Home Status Help

View Permit Status

The information below summarizes the Permit Number you selected.

Permit Number:  BLD2018-00667     Status:   Finaled     Map Info:   1313 S HARBOR BLVD 2103 (Tropical Hideaway)
Name:  WALT DISNEY WORLD CO
Address: 1313 S HARBOR 2103
Received Date: 02/20/2018 
Parcel: 08219019 
Plan Check Date:  
Issue Date: 06/14/2018 
Expiration Date: 06/14/2019 
Finaled Date: 02/27/2019 
Description: Disney - Adventureland / Tropical Hideaway - Change of Use: 4,315 s.ft new outdoor dining area (from A3 occupancy amphitheater to A2 occ dining area). Repair existing bridge with new wood joists and guardrails. New bridge. (2) New concrete ramp, new stairs. (4) 651 s.ft steel canopies. (14) light poles and (14) tiki torches. New rock work water feature 8' high. 66 ln.ft x 2' high retaining wall. (5) door openings to existing building and 1,111 s.ft themed plaster to Plaza Pavillion.  

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Traffic Engineering  2/20/2018  3/8/2018    2/26/2018  NR  RXC 
Approved by Traffic Eng.  2/20/2018      2/26/2018 3:47:54 PM  NR  RXC 
Route to PW Develop. Services  2/20/2018  3/8/2018    3/5/2018  APPR  SXA 
Apprv. by PW Develop. Services  2/20/2018      3/5/2018 1:27:35 PM  APPR  SXA 
Route to Elec Engineering  2/20/2018  3/8/2018    3/12/2018  APPR  CMK 
Approved by Elec Engineering  2/20/2018      3/12/2018 2:30:25 PM  APPR  CMK 
Route to Struct/Architectual  2/20/2018  3/8/2018    3/6/2018  CORR  BVD 
Apprv. by Struct/Architectural  2/20/2018      5/1/2018 6:03:17 AM  APPR  BVD 
Route to Planning Zoning  2/20/2018  3/8/2018    2/23/2018  APPR  EYT 
Approved by Planning Zoning  2/20/2018      2/23/2018 12:28:44 PM  APPR  EYT 
Route to Water Engineering  2/20/2018  7/2/2018    3/7/2018  APPR  DRS 
Approved by Water Engineering  2/20/2018      3/7/2018 2:04:51 PM  APPR  DRS 
Approved: Health Set Required  2/20/2018      6/11/2018  APPR  CMN 
Approved by Bus Lic (Sub List)  2/20/2018  11/15/2018    12/18/2018  APPR  CSL 
Approved by Addressing  2/20/2018      2/23/2018 7:58:06 AM  APPR  HXN 
Route to Addressing  2/20/2018  3/8/2018    2/23/2018  APPR  HXN 
Approved by Electrical  2/20/2018      3/6/2018 9:58:21 AM  APPR  MCS 
Route to Electrical  2/20/2018  3/8/2018    3/6/2018  APPR  MCS 
Approved by Fire Department  2/20/2018      3/8/2018 11:03:23 AM  APPR  408 
Route to Fire Department  2/20/2018  3/8/2018    3/8/2018  APPR  408 
Route to Mechanical  2/20/2018  3/8/2018    3/8/2018  APPR  GAQ 
Approved by Plumbing  2/20/2018      3/8/2018  APPR  GAQ 
Route to Plumbing  2/20/2018  3/8/2018    3/8/2018  APPR  GAQ 
Inspection by Fire Department  3/8/2018  3/26/2018    12/7/2018  DONE  MGA 
Route to Struct/Architectual  4/16/2018  5/2/2018    5/1/2018  APPR  BVD 
Approved by Elec Engineering  6/18/2018      6/22/2018 9:33:52 AM  APPR  CMK 
Route to Elec Engineering  6/18/2018  7/5/2018    6/22/2018  APPR  CMK 
Approved Revision Electrical  6/18/2019      7/3/2018  DONE  MCS 
Route Revision Electrical  6/18/2018  7/5/2018    7/3/2018  APPR  MCS 
Approved by Fire Department  6/18/2018      7/10/2018 10:49:17 AM  APPR  408 
Route to Fire Department  6/18/2018  7/5/2018    7/10/2018  APPR  408 
Approved by Planning Zoning  6/18/2018      7/6/2018 10:06:38 AM  APPR  EYT 
Route to Planning Zoning  6/18/2018  7/5/2018    7/6/2018  APPR  EYT 
Approved by Plumbing  6/18/2018      7/5/2018  APPR  GAQ 
Approved Revision Plumbing  6/18/2018      7/5/2018  DONE  GAQ 
Route Revision Plumbing  6/18/2018  7/5/2018    7/5/2018  APPR  GAQ 
Apprv. by PW Develop. Services  6/18/2018      7/6/2018 3:24:10 PM  APPR  SXA 
Route to PW Develop. Services  6/18/2018  7/5/2018    7/6/2018  APPR  SXA 
Approved Revision Structural  6/18/2018      8/16/2018  APPR  BVD 
Route Revision Structural  6/18/2018  7/5/2018    6/26/2018  CORR  BVD 
Approved by Traffic Eng.  6/18/2018      7/3/2018 11:22:59 AM  NR  RXC 
Route to Traffic Engineering  6/18/2018  7/5/2018    7/3/2018  NR  RXC 
Approved by Water Engineering  6/18/2018      7/2/2018 10:50:15 AM  APPR  DRS 
Route to Water Engineering  6/18/2018  7/5/2018    7/2/2018  APPR  DRS 
Approved: Health Set Required  6/18/2018      6/19/2018  NR  CMN 
Approved by Planning Zoning  7/16/2018      7/24/2018 12:14:48 PM  APPR  EYT 
Route to Planning Zoning  7/16/2018  8/1/2018    7/24/2018  APPR  EYT 
Approved Revision Structural  7/16/2018      7/31/2018  DONE  BVD 
Route Revision Structural  7/16/2018  8/1/2018    7/31/2018  CORR  BVD 
Approved Revision Plumbing  7/16/2018      8/1/2018  NR  GAQ 
Route Revision Plumbing  7/16/2018  8/1/2018    8/1/2018  NR  GAQ 
Approved Revision Electrical  7/16/2018      7/31/2018  NR   MCS 
Route Revision Electrical  7/16/2018  8/1/2018    7/31/2018  NR  MCS 
Route Revision Structural  7/23/2018  8/8/2018    7/31/2018  CORR  BVD 
BLD - Reinforcing Insp  7/27/2018 10:14:34 AM  7/30/2018  10 AM - 2 PM  7/30/2018  GCT 
Route Revision Structural  8/6/2018  8/22/2018    8/16/2018  APPR  BVD 
Route Revision Structural  8/6/2018  8/22/2018    8/21/2018  APPR  BVD 
BLD - Reinforcing Insp  8/6/2018 2:00:43 PM  8/7/2018  10 AM - 2 PM  8/7/2018  BEN 
BLD - Reinforcing Insp  8/9/2018 2:46:13 PM  8/13/2018  8 AM - 12 PM  8/13/2018  PJJ 
BLD - Reinforcing Insp  8/24/2018 7:24:57 AM  8/27/2018  8 AM - 12 PM  8/27/2018  NA  GCT 
BLD - Footings Insp  8/27/2018  8/27/2018    8/28/2018  PJJ 
BLD - Reinforcing Insp  8/29/2018 10:10:16 AM  8/30/2018  8 AM - 12 PM  8/30/2018  BEN 
BLD - Reinforcing Insp  8/30/2018 11:10:52 AM  8/31/2018  8 AM - 12 PM  8/31/2018  DOM 
BLD - Footings Insp  8/30/2018  8/30/2018    8/31/2018  JOS 
Approved Revision Structural  9/10/2018      9/25/2018  APPR  BVD 
Route Revision Structural  9/10/2018  9/26/2018    9/25/2018  APPR  BVD 
BLD - Reinforcing Insp  9/12/2018 3:12:57 PM  9/13/2018  10 AM - 2 PM  9/13/2018  BEN 
BLD - Reinforcing Insp  9/19/2018 8:44:51 AM  9/20/2018  10 AM - 2 PM  9/20/2018  BEN 
BLD - Reinforcing Insp  9/21/2018 8:22:01 AM  9/24/2018  10 AM - 2 PM  9/24/2018  DOM 
BLD - Reinforcing Insp  9/26/2018 10:17:55 PM  9/27/2018  10 AM - 2 PM  9/27/2018  BEN 
BLD - Reinforcing Insp  9/27/2018 9:47:29 PM  9/28/2018  10 AM - 2 PM  9/28/2018  BEN 
BLD - Reinforcing Insp  10/1/2018 10:15:04 AM  10/2/2018  10 AM - 2 PM  10/2/2018  GCT 
BLD - Reinforcing Insp  10/7/2018 8:01:12 AM  10/8/2018  8 AM - 12 PM  10/8/2018  PJJ 
BLD - Reinforcing Insp  10/8/2018 8:35:50 AM  10/9/2018  10 AM - 2 PM  10/9/2018  BEN 
BLD - Reinforcing Insp  10/9/2018 1:56:29 PM  10/10/2018  10 AM - 2 PM  10/10/2018  BEN 
Route to Plumbing  10/12/2018  10/30/2018    10/30/2018  CORR  GAQ 
Approved by Plumbing  10/12/2018      11/14/2018 3:20:12 PM  APPR  GAQ 
Route to Struct/Architectual  10/12/2018  10/30/2018    10/25/2018  CORR  BVD 
Apprv. by Struct/Architectural  10/12/2018      11/13/2018 10:55:14 AM  APPR  BVD 
Route to Electrical  10/12/2018  10/30/2018    10/25/2018  NR  MCS 
Approved by Electrical  10/12/2018      10/25/2018 10:11:53 AM  NR  MCS 
BLD - Framing Insp.  10/20/2018 2:41:35 AM  10/22/2018  8 AM - 12 PM  10/22/2018  PJJ 
Approved Revision Structural  10/22/2018      11/6/2018  APPR  BVD 
Route Revision Structural  10/22/2018  11/7/2018    11/6/2018  APPR  BVD 
BLD - Framing Insp.  10/23/2018 8:10:21 AM  10/26/2018  10 AM - 2 PM  10/26/2018  BEN 
Approved Revision Structural  10/23/2018      11/20/2018  DONE  BVD 
Route Revision Structural  10/23/2018  11/8/2018    11/6/2018  CORR  BVD 
BLD - Drywall Inspection  10/26/2018 3:20:27 PM  10/29/2018  8 AM - 12 PM  10/29/2018  PJJ 
BLD - Exterior Lath Insp  10/31/2018 9:03:17 AM  11/1/2018  10 AM - 2 PM  11/1/2018  BEN 
BLD - Roof Sheathing Insp.  11/1/2018 1:30:49 PM  11/2/2018  10 AM - 2 PM  11/2/2018  BEN 
Route to Plumbing  11/2/2018  11/13/2018    11/14/2018  APPR  GAQ 
Route to Struct/Architectual  11/2/2018  11/13/2018    11/13/2018  APPR  BVD 
BLD - Roof Sheathing Insp.  11/4/2018 5:00:31 AM  11/5/2018  10 AM - 2 PM  11/5/2018  PJJ 
Approved Revision Structural  11/6/2018      11/20/2018  DONE  BVD 
Route Revision Structural  11/6/2018  11/27/2018    11/26/2018  APPR  BVD 
Route Revision Structural  11/9/2018  11/30/2018    11/20/2018  APPR  BVD 
BLD - Reinforcing Insp  11/14/2018 12:21:03 AM  11/15/2018  10 AM - 2 PM  11/15/2018  BEN 
BLD - Footings Insp  11/15/2018 9:37:33 PM  11/16/2018  10 AM - 2 PM  11/16/2018  BEN 
BLD - Framing Insp.  11/16/2018  11/17/2018    11/20/2018  BEN 
BLD - Reinforcing Insp  11/16/2018  11/17/2018    11/20/2018  BEN 
BLD - Framing Insp.  11/24/2018 5:59:07 AM  11/26/2018  8 AM - 12 PM  11/26/2018  PJJ 
BLD - Framing Insp.  11/28/2018 5:07:41 PM  11/29/2018  10 AM - 2 PM  11/29/2018  BEN 
BLD - Exterior Lath Insp  11/28/2018 5:08:21 PM  11/29/2018  10 AM - 2 PM  11/29/2018  BEN 
BLD - Exterior Lath Insp  11/29/2018 11:53:17 AM  11/30/2018  10 AM - 2 PM  11/30/2018  BEN 
BLD - Framing Insp.  11/29/2018 11:53:31 AM  11/30/2018  10 AM - 2 PM  11/30/2018  BEN 
BLD - Exterior Lath Insp  12/4/2018 8:03:17 PM  12/5/2018  10 AM - 2 PM  12/5/2018  BEN 
Route to Fire Department  12/6/2018  12/24/2018    12/6/2018  APPR  EPO 
Inspection by Fire Department  12/6/2018  12/24/2018    12/7/2018  DONE  MGA 
Approved by Fire Department  12/6/2018      12/6/2018  APPR  408 
Route Revision Structural  12/6/2018  12/24/2018    12/6/2018  APPR  BVD 
Approved Revision Structural  12/6/2018      12/6/2018  DONE  BVD 
BLD - Misc. Inspection  12/6/2018  12/7/2018  10 AM - 2 PM  12/7/2018  BEN 
Building Final Insp Request  12/18/2018 11:56:15 AM  12/21/2018  8 AM - 12 PM  12/21/2018  BEN 
Route to Planning Zoning  2/4/2019  2/21/2019    2/21/2019  APPR  EYT 
Approved by Planning Zoning  2/4/2019      2/21/2019 12:32:10 PM  APPR  EYT 
Approved Revision Structural  2/4/2019      2/21/2019  APPR  BVD 
Route Revision Structural  2/4/2019  2/21/2019    2/8/2019  APPR  BVD 
BLD - Framing Insp.  2/26/2019 8:16:25 AM  2/27/2019  10 AM - 2 PM  2/27/2019  BEN 
Building Final Insp Request  2/26/2019 8:16:47 AM  2/27/2019  10 AM - 2 PM  2/27/2019  BEN 
Building Final        2/27/2019    BEN 

 


Back to Search
Help Top of Page