Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
MEC - Rough Duct  |
5/30/2019 1:53:37 PM  |
5/31/2019  |
8 AM - 12 PM  |
5/31/2019  |
P  |
BEN  |
MEC - Rough Duct  |
6/25/2019 5:32:27 AM  |
6/26/2019  |
8 AM - 12 PM  |
6/26/2019  |
P  |
BEN  |
MEC - Rough Duct  |
7/23/2019 4:00:58 PM  |
7/24/2019  |
8 AM - 12 PM  |
7/24/2019  |
P  |
BEN  |
MEC - Rough Mechanical  |
7/23/2019 4:01:18 PM  |
7/24/2019  |
8 AM - 12 PM  |
7/24/2019  |
P  |
BEN  |
MEC - Rough Mechanical  |
7/25/2019  |
7/26/2019  |
10 AM - 2 PM  |
7/26/2019  |
P  |
BEN  |
MEC - Rough Mechanical  |
7/25/2019  |
7/26/2019  |
10 AM - 2 PM  |
7/26/2019  |
P  |
BEN  |
MEC - Rough Duct  |
7/31/2019 11:17:21 AM  |
8/1/2019  |
  |
8/1/2019  |
A  |
BEN  |
Mechanical Final Insp Request  |
2/6/2020 5:20:28 PM  |
2/7/2020  |
8 AM - 12 PM  |
2/7/2020  |
A  |
BEN  |
Mechanical Final  |
  |
  |
  |
2/7/2020  |
  |
BEN  |