Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to C&D Waste Mgmt  |
3/2/2020  |
3/9/2020  |
  |
3/11/2020  |
APPR  |
RGO  |
Approved by C&D Waste Mgmt  |
3/2/2020  |
  |
  |
3/11/2020  |
APPR  |
RGO  |
Approved by Electrical  |
3/2/2020  |
  |
  |
3/4/2020 8:39:07 AM  |
APPR  |
MCS  |
Route to Electrical  |
3/2/2020  |
3/9/2020  |
  |
3/4/2020  |
APPR  |
MCS  |
Approved by Elec Engineering  |
3/2/2020  |
  |
  |
3/9/2020 10:52:29 AM  |
APPR  |
JJB  |
Route to Elec Engineering  |
3/2/2020  |
3/9/2020  |
  |
3/9/2020  |
APPR  |
JJB  |
Approved by Fire Department  |
3/2/2020  |
  |
  |
3/6/2020 11:13:55 AM  |
APPR  |
472  |
Route to Fire Department  |
3/2/2020  |
3/9/2020  |
  |
3/6/2020  |
APPR  |
472  |
Approved by Planning Zoning  |
3/2/2020  |
  |
  |
3/5/2020 9:27:12 AM  |
APPR  |
EYT  |
Route to Planning Zoning  |
3/2/2020  |
3/9/2020  |
  |
3/5/2020  |
APPR  |
EYT  |
Apprv. by Struct/Architectural  |
3/2/2020  |
  |
  |
3/17/2020 12:10:25 PM  |
APPR  |
ITW  |
Route to Struct/Architectual  |
3/2/2020  |
3/9/2020  |
  |
3/17/2020  |
APPR  |
ITW  |
Inspection by Fire Department  |
3/6/2020  |
3/13/2020  |
  |
4/30/2021  |
DONE  |
638  |
Approved by Bus Lic (Sub List)  |
11/4/2020  |
11/12/2020  |
  |
11/12/2020  |
APPR  |
RHZ  |
BLD - Roof Sheathing Insp.  |
4/28/2021  |
4/29/2021  |
12 PM - 3 PM  |
4/29/2021  |
NA  |
BEN  |
Building Final Insp Request  |
5/3/2021 10:26:01 AM  |
5/4/2021  |
8 AM - 12 PM  |
5/4/2021  |
A  |
BEN  |
Building Final  |
  |
  |
  |
5/4/2021  |
  |
BEN  |