Permit Number:  BLD2019-02251     Status:   Finaled     Map Info:   1515 S MANCHESTER AVE
Name:  INTERNATIONAL LINE BUILDERS INC
Address: 1515 S MANCHESTER
Received Date: 05/17/2019 
Parcel: 08221101 
Plan Check Date:  
Issue Date: 05/17/2019 
Expiration Date: 11/17/2020 
Finaled Date: 10/06/2020 
Description: Electrical to support Sybron - Sybron Parking Lot - Site Development of parking lot equipment. REF: BLD2019-01845 

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
ELE - Underground conduit  5/17/2019 2:58:00 PM  5/20/2019    5/20/2019  RML 
ELE - Underground conduit  5/20/2019 1:50:21 PM  5/21/2019    5/21/2019  BEN 
ELE - Underground conduit  5/21/2019 2:58:49 PM  5/23/2019    5/23/2019  BEN 
ELE - Underground conduit  5/22/2019 3:27:50 PM  5/24/2019  12 PM - 3 PM  5/24/2019  BEN 
ELE - Ground Electrode/UFER  5/23/2019 6:40:29 PM  5/24/2019  12 PM - 3 PM  5/24/2019  BEN 
ELE - Underground conduit  5/25/2019 5:02:38 PM  5/28/2019  8 AM - 12 PM  5/28/2019  PJJ 
ELE - Underground conduit  5/25/2019 5:02:56 PM  5/29/2019    5/29/2019  BEN 
ELE - Underground conduit  5/29/2019 5:09:24 PM  5/30/2019  8 AM - 12 PM  5/30/2019  BCJ 
ELE - Underground conduit  5/30/2019 4:40:51 PM  5/31/2019    5/31/2019  BEN 
ELE - Ground Electrode/UFER  5/30/2019 4:41:01 PM  5/31/2019    5/31/2019  BEN 
ELE - Underground conduit  5/30/2019 4:41:12 PM  6/3/2019  8 AM - 12 PM  6/3/2019  KLA 
ELE - Underground conduit  6/3/2019 11:23:47 AM  6/4/2019  8 AM - 12 PM  6/4/2019  BEN 
ELE - Underground conduit  6/4/2019 4:46:22 PM  6/5/2019  8 AM - 12 PM  6/5/2019  BEN 
ELE - Underground conduit  6/4/2019 4:46:43 PM  6/6/2019    6/6/2019  BEN 
ELE - Underground conduit  6/4/2019 4:46:59 PM  6/7/2019  8 AM - 12 PM  6/7/2019  BEN 
ELE - Underground conduit  6/7/2019  6/8/2019    6/11/2019  BEN 
ELE - Underground conduit  6/7/2019  6/9/2019    6/11/2019  BEN 
ELE - Underground conduit  6/8/2019 12:56:41 PM  6/10/2019  8 AM - 12 PM  6/10/2019  PJJ 
ELE - Ground Electrode/UFER  6/8/2019 12:56:52 PM  6/10/2019  8 AM - 12 PM  6/10/2019  PJJ 
ELE - Underground conduit  6/8/2019 12:57:04 PM  6/11/2019  12 PM - 3 PM  6/11/2019  BEN 
ELE - Underground conduit  6/10/2019  6/11/2019    6/11/2019  PJJ 
ELE - Underground conduit  6/12/2019 9:31:03 AM  6/13/2019  10 AM - 2 PM  6/13/2019  BEN 
ELE - Ground Electrode/UFER  6/12/2019 9:31:18 AM  6/13/2019  10 AM - 2 PM  6/13/2019  BEN 
ELE - Underground conduit  6/12/2019 9:31:37 AM  6/14/2019  10 AM - 2 PM  6/14/2019  BEN 
ELE - Underground conduit  6/12/2019 9:32:19 AM  6/17/2019  8 AM - 12 PM  6/17/2019  PJJ 
ELE - Ground Electrode/UFER  6/16/2019 5:05:04 PM  6/17/2019  8 AM - 12 PM  6/17/2019  PJJ 
ELE - Electrical Service/Meter  6/16/2019 5:05:38 PM  6/17/2019  8 AM - 12 PM  6/17/2019  PJJ 
ELE - Underground conduit  6/17/2019 1:29:45 PM  6/18/2019  12 PM - 3 PM  6/18/2019  BEN 
ELE - Electrical Service/Meter  6/17/2019 8:47:06 PM  6/18/2019  12 PM - 3 PM  6/18/2019  BEN 
ELE - Underground conduit  6/19/2019 7:12:43 AM  6/20/2019    6/20/2019  BEN 
ELE - Underground conduit  6/19/2019 7:12:54 AM  6/21/2019  10 AM - 2 PM  6/21/2019  BEN 
ELE - Electrical Service/Meter  6/19/2019 7:13:12 AM  6/20/2019    6/20/2019  BEN 
ELE - Electrical Service/Meter  6/20/2019 4:43:19 PM  6/21/2019  10 AM - 2 PM  6/21/2019  BEN 
ELE - Electrical Service/Meter  6/21/2019 1:33:14 PM  6/24/2019  8 AM - 12 PM  6/24/2019  JFR 
ELE - Rough Electrical  6/21/2019 1:33:59 PM  6/24/2019  8 AM - 12 PM  6/24/2019  JFR 
ELE - Underground conduit  6/23/2019 1:29:06 PM  6/24/2019  8 AM - 12 PM  6/24/2019  JFR 
ELE - Electrical Service/Meter  6/24/2019 3:04:03 PM  6/25/2019  8 AM - 12 PM  6/25/2019  JFR 
ELE - Underground conduit  6/24/2019 3:04:16 PM  6/25/2019  8 AM - 12 PM  6/25/2019  JFR 
ELE - Electrical Service/Meter  6/27/2019 8:43:33 AM  6/28/2019  8 AM - 12 PM  6/28/2019  BEN 
ELE - Rough Electrical  9/17/2019 4:05:24 PM  9/18/2019  8 AM - 12 PM  9/18/2019  BEN 
Electrical Final Insp Request  9/17/2019 4:05:41 PM  9/18/2019  8 AM - 12 PM  9/18/2019  BEN 
ELE - Rough Electrical  9/18/2019 2:52:04 PM  9/19/2019    9/18/2019  MSM 
Electrical Final Insp Request  9/18/2019 2:52:22 PM  9/19/2019    9/18/2019  MSM 
ELE - Rough Electrical  9/18/2019  9/19/2019    9/19/2019  BEN 
Electrical Final Insp Request  9/18/2019  9/19/2019    9/19/2019  BEN 
Electrical Final Insp Request  9/25/2019 4:56:47 PM  9/26/2019  8 AM - 12 PM  9/26/2019  BEN 
Electrical Final Insp Request  9/26/2019 5:29:25 PM  9/27/2019  8 AM - 12 PM  9/27/2019  BEN 
Electrical Final Insp Request  9/29/2020  10/2/2020    9/29/2020  GGO 
Electrical Final Insp Request  10/5/2020 11:01:36 AM  10/6/2020  10 AM - 2 PM  10/6/2020  BEN 
Electrical Final        10/6/2020    BEN 

 