Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Struct/Architectual  |
4/11/2019  |
4/25/2019  |
  |
4/23/2019  |
APPR  |
CSG  |
Apprv. by Struct/Architectural  |
4/11/2019  |
  |
  |
4/23/2019 12:58:27 PM  |
APPR  |
CSG  |
Approved by Addressing  |
4/11/2019  |
  |
  |
4/12/2019 8:05:22 AM  |
APPR  |
HXN  |
Route to Addressing  |
4/11/2019  |
4/25/2019  |
  |
4/12/2019  |
APPR  |
HXN  |
Approved by Elec Engineering  |
4/11/2019  |
  |
  |
4/23/2019 9:59:50 AM  |
APPR  |
JJB  |
Route to Elec Engineering  |
4/11/2019  |
4/25/2019  |
  |
4/23/2019  |
APPR  |
JJB  |
Route to Fire Department  |
4/11/2019  |
4/25/2019  |
  |
4/25/2019  |
CORR  |
EPO  |
Approved by Fire Department  |
4/11/2019  |
  |
  |
5/3/2019 2:59:48 PM  |
APPR  |
EPO  |
Approved by Planning Zoning  |
4/11/2019  |
  |
  |
4/23/2019 3:03:19 PM  |
APPR  |
EYT  |
Route to Planning Zoning  |
4/11/2019  |
4/25/2019  |
  |
4/23/2019  |
APPR  |
EYT  |
Apprv. by PW Develop. Services  |
4/11/2019  |
  |
  |
4/23/2019 12:00:38 PM  |
NR  |
SXA  |
Route to PW Develop. Services  |
4/11/2019  |
4/25/2019  |
  |
4/23/2019  |
NR  |
SXA  |
Approved by Traffic Eng.  |
4/11/2019  |
  |
  |
4/22/2019 6:19:57 PM  |
APPR  |
RXC  |
Route to Traffic Engineering  |
4/11/2019  |
4/25/2019  |
  |
4/22/2019  |
APPR  |
RXC  |
Approved by Electrical  |
4/11/2019  |
  |
  |
5/1/2019 9:05:39 AM  |
APPR  |
MCS  |
Route to Electrical  |
4/11/2019  |
4/25/2019  |
  |
4/23/2019  |
CORR  |
MCS  |
Approved By Utilities -Telecom  |
4/11/2019  |
  |
  |
4/19/2019  |
NR  |
JXP2  |
Route To Utilities - Telecom  |
4/11/2019  |
4/25/2019  |
  |
4/19/2019  |
NR  |
JXP2  |
Approved by C&D Waste Mgmt  |
4/11/2019  |
  |
  |
4/15/2019  |
DONE  |
EYK  |
Route to C&D Waste Mgmt  |
4/11/2019  |
4/25/2019  |
  |
4/15/2019  |
APPR  |
EYK  |
Inspection by Fire Department  |
4/25/2019  |
5/9/2019  |
  |
5/9/2019  |
DONE  |
638  |
Route to Electrical  |
4/26/2019  |
5/3/2019  |
  |
5/1/2019  |
APPR  |
MCS  |
Route to Fire Department  |
4/26/2019  |
5/3/2019  |
  |
5/3/2019  |
APPR  |
EPO  |
Inspection by Fire Department  |
5/3/2019  |
5/17/2019  |
  |
5/9/2019  |
DONE  |
638  |
Building Final Insp Request  |
5/9/2019 1:10:25 PM  |
5/10/2019  |
8 AM - 12 PM  |
5/10/2019  |
N  |
BEN  |
Building Final Insp Request  |
5/16/2019 3:51:00 PM  |
5/17/2019  |
8 AM - 12 PM  |
5/17/2019  |
A  |
BEN  |
Building Final  |
  |
  |
  |
5/17/2019  |
  |
BEN  |