Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Planning Zoning  |
9/20/2019  |
9/27/2019  |
  |
10/3/2019  |
CORR  |
EYT  |
Approved by Planning Zoning  |
9/20/2019  |
  |
  |
10/18/2019  |
DONE  |
EYT  |
Route to PW Develop. Services  |
9/20/2019  |
9/27/2019  |
  |
10/1/2019  |
APPR  |
SXA  |
Apprv. by PW Develop. Services  |
9/20/2019  |
  |
  |
10/1/2019  |
DONE  |
SXA  |
Route to Struct/Architectural  |
9/20/2019  |
9/27/2019  |
  |
9/24/2019  |
CORR  |
ZID  |
Route to Traffic Engineering  |
9/20/2019  |
9/27/2019  |
  |
9/30/2019  |
APPR  |
RXC  |
Approved by Traffic Eng.  |
9/20/2019  |
  |
  |
9/30/2019  |
DONE  |
RXC  |
Apprv. by Struct/Architectural  |
9/20/2019  |
  |
  |
10/14/2019  |
DONE  |
ZID  |
Route to Planning Zoning  |
10/11/2019  |
10/18/2019  |
  |
10/18/2019  |
APPR  |
EYT  |
Route to Struct/Architectural  |
10/11/2019  |
10/18/2019  |
  |
10/14/2019  |
APPR  |
ZID  |
Underground Conduit  |
10/21/2019 11:35:21 AM  |
10/24/2019  |
  |
10/23/2019  |
CANC  |
  |
Masonry(reinf/bond beam/pre go  |
10/25/2019  |
10/26/2019  |
  |
10/29/2019  |
P  |
BEN  |
Underground Conduit  |
10/25/2019  |
10/26/2019  |
  |
10/29/2019  |
P  |
BEN  |
Sign Final Request  |
2/14/2020  |
2/18/2020  |
12 PM - 3 PM  |
2/18/2020  |
A  |
PJJ  |
Sign Final  |
  |
  |
  |
2/18/2020  |
  |
PJJ  |