underground conduit  2/14/2019 1:05:43 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
ELE - Ground Electrode/UFER  2/14/2019 1:05:49 PM  2/15/2019  12 PM - 3 PM  2/15/2019  BEN 
BLD - Pre-Slab Insp  2/19/2019 1:53:55 PM  2/20/2019  10 AM - 2 PM  2/20/2019  PJJ 
BLD - Reinforcing Insp  2/19/2019 1:54:02 PM  2/20/2019  10 AM - 2 PM  2/20/2019  PJJ 
ELE - Underground conduit  2/19/2019 1:54:21 PM  2/20/2019  10 AM - 2 PM  2/20/2019  PJJ 
ELE - Ground Electrode/UFER  2/19/2019 1:54:30 PM  2/20/2019  10 AM - 2 PM  2/20/2019  PJJ 
BLD - Footings Insp  2/19/2019 1:54:45 PM  2/20/2019  10 AM - 2 PM  2/20/2019  PJJ 
BLD - Pre-Slab Insp  2/20/2019 12:58:04 PM  2/21/2019  8 AM - 12 PM  2/21/2019  PJJ 
BLD - Footings Insp  2/20/2019 12:58:19 PM  2/21/2019  8 AM - 12 PM  2/21/2019  PJJ 
BLD - Reinforcing Insp  2/20/2019 12:58:26 PM  2/21/2019  8 AM - 12 PM  2/21/2019  PJJ 
ELE - Ground Electrode/UFER  2/20/2019 12:58:35 PM  2/21/2019  8 AM - 12 PM  2/21/2019  PJJ 
ELE - Underground conduit  2/20/2019 12:58:50 PM  2/21/2019  8 AM - 12 PM  2/21/2019  PJJ 
BLD - Footings Insp  2/21/2019 10:45:13 AM  2/22/2019  8 AM - 12 PM  2/22/2019  BEN 
BLD - Pre-Slab Insp  2/21/2019 10:45:19 AM  2/22/2019  8 AM - 12 PM  2/22/2019  BEN 
BLD - Reinforcing Insp  2/21/2019 10:45:26 AM  2/22/2019  8 AM - 12 PM  2/22/2019  BEN 
ELE - Ground Electrode/UFER  2/21/2019 10:46:48 AM  2/22/2019  8 AM - 12 PM  2/22/2019  BEN 
ELE - Underground conduit  2/21/2019 10:46:58 AM  2/22/2019  8 AM - 12 PM  2/22/2019  BEN 
BLD - Pre-Slab Insp  2/22/2019  2/23/2019    2/26/2019  BEN 
BLD - Footings Insp  2/22/2019  2/23/2019    2/26/2019  BEN 
BLD - Reinforcing Insp  2/24/2019 12:05:22 PM  2/25/2019  8 AM - 12 PM  2/25/2019  PJJ 
ELE - Underground conduit  2/24/2019 12:05:41 PM  2/25/2019  8 AM - 12 PM  2/25/2019  PJJ 
ELE - Ground Electrode/UFER  2/24/2019 12:05:56 PM  2/25/2019  8 AM - 12 PM  2/25/2019  PJJ 
BLD - Pre-Slab Insp  2/24/2019 12:06:13 PM  2/25/2019  8 AM - 12 PM  2/25/2019  PJJ 
BLD - Footings Insp  2/24/2019 12:06:30 PM  2/25/2019  8 AM - 12 PM  2/25/2019  PJJ 
BLD - Footings Insp  2/25/2019 1:41:27 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
BLD - Pre-Slab Insp  2/25/2019 1:41:42 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
BLD - Reinforcing Insp  2/25/2019 1:42:49 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
ELE - Underground conduit  2/25/2019 1:43:18 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
ELE - Ground Electrode/UFER  2/25/2019 1:43:37 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
BLD -Floor Joists/Girders Insp  2/25/2019 3:31:54 PM  2/26/2019  12 PM - 3 PM  2/26/2019  BEN 
BLD - Pre-Slab Insp  2/26/2019 12:03:41 PM  2/27/2019  12 PM - 3 PM  2/27/2019  BEN 
BLD - Reinforcing Insp  2/26/2019 12:03:56 PM  2/27/2019  12 PM - 3 PM  2/27/2019  BEN 
BLD - Footings Insp  2/26/2019 12:04:34 PM  2/27/2019  12 PM - 3 PM  2/27/2019  BEN 
ELE - Underground conduit  2/26/2019 12:05:27 PM  2/27/2019  12 PM - 3 PM  2/27/2019  BEN 
ELE - Ground Electrode/UFER  2/26/2019 12:05:45 PM  2/27/2019  12 PM - 3 PM  2/27/2019  BEN 
Route to Planning Zoning  2/26/2019  3/14/2019    3/1/2019  APPR  EYT 
Approved by Planning Zoning  2/26/2019      3/1/2019 8:36:00 AM  APPR  EYT 
Route to Struct/Architectual  2/26/2019  3/14/2019    3/4/2019  CORR  CSG 
Route to Fire Department  2/26/2019  3/14/2019    3/13/2019  NR  EPO 
Approved by Fire Department  2/26/2019      3/13/2019 3:11:45 PM  NR  EPO 
BLD - Footings Insp  2/27/2019 11:49:44 AM  2/28/2019  12 PM - 3 PM  2/28/2019  BEN 
BLD - Pre-Slab Insp  2/27/2019 11:49:54 AM  2/28/2019  12 PM - 3 PM  2/28/2019  BEN 
BLD - Reinforcing Insp  2/27/2019 11:50:03 AM  2/28/2019  12 PM - 3 PM  2/28/2019  BEN 
ELE - Underground conduit  2/27/2019 11:50:37 AM  2/28/2019  12 PM - 3 PM  2/28/2019  BEN 
ELE - Ground Electrode/UFER  2/27/2019 11:50:45 AM  2/28/2019  12 PM - 3 PM  2/28/2019  BEN 
Approved by Planning Zoning  2/27/2019      3/1/2019 8:36:49 AM  APPR  EYT 
Route to Planning Zoning  2/27/2019  3/15/2019    3/1/2019  APPR  EYT 
Apprv. by Struct/Architectural  2/27/2019      3/4/2019 11:36:59 AM  APPR  CSG 
Route to Struct/Architectual  2/27/2019  3/15/2019    3/4/2019  APPR  CSG 
BLD - Footings Insp  2/28/2019 8:01:26 AM  3/1/2019  8 AM - 12 PM  3/1/2019  BEN 
BLD - Pre-Slab Insp  2/28/2019 8:01:34 AM  3/1/2019  8 AM - 12 PM  3/1/2019  BEN 
BLD - Reinforcing Insp  2/28/2019 8:01:41 AM  3/1/2019  8 AM - 12 PM  3/1/2019  BEN 
ELE - Underground conduit  2/28/2019 8:01:47 AM  3/1/2019  8 AM - 12 PM  3/1/2019  BEN 
ELE - Ground Electrode/UFER  2/28/2019 8:01:56 AM  3/1/2019  8 AM - 12 PM  3/1/2019  BEN 
BLD - Footings Insp  3/1/2019 11:00:22 AM  3/4/2019  8 AM - 12 PM  3/4/2019  PJJ 
BLD - Reinforcing Insp  3/1/2019 11:00:30 AM  3/4/2019  8 AM - 12 PM  3/4/2019  PJJ 
BLD - Pre-Slab Insp  3/1/2019 11:00:58 AM  3/4/2019  8 AM - 12 PM  3/4/2019  PJJ 
ELE - Underground conduit  3/1/2019 11:01:10 AM  3/4/2019  8 AM - 12 PM  3/4/2019  PJJ 
ELE - Ground Electrode/UFER  3/1/2019 11:01:19 AM  3/4/2019  8 AM - 12 PM  3/4/2019  PJJ 
BLD - Pre-Slab Insp  3/1/2019  3/2/2019    3/5/2019  NA  BEN 
BLD - Footings Insp  3/1/2019  3/2/2019    3/5/2019  NA  BEN 
BLD - Footings Insp  3/4/2019 10:15:56 AM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
BLD - Pre-Slab Insp  3/4/2019 10:16:03 AM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
BLD - Reinforcing Insp  3/4/2019 10:16:08 AM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
ELE - Underground conduit  3/4/2019 10:16:17 AM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
ELE - Ground Electrode/UFER  3/4/2019 10:17:35 AM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
Approved by Planning Zoning  3/4/2019      3/18/2019 3:35:36 PM  APPR  EYT 
Route to Planning Zoning  3/4/2019  3/20/2019    3/18/2019  APPR  EYT 
Apprv. by Struct/Architectural  3/4/2019      3/14/2019 12:07:14 PM  APPR  CSG 
BLD - Framing Insp.  3/4/2019 12:12:40 PM  3/5/2019  12 PM - 3 PM  3/5/2019  BEN 
Apprv. by Struct/Architectural  2/26/2019      3/11/2019 11:34:37 AM  APPR  CSG 
Route to Struct/Architectual  3/4/2019  3/20/2019    3/11/2019  APPR  CSG 
BLD - Footings Insp  3/5/2019 12:15:08 PM  3/6/2019  12 PM - 3 PM  3/6/2019  BEN 
BLD - Pre-Slab Insp  3/5/2019 12:15:44 PM  3/6/2019  12 PM - 3 PM  3/6/2019  BEN 
BLD - Reinforcing Insp  3/5/2019 12:15:50 PM  3/6/2019  12 PM - 3 PM  3/6/2019  BEN 
ELE - Ground Electrode/UFER  3/5/2019 12:15:59 PM  3/6/2019  12 PM - 3 PM  3/6/2019  BEN 
ELE - Underground conduit  3/5/2019 12:16:06 PM  3/6/2019  12 PM - 3 PM  3/6/2019  BEN 
BLD - Pre-Slab Insp  3/6/2019 9:43:39 AM  3/7/2019  12 PM - 3 PM  3/7/2019  BEN 
BLD - Footings Insp  3/6/2019 9:43:47 AM  3/7/2019  12 PM - 3 PM  3/7/2019  BEN 
BLD - Reinforcing Insp  3/6/2019 9:43:52 AM  3/7/2019  12 PM - 3 PM  3/7/2019  BEN 
ELE - Ground Electrode/UFER  3/6/2019 9:44:03 AM  3/7/2019  12 PM - 3 PM  3/7/2019  BEN 
ELE - Underground conduit  3/6/2019 9:44:13 AM  3/7/2019  12 PM - 3 PM  3/7/2019  BEN 
BLD - Pre-Slab Insp  3/7/2019 1:19:29 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
BLD - Reinforcing Insp  3/7/2019 1:19:36 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
BLD - Footings Insp  3/7/2019 1:19:44 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
ELE - Ground Electrode/UFER  3/7/2019 1:20:40 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
ELE - Underground conduit  3/7/2019 1:20:49 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
BLD - Framing Insp.  3/7/2019 1:21:00 PM  3/8/2019  12 PM - 3 PM  3/8/2019  BEN 
BLD - Framing Insp.  3/8/2019 10:03:28 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
BLD - Pre-Slab Insp  3/8/2019 10:03:40 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
BLD - Reinforcing Insp  3/8/2019 10:03:47 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
BLD - Footings Insp  3/8/2019 10:03:53 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
ELE - Underground conduit  3/8/2019 10:04:43 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
ELE - Ground Electrode/UFER  3/8/2019 10:05:03 AM  3/11/2019  8 AM - 12 PM  3/11/2019  PJJ 
BLD - Pre-Slab Insp  3/11/2019 8:39:26 AM  3/12/2019  12 PM - 3 PM  3/12/2019  BEN 
BLD - Reinforcing Insp  3/11/2019 8:39:36 AM  3/12/2019  12 PM - 3 PM  3/12/2019  BEN 
BLD - Footings Insp  3/11/2019 8:39:45 AM  3/12/2019  12 PM - 3 PM  3/12/2019  BEN 
ELE - Rough Electrical  3/11/2019 8:39:52 AM  3/12/2019  12 PM - 3 PM  3/12/2019  BEN 
ELE - Ground Electrode/UFER  3/11/2019 8:40:03 AM  3/12/2019  12 PM - 3 PM  3/12/2019  BEN 
Approved by Fire Department  3/11/2019      3/15/2019 2:24:09 PM  APPR  EPO 
Route to Fire Department  3/11/2019  3/19/2019    3/15/2019  APPR  EPO 
Approved by Planning Zoning  3/11/2019      3/18/2019  DONE  EYT 
Route to Planning Zoning  3/11/2019  3/19/2019    3/18/2019  APPR  EYT 
Apprv. by Struct/Architectural  3/11/2019      3/14/2019  APPR  CSG 
Route to Struct/Architectual  3/11/2019  3/19/2019    3/14/2019  APPR  CSG 
BLD - Pre-Slab Insp  3/12/2019 1:57:44 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
BLD - Reinforcing Insp  3/12/2019 1:58:36 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
BLD - Footings Insp  3/12/2019 1:58:45 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
ELE - Underground conduit  3/12/2019 1:59:25 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
ELE - Ground Electrode/UFER  3/12/2019 1:59:35 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
BLD - Framing Insp.  3/12/2019 2:01:55 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BEN 
BLD - Pre-Slab Insp  3/13/2019 1:01:56 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
BLD - Reinforcing Insp  3/13/2019 1:03:14 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
BLD - Footings Insp  3/13/2019 1:03:21 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
ELE - Underground conduit  3/13/2019 1:03:33 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
ELE - Ground Electrode/UFER  3/13/2019 1:03:40 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
BLD - Framing Insp.  3/13/2019 1:04:12 PM  3/14/2019  8 AM - 12 PM  3/14/2019  BEN 
Route to Struct/Architectual  3/14/2019  4/1/2019    3/21/2019  APPR  CSG 
BLD - Pre-Slab Insp  3/15/2019 6:36:29 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
BLD - Footings Insp  3/15/2019 6:36:37 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
BLD - Reinforcing Insp  3/15/2019 6:36:44 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
ELE - Underground conduit  3/15/2019 6:36:57 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
ELE - Ground Electrode/UFER  3/15/2019 6:37:06 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
BLD - Framing Insp.  3/15/2019 6:38:11 AM  3/18/2019  8 AM - 12 PM  3/18/2019  PJJ 
Inspection by Fire Department  3/15/2019  4/2/2019    7/22/2019  DONE  638 
BLD - Pre-Slab Insp  3/18/2019 1:15:50 PM  3/19/2019  8 AM - 12 PM  3/19/2019  BEN 
BLD - Footings Insp  3/18/2019 1:17:02 PM  3/19/2019  8 AM - 12 PM  3/19/2019  BEN 
BLD - Reinforcing Insp  3/18/2019 1:17:09 PM  3/19/2019  8 AM - 12 PM  3/19/2019  BEN 
ELE - Underground conduit  3/18/2019 1:17:18 PM  3/19/2019  8 AM - 12 PM  3/19/2019  BEN 
ELE - Ground Electrode/UFER  3/18/2019 1:17:28 PM  3/19/2019  8 AM - 12 PM  3/19/2019  BEN 
BLD - Footings Insp  3/19/2019 1:54:22 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
BLD - Pre-Slab Insp  3/19/2019 1:54:28 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
BLD - Reinforcing Insp  3/19/2019 1:54:38 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
ELE - Underground conduit  3/19/2019 1:55:21 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
ELE - Ground Electrode/UFER  3/19/2019 1:55:28 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
BLD - Framing Insp.  3/19/2019 1:57:20 PM  3/20/2019  8 AM - 12 PM  3/20/2019  BEN 
BLD - Footings Insp  3/20/2019 12:01:05 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
BLD - Reinforcing Insp  3/20/2019 12:01:16 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
BLD - Pre-Slab Insp  3/20/2019 12:01:24 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
ELE - Underground conduit  3/20/2019 12:01:41 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
ELE - Ground Electrode/UFER  3/20/2019 12:01:53 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
BLD - Framing Insp.  3/20/2019 12:02:03 PM  3/21/2019  8 AM - 12 PM  3/21/2019  BEN 
BLD - Footings Insp  3/21/2019 2:28:33 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
BLD - Pre-Slab Insp  3/21/2019 2:28:39 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
BLD - Reinforcing Insp  3/21/2019 2:28:45 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
ELE - Underground conduit  3/21/2019 2:28:55 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
ELE - Ground Electrode/UFER  3/21/2019 2:29:04 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
BLD - Framing Insp.  3/21/2019 2:29:15 PM  3/22/2019  8 AM - 12 PM  3/22/2019  BEN 
BLD - Pre-Slab Insp  3/22/2019 1:10:08 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
BLD - Footings Insp  3/22/2019 1:10:20 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
BLD - Reinforcing Insp  3/22/2019 1:10:29 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
ELE - Underground conduit  3/22/2019 1:10:38 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
ELE - Ground Electrode/UFER  3/22/2019 1:10:46 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
BLD - Framing Insp.  3/22/2019 1:11:57 PM  3/25/2019  8 AM - 12 PM  3/25/2019  PJJ 
BLD - Footings Insp  3/25/2019 9:52:27 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
BLD - Pre-Slab Insp  3/25/2019 9:52:32 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
BLD - Reinforcing Insp  3/25/2019 9:52:43 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
ELE - Underground conduit  3/25/2019 9:52:50 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
ELE - Ground Electrode/UFER  3/25/2019 9:52:57 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
BLD - Framing Insp.  3/25/2019 9:53:06 AM  3/26/2019  8 AM - 12 PM  3/27/2019  BEN 
BLD - Footings Insp  3/26/2019 2:34:13 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
BLD - Pre-Slab Insp  3/26/2019 2:34:19 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
BLD - Reinforcing Insp  3/26/2019 2:34:25 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
ELE - Underground conduit  3/26/2019 2:35:04 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
ELE - Ground Electrode/UFER  3/26/2019 2:35:12 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
BLD - Framing Insp.  3/26/2019 2:35:51 PM  3/27/2019  12 PM - 3 PM  3/27/2019  BEN 
BLD - Footings Insp  3/27/2019 12:44:42 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
BLD - Reinforcing Insp  3/27/2019 12:45:12 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
BLD - Pre-Slab Insp  3/27/2019 12:45:24 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
ELE - Underground conduit  3/27/2019 12:45:31 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
ELE - Ground Electrode/UFER  3/27/2019 12:46:11 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
BLD - Framing Insp.  3/27/2019 12:46:50 PM  3/28/2019  8 AM - 12 PM  3/28/2019  PJJ 
BLD - Footings Insp  3/28/2019 11:26:08 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
BLD - Pre-Slab Insp  3/28/2019 11:26:23 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
BLD - Reinforcing Insp  3/28/2019 11:26:37 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
ELE - Underground conduit  3/28/2019 11:26:49 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
ELE - Ground Electrode/UFER  3/28/2019 11:26:55 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
BLD - Framing Insp.  3/28/2019 11:27:50 AM  3/29/2019  8 AM - 12 PM  3/29/2019  BEN 
Approved by Planning Zoning  2/27/2019      3/1/2019  DONE  EYT 
Route to Planning Zoning  2/27/2019  3/15/2019    3/1/2019  APPR  EYT 
Route to Struct/Architectual  2/27/2019  3/15/2019    3/1/2019  APPR  CSG 
Apprv. by Struct/Architectural  2/27/2019      3/1/2019  DONE  CSG 
BLD - Pre-Slab Insp  3/29/2019 12:49:31 PM  4/1/2019  10 AM - 2 PM  4/1/2019  PJJ 
BLD - Reinforcing Insp  3/29/2019 12:49:38 PM  4/1/2019  10 AM - 2 PM  4/1/2019  PJJ 
BLD - Footings Insp  3/29/2019 12:49:44 PM  4/1/2019  10 AM - 2 PM  4/1/2019  PJJ 
ELE - Rough Electrical  3/29/2019 12:49:57 PM  4/1/2019  10 AM - 2 PM  4/1/2019  PJJ 
ELE - Ground Electrode/UFER  3/29/2019 12:50:07 PM  4/1/2019  10 AM - 2 PM  4/1/2019  PJJ 
BLD - Footings Insp  4/1/2019 11:20:48 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
BLD - Pre-Slab Insp  4/1/2019 11:20:54 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
BLD - Reinforcing Insp  4/1/2019 11:21:00 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
ELE - Underground conduit  4/1/2019 11:21:06 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
ELE - Ground Electrode/UFER  4/1/2019 11:21:13 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
BLD - Framing Insp.  4/1/2019 11:21:24 AM  4/2/2019  8 AM - 12 PM  4/2/2019  BEN 
BLD - Footings Insp  4/2/2019 11:19:29 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
BLD - Pre-Slab Insp  4/2/2019 11:19:36 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
BLD - Reinforcing Insp  4/2/2019 11:19:44 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
BLD - Framing Insp.  4/2/2019 11:19:58 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
ELE - Underground conduit  4/2/2019 11:20:09 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
ELE - Ground Electrode/UFER  4/2/2019 11:24:45 AM  4/3/2019  8 AM - 12 PM  4/3/2019  BEN 
BLD - Footings Insp  4/3/2019 10:51:50 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
BLD - Reinforcing Insp  4/3/2019 10:51:56 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
BLD - Pre-Slab Insp  4/3/2019 10:52:01 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
BLD - Framing Insp.  4/3/2019 10:52:09 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
ELE - Underground conduit  4/3/2019 10:52:20 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
ELE - Ground Electrode/UFER  4/3/2019 10:52:28 AM  4/4/2019  12 PM - 3 PM  4/4/2019  BEN 
BLD - Footings Insp  4/4/2019 1:31:53 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
BLD - Pre-Slab Insp  4/4/2019 1:32:00 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
BLD - Reinforcing Insp  4/4/2019 1:32:22 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
ELE - Rough Electrical  4/4/2019 1:32:32 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
ELE - Ground Electrode/UFER  4/4/2019 1:32:41 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
BLD - Framing Insp.  4/4/2019 1:32:49 PM  4/5/2019  8 AM - 12 PM  4/5/2019  PJJ 
BLD - Pre-Slab Insp  4/5/2019 9:36:29 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
BLD - Reinforcing Insp  4/5/2019 9:36:35 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
BLD - Footings Insp  4/5/2019 9:36:43 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
ELE - Underground conduit  4/5/2019 9:37:08 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
ELE - Ground Electrode/UFER  4/5/2019 9:37:16 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
BLD - Framing Insp.  4/5/2019 9:37:34 AM  4/8/2019  8 AM - 12 PM  4/8/2019  PJJ 
BLD - Footings Insp  4/5/2019  4/6/2019    4/5/2019  PJJ 
BLD - Pre-Slab Insp  4/5/2019  4/6/2019    4/8/2019  PJJ 
BLD - Footings Insp  4/8/2019 11:43:57 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
BLD - Pre-Slab Insp  4/8/2019 11:44:05 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
BLD - Reinforcing Insp  4/8/2019 11:44:15 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
ELE - Underground conduit  4/8/2019 11:44:21 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
ELE - Ground Electrode/UFER  4/8/2019 11:44:29 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
BLD - Framing Insp.  4/8/2019 11:44:36 AM  4/9/2019  8 AM - 12 PM  4/9/2019  PJJ 
BLD - Footings Insp  4/9/2019 1:25:27 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
BLD - Reinforcing Insp  4/9/2019 1:25:32 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
BLD - Pre-Slab Insp  4/9/2019 1:25:36 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
BLD - Framing Insp.  4/9/2019 1:25:42 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
ELE - Underground conduit  4/9/2019 1:25:54 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
ELE - Ground Electrode/UFER  4/9/2019 1:26:01 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
PLM - Ground/Underfloor waste  4/9/2019 1:36:22 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
PLM - Ground/Underfloor water  4/9/2019 1:36:31 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
MEC - Underground Rough  4/9/2019 1:37:40 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
BLD - Exterior Lath Insp  4/9/2019 1:38:02 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
BLD - Exterior Brown Coat Insp  4/9/2019 1:38:09 PM  4/10/2019  8 AM - 12 PM  4/10/2019  BEN 
Approved by Planning Zoning  4/9/2019      4/12/2019 8:14:25 AM  APPR  EYT 
Route to Planning Zoning  4/9/2019  4/25/2019    4/12/2019  APPR  EYT 
Route to Struct/Architectual  4/9/2019  4/25/2019    4/17/2019  APPR  CSG 
Apprv. by Struct/Architectural  4/9/2019      4/23/2019 12:44:16 PM  APPR  CSG 
BLD - Footings Insp  4/10/2019 11:04:47 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
BLD - Pre-Slab Insp  4/10/2019 11:04:55 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
BLD - Reinforcing Insp  4/10/2019 11:05:03 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
ELE - Underground conduit  4/10/2019 11:05:12 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
ELE - Ground Electrode/UFER  4/10/2019 11:05:19 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
BLD - Framing Insp.  4/10/2019 11:05:26 AM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
PLM - Ground/Underfloor waste  4/10/2019 2:23:14 PM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
PLM - Ground/Underfloor water  4/10/2019 2:23:22 PM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
PLM - Underground gas  4/10/2019 2:23:29 PM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
MEC - Underground Rough  4/10/2019 2:23:41 PM  4/11/2019  8 AM - 12 PM  4/11/2019  BEN 
PLM - Rough/Topout  4/11/2019 10:53:27 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
MEC - Rough Mechanical  4/11/2019 10:53:38 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
BLD - Footings Insp  4/11/2019 10:53:47 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
BLD - Pre-Slab Insp  4/11/2019 10:53:54 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
BLD - Reinforcing Insp  4/11/2019 10:54:00 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
BLD - Framing Insp.  4/11/2019 10:54:11 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
ELE - Underground conduit  4/11/2019 10:54:21 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
ELE - Ground Electrode/UFER  4/11/2019 10:54:27 AM  4/12/2019  8 AM - 12 PM  4/12/2019  BEN 
BLD - Framing Insp.  4/14/2019 2:31:20 PM  4/15/2019  8 AM - 12 PM  4/15/2019  PJJ 
BLD - Pre-Slab Insp  4/14/2019 2:31:37 PM  4/15/2019  8 AM - 12 PM  4/15/2019  PJJ 
ELE - Underground conduit  4/14/2019 2:33:30 PM  4/15/2019  8 AM - 12 PM  4/15/2019  PJJ 
ELE - Ground Electrode/UFER  4/14/2019 2:33:42 PM  4/15/2019  8 AM - 12 PM  4/15/2019  PJJ 
ELE - Rough Electrical  4/15/2019 11:43:36 AM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
ELE - Underground conduit  4/15/2019 11:45:44 AM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
ELE - Ground Electrode/UFER  4/15/2019 11:45:55 AM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
BLD - Framing Insp.  4/15/2019 11:46:01 AM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
PLM - Rough/Topout  4/15/2019 1:21:54 PM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
MEC - Rough Mechanical  4/15/2019 1:22:12 PM  4/16/2019  8 AM - 12 PM  4/16/2019  BEN 
BLD - Framing Insp.  4/16/2019 1:43:05 PM  4/17/2019  12 PM - 3 PM  4/17/2019  BEN 
ELE - Underground conduit  4/16/2019 1:43:15 PM  4/17/2019  12 PM - 3 PM  4/17/2019  BEN 
ELE - Ground Electrode/UFER  4/16/2019 1:43:28 PM  4/17/2019  12 PM - 3 PM  4/17/2019  BEN 
ELE - Rough Electrical  4/16/2019 1:44:12 PM  4/17/2019  12 PM - 3 PM  4/17/2019  BEN 
BLD - Pre-Slab Insp  4/16/2019 2:30:44 PM  4/17/2019  12 PM - 3 PM  4/17/2019  BEN 
Route to Planning Zoning  4/16/2019  5/2/2019    4/24/2019  APPR  EYT 
Approved by Planning Zoning  4/16/2019      4/24/2019 8:50:25 AM  APPR  EYT 
Route to Struct/Architectual  4/16/2019  5/2/2019    4/23/2019  APPR  CSG 
Apprv. by Struct/Architectural  4/16/2019      4/17/2019 2:25:32 PM  APPR  CSG 
BLD - Framing Insp.  4/17/2019 11:02:38 AM  4/18/2019  12 PM - 3 PM  4/18/2019  BEN 
ELE - Ground Electrode/UFER  4/17/2019 11:02:49 AM  4/18/2019  12 PM - 3 PM  4/18/2019  BEN 
ELE - Underground conduit  4/17/2019 11:03:01 AM  4/18/2019  12 PM - 3 PM  4/18/2019  BEN 
ELE - Underground conduit  4/18/2019 2:18:21 PM  4/19/2019  12 PM - 3 PM  4/19/2019  BEN 
BLD - Framing Insp.  4/18/2019 2:18:33 PM  4/19/2019  12 PM - 3 PM  4/19/2019  BEN 
BLD - Framing Insp.  4/21/2019 2:39:35 PM  4/22/2019  8 AM - 12 PM  4/22/2019  PJJ 
ELE - Underground conduit  4/21/2019 2:41:06 PM  4/22/2019  8 AM - 12 PM  4/22/2019  PJJ 
ELE - Ground Electrode/UFER  4/21/2019 2:41:16 PM  4/22/2019  8 AM - 12 PM  4/22/2019  PJJ 
ELE - Underground conduit  4/22/2019 9:52:19 AM  4/23/2019  12 PM - 3 PM  4/23/2019  BEN 
ELE - Ground Electrode/UFER  4/22/2019 9:52:30 AM  4/23/2019  12 PM - 3 PM  4/23/2019  BEN 
BLD - Framing Insp.  4/22/2019 9:53:28 AM  4/23/2019  12 PM - 3 PM  4/23/2019  BEN 
ELE - Rough Electrical  4/22/2019 9:53:46 AM  4/23/2019  12 PM - 3 PM  4/23/2019  BEN 
BLD - Framing Insp.  4/23/2019 2:14:25 PM  4/24/2019  8 AM - 12 PM  4/24/2019  BEN 
BLD - TCO App Consideration  4/24/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BEN 
BLD - Framing Insp.  4/24/2019 4:58:49 PM  4/25/2019  8 AM - 12 PM  4/25/2019  BEN 
BLD - TCO App Consideration  4/25/2019  4/26/2019  12 PM - 3 PM  4/26/2019  BEN 
Electrical Final Insp Request  4/25/2019 4:45:07 PM  4/26/2019  12 PM - 3 PM  4/26/2019  BEN 
Plumbing Final Insp Request  4/25/2019 4:45:21 PM  4/26/2019  12 PM - 3 PM  4/26/2019  BEN 
Mechanical Final Insp Request  4/25/2019 4:45:48 PM  4/26/2019  12 PM - 3 PM  4/26/2019  BEN 
BLD - TCO App Consideration  4/26/2019  4/27/2019  8 AM - 12 PM  4/27/2019  BEN 
Electrical Final        4/26/2019    BEN 
Electrical Final Insp Request  4/27/2019 10:19:38 AM  4/29/2019  10 AM - 2 PM  4/29/2019  PJJ 
ELE - Rough Electrical  5/2/2019 12:39:47 PM  5/3/2019    5/3/2019  BEN 
BLD - Framing Insp.  5/2/2019 4:37:59 PM  5/3/2019    5/3/2019  BEN 
Building Final Insp Request  7/22/2019 7:59:06 AM  7/23/2019  8 AM - 12 PM  7/23/2019  BEN 
Mechanical Final Insp Request  7/23/2019 2:04:31 PM  7/24/2019  8 AM - 12 PM  7/24/2019  BEN 
Building Final Insp Request  7/23/2019 2:04:51 PM  7/24/2019  8 AM - 12 PM  7/24/2019  BEN 
Building Final        7/23/2019    BEN 
Building Final        7/24/2019    BEN 
Mechanical Final        7/24/2019    BEN 
Plumbing Final Insp Request  7/26/2019  7/26/2019    7/26/2019  BEN 
Plumbing Final        7/26/2019    BEN 

 