Home Status Help

View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2019-01845     Status:   Finaled     Map Info:   1515 S MANCHESTER AVE
Name:  36/38/40 WEST 66 REALTY COMPANY
Address: 1515 S MANCHESTER
Received Date: 04/30/2019 
Parcel: 08221101 
Plan Check Date:  
Issue Date: 05/15/2019 
Expiration Date: 11/15/2020 
Finaled Date: 10/06/2020 
Description: Sybron - Sybron Parking Lot - Site Development: Install (51) light poles, (8) EV chargers, (1) motorized gate arm, (2) card readers, (1) 2500 amp switchboard, (14) 100 and 200 amp panels and 135 ln ft x 7 ft high fence with swing gate.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Struct/Architectual  4/30/2019  5/14/2019    5/9/2019  CORR  ITW 
Apprv. by Struct/Architectural  4/30/2019      5/15/2019 11:15:40 AM  APPR  WCL 
Route to Planning Zoning  4/30/2019  5/14/2019    5/10/2019  APPR  EYT 
Approved by Planning Zoning  4/30/2019      5/13/2019 1:44:11 PM  APPR  EYT 
Approved by Addressing  4/30/2019      5/3/2019 7:12:52 AM  APPR  HXN 
Route to Addressing  4/30/2019  5/14/2019    5/3/2019  APPR  HXN 
Approved by Bus Lic (Sub List)  4/30/2019  6/4/2019    6/5/2019  APPR  RHZ 
Route to C&D Waste Mgmt  4/30/2019  5/14/2019    5/7/2019  APPR  OXM 
Approved by C&D Waste Mgmt  4/30/2019      5/7/2019  APPR  OXM 
Approved by Electrical  4/30/2019      5/7/2019 11:01:23 AM  APPR  MCS 
Route to Electrical  4/30/2019  5/14/2019    5/7/2019  APPR  MCS 
Approved by Elec Engineering  4/30/2019      5/8/2019 2:31:12 PM  APPR  CMK 
Route to Elec Engineering  4/30/2019  5/14/2019    5/8/2019  APPR  CMK 
Approved by Fire Department  4/30/2019      5/8/2019 2:57:56 PM  APPR  EPO 
Route to Fire Department  4/30/2019  5/14/2019    5/8/2019  APPR  EPO 
Apprv. by PW Develop. Services  4/30/2019      5/8/2019 1:24:39 PM  APPR  SXA 
Route to PW Develop. Services  4/30/2019  5/14/2019    5/8/2019  APPR  SXA 
Approved by Traffic Eng.  4/30/2019      5/15/2019 11:01:49 AM  APPR  RXC 
Route to Traffic Engineering  4/30/2019  5/14/2019    5/9/2019  CORR  RXC 
Approved by Water Engineering  4/30/2019      5/8/2019 5:03:50 PM  APPR  DRS 
Route to Water Engineering  4/30/2019  5/14/2019    5/8/2019  APPR  DRS 
Approved Alternate MatL/Method  5/1/2019      5/1/2019  DONE  AJP2 
Route To Alternate MatL/Method        5/1/2019  APPR  AJP2 
Route to Struct/Architectual  5/15/2019  5/29/2019    5/15/2019  APPR  WCL 
Route to Traffic Engineering  5/15/2019  5/29/2019    5/15/2019  APPR  RXC 
BLD - Reinforcing Insp  5/21/2019 2:16:00 PM  5/22/2019    5/22/2019  BEN 
BLD - Reinforcing Insp  5/22/2019 3:39:04 PM  5/23/2019    5/23/2019  BEN 
BLD - Reinforcing Insp  5/23/2019 4:42:17 PM  5/24/2019  12 PM - 3 PM  5/24/2019  BEN 
BLD - Reinforcing Insp  5/25/2019 1:06:20 PM  5/28/2019  8 AM - 12 PM  5/28/2019  PJJ 
BLD - Reinforcing Insp  5/25/2019 1:06:50 PM  5/29/2019    5/29/2019  BEN 
BLD - Reinforcing Insp  5/25/2019 1:07:13 PM  5/30/2019  8 AM - 12 PM  5/30/2019  BCJ 
BLD - Reinforcing Insp  5/25/2019 1:07:30 PM  5/31/2019    5/31/2019  BEN 
Route Revision Electrical  6/3/2019  6/17/2019    6/11/2019  APPR  MCS 
Approved Revision Electrical        6/11/2019  DONE  MCS 
Approved Revision Structural  6/3/2019      6/5/2019  DONE  ITW 
Route Revision Structural  6/3/2019  6/17/2019    6/5/2019  APPR  ITW 
BLD - Reinforcing Insp  6/16/2019 3:35:54 PM  6/17/2019  8 AM - 12 PM  6/17/2019  PJJ 
BLD - Reinforcing Insp  6/21/2019  6/22/2019    6/26/2019  BEN 
BLD - Misc. Inspection  6/21/2019  6/24/2019  8 AM - 12 PM  6/24/2019  JFR 
BLD - Reinforcing Insp  6/24/2019 1:53:33 PM  6/25/2019  8 AM - 12 PM  6/25/2019  JFR 
Approved Revision Electrical        7/2/2019  APPR  MCS 
Route Revision Electrical  6/27/2019  7/5/2019    7/2/2019  APPR  MCS 
Approved by Fire Department  6/27/2019      8/20/2019 10:53:47 AM  APPR  EPO 
Route to Fire Department  6/27/2019  7/5/2019    7/5/2019  APPR  EPO 
Approved by Planning Zoning  6/27/2019      7/5/2019 4:26:25 PM  APPR  EYT 
Route to Planning Zoning  6/27/2019  7/5/2019    7/5/2019  APPR  EYT 
Apprv. by PW Develop. Services  6/27/2019      7/8/2019 11:36:22 AM  APPR  SXA 
Route to PW Develop. Services  6/27/2019  7/5/2019    7/8/2019  APPR  SXA 
Approved Revision Structural  6/27/2019      7/5/2019  APPR   
Route Revision Structural  6/27/2019  7/5/2019    7/8/2019  APPR  ITW 
Approved by Traffic Eng.  6/27/2019      7/15/2019 9:36:30 AM  APPR  RXC 
Route to Traffic Engineering  6/27/2019  7/5/2019    7/15/2019  APPR  RXC 
Inspection by Fire Department  7/5/2019  7/19/2019    8/3/2020  DONE  638 
BLD - Reinforcing Insp  7/16/2019 3:53:40 PM  7/18/2019  10 AM - 2 PM  7/18/2019  BEN 
BLD - Pre-Slab Insp  9/16/2019 3:15:23 PM  9/17/2019  10 AM - 2 PM  9/17/2019  BEN 
BLD - Pre-Slab Insp  9/17/2019 5:04:12 PM  9/18/2019  8 AM - 12 PM  9/18/2019  BEN 
BLD - Misc. Inspection  9/18/2019  9/19/2019    9/19/2019  BEN 
Building Final Insp Request  8/5/2020  8/6/2020  8 AM - 12 PM  8/6/2020  BCJ 
Building Final Insp Request  8/6/2020  8/11/2020  10 AM - 2 PM  8/11/2020  BEN 
Building Final Insp Request  8/17/2020  8/19/2020  8 AM - 12 PM  8/19/2020  BEN 
Building Final Insp Request  9/29/2020  10/2/2020    9/29/2020  GGO 
Building Final Insp Request  10/5/2020 11:00:43 AM  10/6/2020  10 AM - 2 PM  10/6/2020  BEN 
Building Final        10/6/2020    BEN 

 