Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Struct/Architectual  |
2/25/2021  |
3/11/2021  |
  |
3/11/2021  |
APPR  |
ZID  |
Apprv. by Struct/Architectural  |
2/25/2021  |
  |
  |
3/11/2021 10:11:26 AM  |
APPR  |
ZID  |
Route to Planning Zoning  |
2/25/2021  |
3/11/2021  |
  |
3/12/2021  |
APPR  |
EYT  |
Approved by Planning Zoning  |
2/25/2021  |
  |
  |
3/12/2021 11:55:29 AM  |
APPR  |
EYT  |
Approved by Electrical  |
2/25/2021  |
  |
  |
3/12/2021 8:19:29 AM  |
APPR  |
JFR  |
Route to Electrical  |
2/25/2021  |
3/11/2021  |
  |
3/12/2021  |
APPR  |
JFR  |
Approved by Elec Engineering  |
2/25/2021  |
  |
  |
3/9/2021 8:28:43 AM  |
APPR  |
NEG  |
Route to Elec Engineering  |
2/25/2021  |
3/11/2021  |
  |
3/9/2021  |
APPR  |
NEG  |
Approved by Fire Department  |
2/25/2021  |
  |
  |
3/12/2021 10:38:10 AM  |
APPR  |
DRZ  |
Route to Fire Department  |
2/25/2021  |
3/11/2021  |
  |
3/12/2021  |
APPR  |
DRZ  |
Approved by Mechanical  |
2/25/2021  |
  |
  |
3/10/2021 4:29:35 PM  |
APPR  |
EWC  |
Route to Mechanical  |
2/25/2021  |
3/11/2021  |
  |
3/10/2021  |
APPR  |
EWC  |
Approved by Plumbing  |
2/25/2021  |
  |
  |
3/10/2021 4:29:05 PM  |
APPR  |
EWC  |
Route to Plumbing  |
2/25/2021  |
3/11/2021  |
  |
3/10/2021  |
APPR  |
EWC  |
Inspection by Fire Department  |
3/12/2021  |
3/26/2021  |
  |
7/2/2021  |
DONE  |
638  |
Approved Revision Structural  |
4/22/2021  |
  |
  |
4/29/2021  |
APPR  |
CSG  |
Route Revision Structural  |
4/22/2021  |
5/6/2021  |
  |
4/29/2021  |
APPR  |
ZID  |
BLD - Framing Insp.  |
5/7/2021 12:00:04 PM  |
5/10/2021  |
8 AM - 12 PM  |
5/10/2021  |
P  |
PJJ  |
BLD - Framing Insp.  |
5/13/2021 1:49:19 PM  |
5/14/2021  |
8 AM - 12 PM  |
5/14/2021  |
P  |
BEN  |
BLD - Framing Insp.  |
5/14/2021 12:32:27 PM  |
5/17/2021  |
8 AM - 12 PM  |
5/17/2021  |
P  |
PJJ  |
BLD - Framing Insp.  |
5/19/2021 12:13:42 PM  |
5/25/2021  |
8 AM - 12 PM  |
5/25/2021  |
N  |
PJJ  |
BLD - Drywall Inspection  |
5/19/2021 12:14:42 PM  |
5/21/2021  |
12 PM - 3 PM  |
5/21/2021  |
A  |
BEN  |
BLD - Framing Insp.  |
5/25/2021 11:25:27 AM  |
5/26/2021  |
8 AM - 12 PM  |
5/26/2021  |
P  |
BEN  |
BLD - Drywall Inspection  |
5/26/2021 12:28:09 PM  |
5/27/2021  |
8 AM - 12 PM  |
5/27/2021  |
A  |
BEN  |
BLD - T-Bar (Structural) Insp  |
5/28/2021 8:40:15 AM  |
6/1/2021  |
  |
5/28/2021  |
C  |
ALY  |
BLD - T-Bar (Structural) Insp  |
6/8/2021 4:19:56 PM  |
6/9/2021  |
8 AM - 12 PM  |
6/9/2021  |
A  |
BEN  |
Approved by Bus Lic (Sub List)  |
6/30/2021  |
6/30/2021  |
  |
7/8/2021  |
APPR  |
RHZ  |
BLD - Framing Insp.  |
7/7/2021 12:23:17 PM  |
7/8/2021  |
8 AM - 12 PM  |
7/8/2021  |
P  |
BEN  |
Building Final Insp Request  |
7/9/2021 3:50:40 PM  |
7/12/2021  |
8 AM - 12 PM  |
7/12/2021  |
A  |
PJJ  |
Building Final  |
  |
  |
  |
7/12/2021  |
  |
PJJ  |