Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Approved by Traffic Eng.  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
RXC  |
Apprv. by PW Develop. Services  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
SXA  |
FIRE - Create BFP case  |
2/1/2021  |
  |
  |
  |
  |
  |
Approved by Fire Department  |
2/1/2021  |
  |
  |
2/9/2021  |
APPR  |
DRS  |
Approved by Plumbing  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
EWC  |
Approved by Mechanical  |
2/1/2021  |
  |
  |
2/9/2021  |
N/A  |
EWC  |
Apprv. by Struct/Architectural  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
ZID  |
Approved by Planning Zoning  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
EYT  |
Approved by Electrical  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
JFR  |
Approved by Bus Lic (Sub List)  |
2/1/2021  |
2/18/2021  |
  |
2/25/2021  |
APPR  |
RHZ  |
Approved by Elec Engineering  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
JJB  |
Approved by Water Engineering  |
2/1/2021  |
  |
  |
2/9/2021  |
DONE  |
DRS  |
Approved: School Fees Due  |
2/1/2021  |
  |
  |
2/9/2021  |
APPR  |
CMN  |
Inspection by Fire Department  |
2/9/2021  |
2/24/2021  |
  |
2/24/2021  |
DONE  |
638  |
ELE - Underground conduit  |
2/9/2021  |
2/10/2021  |
10 AM - 2 PM  |
2/10/2021  |
F  |
BEN  |
PLM - Water Service  |
2/9/2021  |
2/10/2021  |
10 AM - 2 PM  |
2/10/2021  |
A  |
BEN  |
PLM - Sewer  |
2/9/2021  |
2/10/2021  |
10 AM - 2 PM  |
2/10/2021  |
A  |
BEN  |
PLM - Ground/Underfloor waste  |
2/18/2021  |
2/19/2021  |
8 AM - 12 PM  |
2/19/2021  |
C  |
BEN  |
PLM - Ground/Underfloor water  |
2/18/2021  |
2/19/2021  |
8 AM - 12 PM  |
2/19/2021  |
C  |
BEN  |
ELE - Ground Electrode/UFER  |
2/23/2021  |
2/24/2021  |
10 AM - 2 PM  |
2/23/2021  |
C  |
ALY  |
ELE - Underground conduit  |
2/23/2021  |
2/24/2021  |
10 AM - 2 PM  |
2/24/2021  |
N  |
PJJ  |
Electrical Final Insp Request  |
2/23/2021  |
2/24/2021  |
10 AM - 2 PM  |
2/24/2021  |
N  |
PJJ  |
Plumbing Final Insp Request  |
2/23/2021  |
2/24/2021  |
10 AM - 2 PM  |
2/24/2021  |
A  |
PJJ  |
BLD - Footings Insp  |
2/23/2021  |
2/24/2021  |
10 AM - 2 PM  |
2/24/2021  |
P  |
PJJ  |
Plumbing Final  |
  |
  |
  |
2/24/2021  |
  |
PJJ  |
ELE - Underground conduit  |
2/24/2021  |
2/25/2021  |
8 AM - 12 PM  |
2/25/2021  |
A  |
BEN  |
ELE - Rough Electrical  |
2/24/2021  |
2/25/2021  |
8 AM - 12 PM  |
2/25/2021  |
N  |
BEN  |
Electrical Final Insp Request  |
2/24/2021  |
2/25/2021  |
8 AM - 12 PM  |
2/25/2021  |
N  |
BEN  |
ELE - Rough Electrical  |
3/1/2021  |
3/2/2021  |
8 AM - 12 PM  |
3/2/2021  |
F  |
BEN  |
Electrical Final Insp Request  |
3/5/2021 1:19:59 PM  |
3/8/2021  |
  |
3/8/2021  |
NA  |
PJJ  |
ELE - Rough Electrical  |
3/8/2021 2:05:40 PM  |
3/9/2021  |
8 AM - 12 PM  |
3/9/2021  |
A  |
PJJ  |
Electrical Final Insp Request  |
3/8/2021 2:07:16 PM  |
3/9/2021  |
8 AM - 12 PM  |
3/9/2021  |
A  |
PJJ  |
Electrical Final  |
  |
  |
  |
3/9/2021  |
  |
PJJ  |
Building Final Insp Request  |
3/9/2021 3:36:26 PM  |
3/10/2021  |
10 AM - 2 PM  |
3/10/2021  |
A  |
BEN  |
Planning GIS - Building Change  |
3/10/2021 2:33:52 PM  |
  |
  |
4/5/2021  |
DONE  |
MAR3  |
Building Final  |
  |
  |
  |
3/10/2021  |
  |
BEN  |