View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2019-04210     Status:   Issued     Map Info:   1313 S HARBOR BLVD 6205
Name:  WALT DISNEY WORLD CO
Address: 1313 S HARBOR 6205
Received Date: 08/26/2019 
Parcel: 08211074 
Plan Check Date:  
Issue Date: 11/05/2019 
Expiration Date: 12/05/2021 
Finaled Date:  
Description: Disney - Bldg 6205 - Non Residential Addition: (Core and Shell) 119,558 sq.ft to construction 3 story building with associated underground plumbing, electrical for future project. (West) Canopy 1,656 sq.ft and (South) Canopy 284 sq.ft, (6) awnings.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Traffic Engineering  8/26/2019  9/12/2019    9/4/2019  APPR  RXC 
Approved by Traffic Eng.  8/26/2019      9/4/2019 8:14:32 AM  APPR  RXC 
Route to PW Develop. Services  8/26/2019  9/12/2019    9/17/2019  CORR  SXA 
Apprv. by PW Develop. Services  8/26/2019      10/31/2019 12:11:24 PM  APPR  SXA 
Route to Fire Department  8/26/2019  9/12/2019    9/12/2019  CORR  EPO 
Approved by Fire Department  8/26/2019      10/15/2019 3:00:33 PM  APPR  EPO 
Route to Elec Engineering  8/26/2019  9/12/2019    9/10/2019  APPR  NEG 
Approved by Elec Engineering  8/26/2019      9/10/2019 8:14:58 AM  APPR  NEG 
Route to Struct/Architectual  8/26/2019  9/12/2019    9/12/2019  CORR  ITW 
Apprv. by Struct/Architectural  8/26/2019      10/23/2019 5:01:26 PM  APPR  ITW 
Approved by Planning Zoning  8/26/2019      10/29/2019 11:54:25 AM  APPR  EYT 
Route to Water Engineering  8/26/2019  9/12/2019    9/11/2019  APPR  DRS 
Approved by Water Engineering  8/26/2019      9/11/2019 11:24:07 AM  APPR  DRS 
Approved: School Fees Due  8/26/2019      11/5/2019  APPR  CMN 
Route to Mechanical  8/26/2019  9/12/2019    9/10/2019  NR  EWC 
Approved by Mechanical  8/26/2019      9/10/2019 9:55:25 AM  NR  EWC 
Route to Electrical  8/26/2019  9/12/2019    9/12/2019  APPR  MCS 
Approved by Electrical  8/27/2019      9/12/2019 6:49:42 AM  APPR  MCS 
Approved by Plumbing  8/26/2019      9/10/2019 9:55:05 AM  APPR  EWC 
Route to Plumbing  8/26/2019  9/12/2019    9/10/2019  APPR  EWC 
Route to Planning Zoning  8/26/2019  9/12/2019    9/13/2019  CORR  EYT 
Route to Struct/Architectual  10/1/2019  10/17/2019    10/16/2019  CORR  ITW 
Route to Fire Department  10/1/2019  10/17/2019    10/15/2019  APPR  EPO 
Route to Planning Zoning  10/1/2019  10/17/2019    10/21/2019  CORR  EYT 
Route to PW Develop. Services  10/1/2019  10/17/2019    10/17/2019  CORR  SXA 
Approved by C&D Waste Mgmt  8/26/2019      11/5/2019  APPR  RGO 
Route to C&D Waste Mgmt  10/1/2019  10/17/2019    11/5/2019  APPR  RGO 
Route to C&D Waste Mgmt  10/23/2019  11/8/2019    11/5/2019  APPR  RGO 
Route to Planning Zoning  10/23/2019  11/8/2019    10/29/2019  APPR  EYT 
Route to PW Develop. Services  10/23/2019  11/8/2019    10/31/2019  APPR  SXA 
Route to Struct/Architectual  10/23/2019  11/8/2019    10/23/2019  APPR  ITW 
Route to Fire Department  11/5/2019  11/22/2019    11/21/2019  NR  EPO 
Approved by Fire Department  11/5/2019      11/21/2019 3:32:52 PM  NR  EPO 
Route to Planning Zoning  11/5/2019  11/22/2019    11/7/2019  APPR  EYT 
Approved by Planning Zoning  11/5/2019      11/7/2019 1:25:20 PM  APPR  EYT 
Apprv. by PW Develop. Services  11/5/2019      11/22/2019 3:26:54 PM  APPR  SXA 
Route to PW Develop. Services  11/5/2019  11/22/2019    11/22/2019  APPR  SXA 
Approved Revision Structural  11/5/2019      12/4/2019  DONE  ITW 
Route Revision Structural  11/5/2019  11/22/2019    11/21/2019  CORR  ITW 
Inspection by Fire Department  11/21/2019  12/11/2019         
Route Revision Structural  12/4/2019  12/20/2019    12/4/2019  APPR  ITW 
ELE - Underground conduit  1/3/2020  1/4/2020  8 AM - 12 PM  1/7/2020  BEN 
ELE - Underground conduit  1/6/2020 11:21:58 AM  1/7/2020  8 AM - 12 PM  1/7/2020  BEN 
ELE - Underground conduit  1/7/2020 2:24:53 PM  1/8/2020  8 AM - 12 PM  1/8/2020  BEN 
ELE - Underground conduit  1/9/2020 12:14:26 PM  1/10/2020  8 AM - 12 PM  1/10/2020  BEN 
ELE - Underground conduit  1/10/2020 2:58:37 PM  1/13/2020  8 AM - 12 PM  1/13/2020  PJJ 
ELE - Underground conduit  1/10/2020  1/11/2020    1/14/2020  BEN 
ELE - Underground conduit  1/13/2020 2:28:43 PM  1/14/2020  8 AM - 12 PM  1/14/2020  BEN 
ELE - Underground conduit  1/15/2020 12:05:41 PM  1/16/2020  8 AM - 12 PM  1/16/2020  BEN 
ELE - Underground conduit  1/16/2020 11:47:24 AM  1/17/2020  8 AM - 12 PM  1/17/2020  PJJ 
ELE - Underground conduit  1/21/2020 10:13:17 AM  1/23/2020  10 AM - 2 PM  1/23/2020  PJJ 
ELE - Underground conduit  1/23/2020 1:48:20 PM  1/24/2020  8 AM - 12 PM  1/24/2020  BEN 
ELE - Underground conduit  1/28/2020 12:42:16 PM  1/29/2020  8 AM - 12 PM  1/29/2020  BEN 
ELE - Underground conduit  1/30/2020  2/1/2020    2/4/2020  BEN 
Approved by Electrical  2/4/2020      2/4/2020  APPR  MCS 
BLD - Footings Insp  2/4/2020 2:54:58 PM  2/5/2020  8 AM - 12 PM  2/5/2020  BEN 
ELE - Ground Electrode/UFER  2/4/2020 2:57:36 PM  2/5/2020  8 AM - 12 PM  2/5/2020  BEN 
Approved Revision Electrical        2/4/2020  DONE  MCS 
Route Revision Electrical  2/4/2020  2/21/2020    2/4/2020  APPR  MCS 
ELE - Underground conduit  2/7/2020 10:51:35 AM  2/10/2020  8 AM - 12 PM  2/10/2020  PJJ 
BLD - Footings Insp  2/10/2020 1:39:05 PM  2/11/2020  8 AM - 12 PM  2/11/2020  BEN 
ELE - Ground Electrode/UFER  2/10/2020 1:39:46 PM  2/11/2020  8 AM - 12 PM  2/11/2020  BEN 
BLD - Footings Insp  2/11/2020 1:52:52 PM  2/12/2020  8 AM - 12 PM  2/12/2020  BEN 
BLD - Reinforcing Insp  2/12/2020 2:25:04 PM  2/13/2020  8 AM - 12 PM  2/13/2020  BEN 
BLD - Penetrations -Fire Rated  2/12/2020 2:37:30 PM  2/13/2020  8 AM - 12 PM  2/13/2020  BEN 
ELE - Penetrations- Fire Rated  2/12/2020 2:38:13 PM  2/13/2020  8 AM - 12 PM  2/13/2020  BEN 
BLD - Reinforcing Insp  2/13/2020 2:24:44 PM  2/14/2020  8 AM - 12 PM  2/14/2020  BEN 
PLM - Ground/Underfloor waste  2/13/2020 2:26:59 PM  2/14/2020  8 AM - 12 PM  2/14/2020  BEN 
ELE - Underground conduit  2/17/2020 12:48:29 PM  2/18/2020  8 AM - 12 PM  2/18/2020  PJJ 
BLD - Reinforcing Insp  2/17/2020 12:49:02 PM  2/18/2020  8 AM - 12 PM  2/18/2020  PJJ 
BLD - Footings Insp  2/17/2020 12:50:03 PM  2/18/2020  8 AM - 12 PM  2/18/2020  PJJ 
ELE - Ground Electrode/UFER  2/17/2020 12:50:42 PM  2/18/2020  8 AM - 12 PM  2/18/2020  PJJ 
BLD - Footings Insp  2/18/2020 3:20:24 PM  2/19/2020  8 AM - 12 PM  2/19/2020  PJJ 
BLD - Reinforcing Insp  2/18/2020 3:21:34 PM  2/19/2020  8 AM - 12 PM  2/19/2020  PJJ 
BLD - Reinforcing Insp  2/21/2020 1:22:01 PM  2/24/2020  10 AM - 2 PM  2/24/2020  PJJ 
ELE - Underground conduit  2/21/2020 1:23:27 PM  2/24/2020  10 AM - 2 PM  2/24/2020  PJJ 
PLM - Rough/Topout  2/21/2020 1:23:55 PM  2/24/2020  10 AM - 2 PM  2/24/2020  PJJ 
ELE - Ground Electrode/UFER  2/21/2020 1:33:54 PM  2/24/2020  10 AM - 2 PM  2/24/2020  PJJ 
PLM - Rough/Topout  2/24/2020 2:46:56 PM  2/25/2020  8 AM - 12 PM  2/25/2020  PJJ 
ELE - Rough Electrical  2/24/2020 2:48:01 PM  2/25/2020  8 AM - 12 PM  2/25/2020  PJJ 
BLD - Reinforcing Insp  2/25/2020 3:32:39 PM  2/26/2020  12 PM - 3 PM  2/26/2020  BEN 
ELE - Underground conduit  2/25/2020 3:33:18 PM  2/26/2020  12 PM - 3 PM  2/26/2020  BEN 
BLD - Reinforcing Insp  2/27/2020 3:01:14 PM  2/28/2020  8 AM - 12 PM  2/28/2020  PJJ 
PLM - Rough/Topout  2/27/2020 3:01:50 PM  2/28/2020  8 AM - 12 PM  2/28/2020  PJJ 
ELE - Underground conduit  2/28/2020 2:53:46 PM  3/2/2020  8 AM - 12 PM  3/2/2020  PJJ 
BLD - Reinforcing Insp  2/28/2020 2:58:57 PM  3/2/2020  8 AM - 12 PM  3/2/2020  PJJ 
BLD - Reinforcing Insp  3/2/2020 1:59:08 PM  3/3/2020  8 AM - 12 PM  3/3/2020  BEN 
BLD - Reinforcing Insp  3/3/2020  3/3/2020    3/4/2020  PJJ 
ELE - Ground Electrode/UFER  3/3/2020  3/3/2020    3/4/2020  PJJ 
BLD - Reinforcing Insp  3/3/2020 2:51:47 PM  3/4/2020  12 PM - 3 PM  3/4/2020  BEN 
PLM - Rough/Topout  3/3/2020 3:57:25 PM  3/4/2020  12 PM - 3 PM  3/4/2020  BEN 
BLD - Reinforcing Insp  3/5/2020 3:47:02 PM  3/6/2020  8 AM - 12 PM  3/6/2020  BEN 
Route Revision Structural  3/9/2020  3/16/2020    3/13/2020  APPR  ITW 
Approved Revision Structural  3/9/2020      3/13/2020  DONE  ITW 
BLD - Reinforcing Insp  3/9/2020 3:39:28 PM  3/10/2020  8 AM - 12 PM  3/10/2020  PJJ 
PLM - Rough/Topout  3/9/2020 3:40:13 PM  3/10/2020  8 AM - 12 PM  3/10/2020  PJJ 
BLD - Reinforcing Insp  3/12/2020 1:11:04 PM  3/13/2020  10 AM - 2 PM  3/13/2020  PJJ 
Route to Planning Zoning  4/20/2020  5/11/2020    5/1/2020  APPR  EYT 
Approved Revision Structural  4/20/2020      5/13/2020  APPR  ITW 
Route Revision Structural  4/20/2020  5/11/2020    5/13/2020  APPR  ITW 
Approved by Fire Department  4/20/2020      5/11/2020 4:12:46 PM  APPR  LIY 
Route to Fire Department  4/20/2020  5/11/2020    5/11/2020  APPR  LIY 
Approved by Planning Zoning  4/20/2020      5/1/2020 8:38:25 AM  APPR  EYT 
Inspection by Fire Department  5/11/2020  5/28/2020         
ELE - Underground conduit  6/26/2020 10:53:23 AM  6/29/2020  8 AM - 12 PM  6/29/2020  JOS 
ELE - Underground conduit  7/10/2020 2:51:24 PM  7/13/2020  10 AM - 2 PM  7/13/2020  JOS 
BLD - Reinforcing Insp  7/14/2020 2:18:22 PM  7/15/2020  8 AM - 12 PM  7/15/2020  BEN 
BLD - Reinforcing Insp  7/15/2020 2:39:32 PM  7/16/2020  12 PM - 3 PM  7/16/2020  BEN 
BLD - Reinforcing Insp  7/16/2020 2:41:56 PM  7/17/2020  8 AM - 12 PM  7/17/2020  BEN 
ELE - Ground Electrode/UFER  7/17/2020 1:33:02 PM  7/20/2020  8 AM - 12 PM  7/20/2020  JOS 
BLD - Reinforcing Insp  7/20/2020 2:36:10 PM  7/21/2020  8 AM - 12 PM  7/21/2020  BEN 
PLM - Rough/Topout  7/20/2020 2:36:57 PM  7/21/2020  8 AM - 12 PM  7/21/2020  BEN 
BLD - Reinforcing Insp  7/22/2020 2:54:00 PM  7/23/2020  8 AM - 12 PM  7/23/2020  BEN 
PLM - Rough/Topout  7/22/2020 2:54:50 PM  7/23/2020  8 AM - 12 PM  7/23/2020  BEN 
BLD - Reinforcing Insp  7/27/2020 2:11:34 PM  7/28/2020  8 AM - 12 PM  7/28/2020  BEN 
BLD - Reinforcing Insp  7/28/2020 2:38:00 PM  7/29/2020  8 AM - 12 PM  7/29/2020  BEN 
PLM - Rough/Topout  7/28/2020 2:38:48 PM  7/29/2020  8 AM - 12 PM  7/29/2020  BEN 
BLD - Reinforcing Insp  7/31/2020 1:54:33 PM  8/3/2020  8 AM - 12 PM  8/3/2020  GCT 
PLM - Rough/Topout  7/31/2020 1:55:24 PM  8/3/2020  8 AM - 12 PM  8/3/2020  GCT 
BLD - Reinforcing Insp  8/3/2020 3:10:56 PM  8/4/2020  8 AM - 12 PM  8/4/2020  BEN 
ELE - Ground Electrode/UFER  8/3/2020 3:11:23 PM  8/4/2020  8 AM - 12 PM  8/4/2020  BEN 
ELE - Ground Electrode/UFER  8/4/2020 12:53:24 PM  8/5/2020  8 AM - 12 PM  8/5/2020  BEN 
BLD - Reinforcing Insp  8/4/2020 12:53:45 PM  8/5/2020  8 AM - 12 PM  8/5/2020  BEN 
BLD - Reinforcing Insp  8/10/2020 1:23:56 PM  8/11/2020  8 AM - 12 PM  8/11/2020  BEN 
PLM - Rough/Topout  8/10/2020 1:24:33 PM  8/11/2020  8 AM - 12 PM  8/11/2020  BEN 
PLM - Underfloor Gas  8/11/2020 3:15:36 PM  8/12/2020  8 AM - 12 PM  8/12/2020  BEN 
PLM - Misc. Inspection  8/11/2020  8/11/2020  8 AM - 12 PM  8/11/2020  BEN 
BLD - Reinforcing Insp  8/12/2020 2:35:58 PM  8/13/2020  12 PM - 3 PM  8/13/2020  BEN 
PLM - Underground gas  8/12/2020 2:36:35 PM  8/13/2020  12 PM - 3 PM  8/13/2020  BEN 
BLD - Reinforcing Insp  8/13/2020 2:20:51 PM  8/14/2020  8 AM - 12 PM  8/14/2020  BEN 
PLM - Underground gas  8/14/2020 2:41:13 PM  8/17/2020  8 AM - 12 PM  8/17/2020  PJJ 
BLD - Reinforcing Insp  8/17/2020 2:34:06 PM  8/18/2020  8 AM - 12 PM  8/18/2020  PJJ 
BLD - Reinforcing Insp  8/18/2020 2:36:23 PM  8/19/2020  8 AM - 12 PM  8/19/2020  BEN 
BLD - Reinforcing Insp  8/19/2020 2:55:54 PM  8/20/2020    8/20/2020  BEN 
BLD - Reinforcing Insp  8/21/2020 2:26:36 PM  8/24/2020  8 AM - 12 PM  8/24/2020  PJJ 
PLM - Rough/Topout  8/21/2020 2:27:47 PM  8/24/2020  8 AM - 12 PM  8/24/2020  PJJ 
BLD - Reinforcing Insp  8/31/2020 1:23:53 PM  9/1/2020  8 AM - 12 PM  9/1/2020  BEN 
ELE - Underground conduit  9/1/2020 12:16:13 PM  9/2/2020  8 AM - 12 PM  9/2/2020  BEN 
BLD - Reinforcing Insp  9/10/2020 2:13:01 PM  9/11/2020  8 AM - 12 PM  9/11/2020  BEN 
BLD - Reinforcing Insp  9/11/2020 12:35:49 PM  9/14/2020  8 AM - 12 PM  9/14/2020  PJJ 
BLD - Reinforcing Insp  9/14/2020 3:20:01 PM  9/15/2020  8 AM - 12 PM  9/15/2020  BEN 
BLD - Reinforcing Insp  9/18/2020 12:26:36 PM  9/21/2020  8 AM - 12 PM  9/21/2020  KLA 
BLD - Pre-Slab Insp  9/28/2020 11:40:23 AM  9/29/2020  8 AM - 12 PM  9/29/2020  BEN 
BLD - Pre-Grout Insp  9/29/2020 1:43:11 PM  9/30/2020  8 AM - 12 PM  9/30/2020  BEN 
BLD - Pre-Grout Insp  9/30/2020 2:55:59 PM  10/1/2020  8 AM - 12 PM  10/1/2020  BEN 
BLD - Reinforcing Insp  10/5/2020 1:43:01 PM  10/6/2020  8 AM - 12 PM  10/6/2020  BEN 
ELE - Ground Electrode/UFER  10/5/2020 1:43:50 PM  10/6/2020  8 AM - 12 PM  10/6/2020  BEN 
BLD - Reinforcing Insp  10/12/2020 3:09:31 PM  10/13/2020  8 AM - 12 PM  10/13/2020  BEN 
BLD - Reinforcing Insp  10/13/2020 1:44:56 PM  10/14/2020  8 AM - 12 PM  10/14/2020  BEN 
BLD - Footings Insp  10/13/2020 1:46:20 PM  10/14/2020  8 AM - 12 PM  10/14/2020  BEN 
BLD - Framing Insp.  10/13/2020 1:49:53 PM  10/14/2020  8 AM - 12 PM  10/14/2020  BEN 
BLD - Reinforcing Insp  10/19/2020 4:25:15 PM  10/20/2020  8 AM - 12 PM  10/20/2020  BEN 
BLD - Framing Insp.  10/20/2020 3:20:44 PM  10/21/2020  8 AM - 12 PM  10/21/2020  BEN 
BLD - Pre-Grout Insp  10/21/2020 2:50:12 PM  10/22/2020  8 AM - 12 PM  10/22/2020  BEN 
BLD - Pre-Slab Insp  10/22/2020 3:54:50 PM  10/23/2020  12 PM - 3 PM  10/23/2020  BEN 
PLM - Rough/Topout  10/22/2020 3:55:39 PM  10/23/2020  12 PM - 3 PM  10/23/2020  BEN 
BLD - Reinforcing Insp  10/22/2020 3:57:41 PM  10/23/2020  12 PM - 3 PM  10/23/2020  BEN 
BLD -Floor Joists/Girders Insp  10/23/2020 1:38:23 PM  10/26/2020  8 AM - 12 PM  10/26/2020  PJJ 
BLD - Pre-Slab Insp  10/26/2020 3:23:45 PM  10/27/2020  8 AM - 12 PM  10/27/2020  BEN 
BLD - Framing Insp.  10/26/2020 3:25:08 PM  10/27/2020  8 AM - 12 PM  10/27/2020  BEN 
BLD - Pre-Grout Insp  10/26/2020 4:08:13 PM  10/27/2020  8 AM - 12 PM  10/27/2020  BEN 
ELE - Ground Electrode/UFER  10/26/2020 4:09:46 PM  10/27/2020  8 AM - 12 PM  10/27/2020  BEN 
BLD - Pre-Slab Insp  10/27/2020 2:52:43 PM  10/28/2020  8 AM - 12 PM  10/28/2020  BEN 
BLD - Reinforcing Insp  10/30/2020 1:51:57 PM  11/2/2020  8 AM - 12 PM  11/2/2020  PJJ 
BLD - Reinforcing Insp  11/2/2020 2:20:03 PM  11/3/2020  8 AM - 12 PM  11/3/2020  PJJ 
BLD - Pre-Slab Insp  11/6/2020 1:51:33 PM  11/9/2020  8 AM - 12 PM  11/9/2020  PJJ 
BLD - Pre-Slab Insp  11/13/2020 11:59:51 AM  11/16/2020  8 AM - 12 PM  11/16/2020  PJJ 
BLD - Footings Insp  11/16/2020 2:01:30 PM  11/17/2020  8 AM - 12 PM  11/17/2020  BEN 
BLD - Framing Insp.  11/16/2020 2:02:28 PM  11/17/2020  8 AM - 12 PM  11/17/2020  BEN 
BLD - Framing Insp.  11/19/2020 4:36:15 PM  11/20/2020  8 AM - 12 PM  11/20/2020  BEN 
BLD - Reinforcing Insp  11/24/2020 3:55:46 PM  11/25/2020  10 AM - 2 PM  11/25/2020  BEN 
BLD - Pre-Slab Insp  11/24/2020 3:56:29 PM  11/25/2020  10 AM - 2 PM  11/25/2020  BEN 
BLD - Pre-Slab Insp  11/30/2020 2:14:12 PM  12/1/2020  12 PM - 3 PM  12/1/2020  BEN 
BLD - Reinforcing Insp  11/30/2020 2:15:05 PM  12/1/2020  12 PM - 3 PM  12/1/2020  BEN 
BLD - Reinforcing Insp  12/2/2020 3:43:01 PM  12/3/2020  10 AM - 2 PM  12/3/2020  BEN 
BLD - Pre-Slab Insp  12/3/2020 3:06:51 PM  12/4/2020  8 AM - 12 PM  12/4/2020  BEN 
BLD - Pre-Slab Insp  12/7/2020 11:21:37 AM  12/8/2020  8 AM - 12 PM  12/8/2020  PJJ 
BLD - Reinforcing Insp  12/7/2020 2:52:00 PM  12/8/2020  8 AM - 12 PM  12/8/2020  PJJ 
BLD - Framing Insp.  12/10/2020 3:43:33 PM  12/11/2020  8 AM - 12 PM  12/11/2020  BEN 
BLD - Pre-Grout Insp  12/10/2020 3:44:06 PM  12/11/2020  8 AM - 12 PM  12/11/2020  BEN 
BLD - Framing Insp.  12/11/2020 3:09:21 PM  12/14/2020  8 AM - 12 PM  12/14/2020  KLA 
BLD - Framing Insp.  12/15/2020 4:02:37 PM  12/17/2020  10 AM - 2 PM  12/17/2020  BEN 
BLD - Reinforcing Insp  12/16/2020 4:14:14 PM  12/17/2020  10 AM - 2 PM  12/17/2020  BEN 
BLD - Pre-Slab Insp  12/16/2020 4:15:34 PM  12/18/2020  8 AM - 12 PM  12/18/2020  BEN 
BLD - Framing Insp.  12/17/2020 12:38:42 PM  12/18/2020  8 AM - 12 PM  12/18/2020  BEN 
BLD - Pre-Slab Insp  12/18/2020 9:57:30 AM  12/21/2020  8 AM - 12 PM  12/21/2020  PJJ 
BLD - Framing Insp.  12/18/2020 9:58:50 AM  12/21/2020  8 AM - 12 PM  12/21/2020  PJJ 
BLD - Reinforcing Insp  12/21/2020 3:21:31 PM  12/22/2020  8 AM - 12 PM  12/22/2020  BEN 
BLD - Pre-Slab Insp  12/21/2020 3:22:54 PM  12/22/2020  8 AM - 12 PM  12/22/2020  BEN 
BLD - Framing Insp.  12/22/2020 3:54:48 PM  12/23/2020  8 AM - 12 PM  12/23/2020  BEN 
BLD - Framing Insp.  12/29/2020 3:13:17 PM  12/30/2020  8 AM - 12 PM  12/30/2020  BEN 
BLD - Drywall Inspection  12/30/2020 3:47:37 PM  12/31/2020  8 AM - 12 PM  12/31/2020  NA  MMO 
BLD - Drywall Inspection  12/31/2020  1/5/2021  8 AM - 12 PM  1/5/2021  PJJ 
BLD - Pre-Slab Insp  1/5/2021 2:53:31 PM  1/6/2021  10 AM - 2 PM  1/6/2021  PJJ 
BLD - Reinforcing Insp  1/5/2021 2:54:08 PM  1/6/2021  10 AM - 2 PM  1/6/2021  PJJ 
BLD - Insulation Insp  1/6/2021 3:35:00 PM  1/7/2021  10 AM - 2 PM  1/7/2021  PJJ 
BLD - Insulation Insp  1/6/2021 3:35:25 PM  1/8/2021  10 AM - 2 PM  1/8/2021  PJJ 
BLD - Pre-Slab Insp  1/6/2021 3:36:55 PM  1/8/2021  10 AM - 2 PM  1/8/2021  PJJ 
BLD - Framing Insp.  1/8/2021 11:24:11 AM  1/11/2021  8 AM - 12 PM  1/11/2021  PJJ 
BLD - Reinforcing Insp  1/8/2021 11:26:08 AM  1/11/2021  8 AM - 12 PM  1/11/2021  PJJ 
BLD - Framing Insp.  1/13/2021 4:01:26 PM  1/14/2021  8 AM - 12 PM  1/14/2021  BEN 
BLD - Insulation Insp  1/13/2021 4:01:58 PM  1/14/2021  8 AM - 12 PM  1/14/2021  BEN 
BLD - Framing Insp.  1/14/2021 4:00:36 PM  1/15/2021  10 AM - 2 PM  1/15/2021  BEN 
BLD - Reinforcing Insp  1/14/2021 4:01:32 PM  1/15/2021  10 AM - 2 PM  1/15/2021  BEN 
Route to Struct/Architectual  1/26/2021  2/11/2021    2/10/2021  APPR  ITW 
Apprv. by Struct/Architectural  1/26/2021      2/10/2021 3:23:01 PM  APPR  ITW 
BLD - Reinforcing Insp  3/1/2021 3:26:56 PM  3/2/2021  8 AM - 12 PM  3/2/2021  BEN 
BLD - Reinforcing Insp  3/2/2021 3:22:39 PM  3/3/2021  8 AM - 12 PM  3/3/2021  PJJ 
BLD - Underfloor Insulation   3/8/2021 4:02:54 PM  3/9/2021  8 AM - 12 PM  3/9/2021  PJJ 
BLD - Framing Insp.  3/8/2021 4:04:03 PM  3/9/2021  8 AM - 12 PM  3/9/2021  PJJ 
ELE - Underground conduit  3/10/2021 4:07:22 PM  3/11/2021  8 AM - 12 PM  3/11/2021  BEN 
BLD - Drywall Inspection  3/10/2021 4:08:13 PM  3/11/2021  8 AM - 12 PM  3/11/2021  BEN 
BLD - Framing Insp.  3/10/2021 4:09:23 PM  3/11/2021  8 AM - 12 PM  3/11/2021  BEN 
BLD - Pre-Slab Insp  3/10/2021 4:10:25 PM  3/11/2021  8 AM - 12 PM  3/11/2021  BEN 
BLD - Drywall Inspection  4/12/2021 4:17:13 PM  4/13/2021  8 AM - 12 PM  4/13/2021  BEN 
BLD - Framing Insp.  4/13/2021 3:47:47 PM  4/14/2021  8 AM - 12 PM  4/14/2021  BEN 
BLD - Misc. Inspection  6/1/2021  6/2/2021    6/2/2021  MMO 
PLM - Ground/Underfloor water  6/16/2021 4:06:29 PM  6/17/2021  8 AM - 12 PM  6/17/2021  BEN 
ELE - Underground conduit  6/16/2021 4:07:15 PM  6/17/2021  8 AM - 12 PM  6/17/2021  BEN 
BLD - Drywall Inspection  6/18/2021 3:43:28 PM  6/21/2021  10 AM - 2 PM  6/21/2021  PJJ 
BLD - Insulation Insp  6/18/2021 3:46:04 PM  6/21/2021  10 AM - 2 PM  6/21/2021  PJJ 
BLD - Framing Insp.  6/18/2021 3:46:48 PM  6/21/2021  10 AM - 2 PM  6/21/2021  PJJ 
ELE - Rough Electrical  6/18/2021 3:47:21 PM  6/21/2021  10 AM - 2 PM  6/21/2021  PJJ 
PLM - Rough/Topout  6/18/2021 3:47:42 PM  6/21/2021  10 AM - 2 PM  6/21/2021  PJJ 
BLD - Footings Insp  7/12/2021 4:34:54 PM  7/13/2021  8 AM - 12 PM  7/13/2021  BEN 
BLD - Footings Insp  7/27/2021 2:14:05 PM  7/28/2021  8 AM - 12 PM  7/28/2021  BEN 
BLD - Footings Insp  7/28/2021 3:36:01 PM  7/29/2021  8 AM - 12 PM  7/29/2021  BEN 
BLD - Reinforcing Insp  8/3/2021 4:08:01 PM  8/4/2021  8 AM - 12 PM  8/4/2021  BEN 
BLD - Reinforcing Insp  8/4/2021 3:54:24 PM  8/5/2021  8 AM - 12 PM  8/5/2021  BEN 
BLD - Footings Insp  8/4/2021 3:54:44 PM  8/5/2021  8 AM - 12 PM  8/5/2021  BEN 
ELE - Electrical Service/Meter  8/16/2021 3:09:26 PM  8/17/2021  8 AM - 12 PM  8/17/2021  BEN 
ELE - Electrical Service/Meter  8/17/2021 4:28:49 PM  8/18/2021  8 AM - 12 PM  8/18/2021  BEN 
BLD - Footings Insp  8/19/2021 2:14:53 PM  8/20/2021  12 PM - 3 PM  8/20/2021  BCJ 
BLD - Footings Insp  8/30/2021 2:58:21 PM  8/31/2021  8 AM - 12 PM  8/31/2021  BEN 
BLD - Footings Insp  8/31/2021 3:00:27 PM  9/1/2021  8 AM - 12 PM  9/1/2021  BEN 
BLD - Footings Insp  8/31/2021  9/1/2021    9/1/2021  BEN 
BLD - Reinforcing Insp  8/31/2021  9/1/2021    9/1/2021  BEN 
BLD - Reinforcing Insp  9/27/2021 3:37:07 PM  9/28/2021  8 AM - 12 PM  9/28/2021  GCT 
BLD - Reinforcing Insp  10/1/2021 4:17:22 PM  10/4/2021  8 AM - 12 PM  10/4/2021  GCT 
BLD - Reinforcing Insp  10/4/2021 3:55:32 PM  10/5/2021  10 AM - 2 PM  10/5/2021  BCJ 
BLD - Framing Insp.  10/5/2021 4:21:54 PM  10/6/2021  12 PM - 3 PM  10/6/2021  BCJ 
BLD - Pre-Grout Insp  10/6/2021 4:23:57 PM  10/7/2021  12 PM - 3 PM  10/7/2021  BCJ 
BLD - Pre-Slab Insp  10/7/2021 3:53:37 PM  10/8/2021  10 AM - 2 PM  10/8/2021  BCJ 

 


Back to Search