Type  |
Requested  |
Scheduled  |
Time of Inspection  |
Completed  |
Disposition  |
Employee  |
Route to Traffic Engineering  |
12/20/2018  |
1/9/2019  |
  |
1/11/2019  |
APPR  |
RXC  |
Approved by Traffic Eng.  |
12/20/2018  |
  |
  |
1/11/2019 9:49:17 AM  |
APPR  |
RXC  |
Route to PW Develop. Services  |
12/20/2018  |
1/9/2019  |
  |
1/14/2019  |
CORR  |
SXA  |
Apprv. by PW Develop. Services  |
12/20/2018  |
  |
  |
6/10/2019 3:07:08 PM  |
APPR  |
SXA  |
Route to PW Operations  |
12/20/2018  |
1/9/2019  |
  |
12/21/2018  |
APPR  |
LMM  |
Approved by PW Operations  |
12/20/2018  |
  |
  |
12/21/2018 11:22:32 AM  |
APPR  |
LMM  |
Route to Fire Department  |
12/20/2018  |
1/9/2019  |
  |
1/8/2019  |
CORR  |
EPO  |
Approved by Fire Department  |
12/20/2018  |
  |
  |
3/22/2019 10:29:39 AM  |
APPR  |
472  |
Route to Elec Engineering  |
12/20/2018  |
1/9/2019  |
  |
1/9/2019  |
CORR  |
JJB  |
Approved by Elec Engineering  |
12/20/2018  |
  |
  |
3/28/2019 11:43:31 AM  |
APPR  |
JJB  |
Route to Struct/Architectual  |
12/20/2018  |
1/9/2019  |
  |
1/8/2019  |
CORR  |
ZID  |
Apprv. by Struct/Architectural  |
12/20/2018  |
  |
  |
5/9/2019 4:31:44 PM  |
APPR  |
ZID  |
Route to Planning Zoning  |
12/20/2018  |
1/9/2019  |
  |
1/11/2019  |
CORR  |
JFM  |
Approved by Planning Zoning  |
12/20/2018  |
  |
  |
5/9/2019 2:27:29 PM  |
APPR  |
EYT  |
Approved by Water Engineering  |
12/20/2018  |
  |
  |
1/7/2019 8:41:37 AM  |
APPR  |
DRS  |
Route to Electrical  |
12/20/2018  |
1/9/2019  |
  |
1/8/2019  |
APPR  |
MCS  |
Approved by Electrical  |
12/20/2018  |
  |
  |
1/8/2019 8:20:01 AM  |
APPR  |
MCS  |
Approved by Addressing  |
12/20/2018  |
  |
  |
12/21/2018 8:45:22 AM  |
APPR  |
HXN  |
Route to Addressing  |
12/20/2018  |
1/9/2019  |
  |
12/21/2018  |
APPR  |
HXN  |
Approved: School Fees Due  |
12/20/2018  |
  |
  |
6/11/2019  |
APPR  |
AEG  |
Route to Water Engineering  |
12/20/2018  |
1/9/2019  |
  |
1/7/2019  |
APPR  |
DRS  |
Route to Mechanical  |
12/20/2018  |
1/9/2019  |
  |
1/9/2019  |
APPR  |
GAQ  |
Approved by Mechanical  |
12/20/2018  |
  |
  |
1/9/2019  |
APPR  |
GAQ  |
Route to Plumbing  |
12/20/2018  |
1/9/2019  |
  |
1/9/2019  |
APPR  |
GAQ  |
Approved by Plumbing  |
12/20/2018  |
  |
  |
1/9/2019  |
APPR  |
GAQ  |
Route to Elec Engineering  |
3/11/2019  |
3/28/2019  |
  |
3/14/2019  |
APPR  |
JJB  |
Route to Fire Department  |
3/11/2019  |
3/19/2019  |
  |
3/22/2019  |
APPR  |
472  |
Route to Planning Zoning  |
3/11/2019  |
3/19/2019  |
  |
3/28/2019  |
APPR  |
EYT  |
Route to PW Develop. Services  |
3/11/2019  |
3/19/2019  |
  |
3/19/2019  |
CORR  |
SXA  |
Route to Struct/Architectual  |
3/11/2019  |
3/19/2019  |
  |
3/13/2019  |
CORR  |
ZID  |
Route to PW Develop. Services  |
5/9/2019  |
5/28/2019  |
  |
5/28/2019  |
APPR  |
SXA  |
Route to Struct/Architectual  |
5/9/2019  |
5/27/2019  |
  |
5/9/2019  |
APPR  |
ZID  |
Approved by Bus Lic (Sub List)  |
6/11/2019  |
9/26/2019  |
  |
10/7/2019  |
APPR  |
TFG  |
Approved Revision Electrical  |
  |
  |
  |
6/27/2019  |
DONE  |
MCS  |
Route Revision Electrical  |
6/17/2019  |
6/25/2019  |
  |
6/20/2019  |
APPR  |
MCS  |
Approved by Fire Department  |
6/17/2019  |
  |
  |
6/20/2019 3:02:51 PM  |
APPR  |
EPO  |
Route to Fire Department  |
6/17/2019  |
6/25/2019  |
  |
6/20/2019  |
APPR  |
EPO  |
Approved Revision Mechanical  |
  |
  |
  |
6/27/2019  |
DONE  |
ITW  |
Route Revision Mechanical  |
6/17/2019  |
6/25/2019  |
  |
6/24/2019  |
APPR  |
ITW  |
Approved Revision Plumbing  |
  |
  |
  |
6/27/2019  |
DONE  |
ITW  |
Route Revision Plumbing  |
6/17/2019  |
6/25/2019  |
  |
6/24/2019  |
APPR  |
ITW  |
Approved Revision Structural  |
6/17/2019  |
  |
  |
7/31/2019  |
DONE  |
ZID  |
Route Revision Structural  |
6/17/2019  |
6/25/2019  |
  |
6/19/2019  |
CORR  |
ZID  |
Route to Planning Zoning  |
6/17/2019  |
6/25/2019  |
  |
6/26/2019  |
APPR  |
EYT  |
Approved by Planning Zoning  |
6/17/2019  |
  |
  |
6/26/2019 9:18:38 AM  |
APPR  |
EYT  |
Inspection by Fire Department  |
6/20/2019  |
7/9/2019  |
  |
10/18/2019  |
DONE  |
638  |
Route Revision Structural  |
7/15/2019  |
7/31/2019  |
  |
7/23/2019  |
APPR  |
ZID  |
BLD - Reinforcing Insp  |
7/19/2019 2:14:18 PM  |
7/22/2019  |
8 AM - 12 PM  |
7/22/2019  |
C  |
PJJ  |
BLD - Reinforcing Insp  |
7/22/2019 2:32:39 PM  |
7/23/2019  |
  |
7/23/2019  |
N  |
BEN  |
BLD - Reinforcing Insp  |
7/23/2019 9:41:09 PM  |
7/24/2019  |
10 AM - 2 PM  |
7/24/2019  |
A  |
BEN  |
BLD - Framing Insp.  |
8/1/2019 4:18:37 PM  |
8/2/2019  |
10 AM - 2 PM  |
8/2/2019  |
N  |
BEN  |
BLD - Reinforcing Insp  |
8/5/2019 6:01:08 AM  |
8/6/2019  |
10 AM - 2 PM  |
8/6/2019  |
N  |
MMO  |
BLD - Reinforcing Insp  |
8/13/2019 4:16:26 PM  |
8/14/2019  |
10 AM - 2 PM  |
8/14/2019  |
C  |
BEN  |
BLD - Roof Sheathing Insp.  |
8/19/2019 11:49:55 AM  |
8/20/2019  |
10 AM - 2 PM  |
8/20/2019  |
N  |
BEN  |
BLD - Framing Insp.  |
8/19/2019 11:51:20 AM  |
8/20/2019  |
10 AM - 2 PM  |
8/20/2019  |
N  |
BEN  |
BLD - 1st Floor Shear Insp  |
8/20/2019 1:26:13 PM  |
8/21/2019  |
10 AM - 2 PM  |
8/21/2019  |
F  |
BEN  |
BLD - Roof Sheathing Insp.  |
8/20/2019 1:28:51 PM  |
8/21/2019  |
10 AM - 2 PM  |
8/21/2019  |
N  |
BEN  |
BLD - Roof Sheathing Insp.  |
8/21/2019 5:47:13 PM  |
8/22/2019  |
10 AM - 2 PM  |
8/22/2019  |
A  |
BEN  |
BLD - 1st Floor Shear Insp  |
8/21/2019 5:47:37 PM  |
8/22/2019  |
10 AM - 2 PM  |
8/22/2019  |
N  |
BEN  |
BLD - 1st Floor Shear Insp  |
8/22/2019 9:59:28 PM  |
8/23/2019  |
8 AM - 12 PM  |
8/23/2019  |
A  |
BEN  |
BLD - 1st Floor Shear Insp  |
8/25/2019 1:42:09 PM  |
8/26/2019  |
8 AM - 12 PM  |
8/26/2019  |
C  |
PJJ  |
BLD - Reinforcing Insp  |
8/29/2019 1:26:50 PM  |
8/30/2019  |
8 AM - 12 PM  |
8/30/2019  |
P  |
BEN  |
BLD - Roof Sheathing Insp.  |
9/4/2019 10:58:17 AM  |
9/5/2019  |
10 AM - 2 PM  |
9/5/2019  |
P  |
BEN  |
BLD - Framing Insp.  |
9/5/2019 4:43:14 PM  |
9/6/2019  |
8 AM - 12 PM  |
9/6/2019  |
A  |
BEN  |
BLD - Roof Sheathing Insp.  |
9/5/2019 4:43:58 PM  |
9/6/2019  |
8 AM - 12 PM  |
9/6/2019  |
A  |
BEN  |
BLD - Insulation Insp  |
9/7/2019 5:24:46 PM  |
9/9/2019  |
8 AM - 12 PM  |
9/9/2019  |
P  |
PJJ  |
BLD - Drywall Inspection  |
9/12/2019 8:59:58 AM  |
9/13/2019  |
10 AM - 2 PM  |
9/13/2019  |
A  |
BEN  |
BLD - T-Bar (Structural) Insp  |
9/26/2019 4:55:51 PM  |
9/27/2019  |
12 PM - 3 PM  |
9/27/2019  |
P  |
BEN  |
BLD - 1st Floor Shear Insp  |
10/4/2019  |
10/5/2019  |
8 AM - 12 PM  |
10/9/2019  |
A  |
BEN  |
BLD - TCO App Consideration  |
10/4/2019  |
10/4/2019  |
  |
10/4/2019  |
A  |
BEN  |
BLD - Misc. Inspection  |
10/4/2019  |
10/9/2019  |
10 AM - 2 PM  |
10/9/2019  |
A  |
BEN  |
BLD - Drywall Inspection  |
10/8/2019 5:27:14 PM  |
10/9/2019  |
10 AM - 2 PM  |
10/9/2019  |
C  |
BEN  |
Building Final Insp Request  |
2/11/2020 6:30:18 AM  |
2/12/2020  |
  |
2/12/2020  |
A  |
BEN  |
Planning GIS - Building Change  |
2/12/2020 4:31:38 PM  |
  |
  |
2/21/2020  |
DONE  |
MAR3  |
Building Final  |
  |
  |
  |
2/12/2020  |
  |
BEN  |