The information below summarizes the Permit Number you selected.

Permit Number:  BLD2016-02743     Status:   Finaled     Map Info:   1921 S UNION ST
Name: GENE SALAS
Address: 1921 S UNION
Received Date: 06/06/2016 
Parcel: 08329301 
Plan Check Date:  
Issue Date: 03/06/2017 
Expiration Date: 03/09/2020 
Finaled Date: 10/10/2019 
Description: New Residential Construction: 371-Unit apartment "A" building with balconies, leasing office, interior corridor, clubroom, fitness/yoga/stretch center(s), and WiFi/Cafe. 

Activities
Type  Requested  Scheduled  Time of Inspection  Completed  Disposition  Employee 
Route to Traffic Engineering  6/6/2016  8/2/2016    8/9/2016  APPR  DJK 
Approved by Traffic Eng.  6/6/2016      8/11/2016 6:26:40 PM  APPR  DJK 
Route to PW Develop. Services  6/6/2016  8/2/2016    8/10/2016  CORR  SXA 
Apprv. by PW Develop. Services  6/6/2016      2/28/2017  DONE  SXA 
Route to PW Operations  6/6/2016  8/2/2016    8/17/2016  CORR  LMM 
Approved by PW Operations  6/6/2016      12/1/2016 1:15:09 PM  NR  LMM 
FIRE - Create BFP case  6/6/2016      8/10/2016  DONE  408 
Route to Fire Department  6/6/2016  8/2/2016    8/10/2016  CORR  408 
Approved by Fire Department  6/6/2016      9/26/2016  APPR  408 
Route to Plumbing  6/6/2016  8/2/2016    8/2/2016  CORR  BVD 
Approved by Plumbing  6/6/2016      12/12/2016 7:26:17 AM  APPR  BVD 
Route to Mechanical  6/6/2016  8/2/2016    8/2/2016  CORR  BVD 
Approved by Mechanical  6/6/2016      12/12/2016 7:26:46 AM  APPR  BVD 
Route to Struct/Architectual  6/6/2016  8/2/2016    8/2/2016  CORR  BVD 
Apprv. by Struct/Architectural  6/6/2016      12/12/2016 7:25:02 AM  APPR  BVD 
Route to Planning Zoning  6/6/2016  8/2/2016    8/18/2016  CORR  GSK 
Approved by Planning Zoning  6/6/2016      12/15/2016 4:24:04 PM  APPR  GSK 
Route to Electrical  6/6/2016  8/2/2016    8/2/2016  CORR  BVD 
Approved by Electrical  6/6/2016      12/12/2016 6:58:09 AM  APPR  BVD 
Approved by Bus Lic (Sub List)  6/6/2016  4/29/2019    4/30/2019  APPR  CSL 
Approved: School Fees Due  6/6/2016      3/3/2017  APPR  MJF 
Route to Elec Engineering  6/6/2016  8/2/2016    8/16/2016  CORR  CMK 
Approved by Elec Engineering  6/6/2016      12/6/2016 6:06:32 AM  APPR  CMK 
Route to Water Engineering  6/6/2016  8/2/2016    6/16/2016  CORR  DRS 
Approved by Water Engineering  6/6/2016      9/8/2016 4:13:12 PM  APPR  DRS 
Approved by Addressing  6/6/2016      6/7/2016 7:54:49 AM  APPR  HXN 
Route to Addressing  6/6/2016  8/2/2016    6/7/2016 7:54:48 AM  APPR  HXN 
Route to Electrical  8/23/2016  9/9/2016    9/26/2016  CORR  BVD 
Route to Struct/Architectual  8/23/2016  9/9/2016    9/26/2016  CORR  BVD 
Route to Elec Engineering  8/23/2016  9/9/2016    9/7/2016  CORR  CMK 
Route to Fire Department  8/23/2016  9/9/2016    9/16/2016  CORR  472 
Route to Mechanical  8/23/2016  9/9/2016    9/26/2016  CORR  BVD 
Route to Planning Zoning  8/23/2016  9/9/2016    9/29/2016  CORR  GSK 
Route to Plumbing  8/23/2016  9/9/2016    9/26/2016  CORR  BVD 
Route to PW Develop. Services  8/23/2016  9/9/2016    9/22/2016  CORR  SXA 
Route to PW Operations  8/23/2016  9/9/2016    10/19/2016  CORR  LMM 
Route to Water Engineering  8/23/2016  9/9/2016    9/8/2016  APPR  DRS 
Route to Electrical  10/14/2016  11/1/2016    11/1/2016  CORR  BVD 
Route to Elec Engineering  10/14/2016  11/1/2016    10/25/2016  CORR  CMK 
Route to Mechanical  10/14/2016  11/1/2016    11/1/2016  CORR  BVD 
Route to Planning Zoning  10/14/2016  11/1/2016    12/12/2016  APPR  GSK 
Route to Plumbing  10/14/2016  11/1/2016    11/1/2016  CORR  BVD 
Route to PW Develop. Services  10/14/2016  11/1/2016    11/14/2016  CORR  CJO 
Route to PW Operations  10/14/2016  11/1/2016    10/19/2016  CORR  LMM 
Route to Struct/Architectual  10/14/2016  11/1/2016    11/1/2016  CORR  BVD 
Route to Electrical  11/22/2016  12/12/2016    12/12/2016  APPR  BVD 
Route to Elec Engineering  11/22/2016  12/12/2016    12/6/2016  APPR  CMK 
Route to Fire Department  11/22/2016  12/12/2016    12/20/2016  CORR  408 
Route to Mechanical  11/22/2016  12/12/2016    12/12/2016  APPR  BVD 
Route to Planning Zoning  11/22/2016  12/12/2016    12/15/2016  APPR  GSK 
Route to Plumbing  11/22/2016  12/12/2016    12/12/2016  APPR  BVD 
Route to PW Develop. Services  11/22/2016  12/12/2016    12/20/2016  CORR  SXA 
Route to PW Operations  11/22/2016  12/12/2016    12/1/2016  NR  LMM 
Route to Struct/Architectual  11/22/2016  12/12/2016    12/12/2016  APPR  BVD 
Route to Electrical  12/21/2016  1/10/2017    12/21/2016  APPR  BVD 
Route to Mechanical  12/21/2016  1/10/2017    12/21/2016  APPR  BVD 
Route to Plumbing  12/21/2016  1/10/2017    12/21/2016  APPR  BVD 
Route to Struct/Architectual  12/21/2016  1/10/2017    12/21/2016  APPR  BVD 
Route to PW Develop. Services  12/21/2016  1/10/2017    2/28/2017  APPR  ZAC 
Approved Revision Electrical        6/1/2017  APPR  BVD 
Route Revision Electrical  5/4/2017  6/1/2017    6/1/2017  APPR  BVD 
Approved Revision Mechanical        6/1/2017  APPR  BVD 
Route Revision Mechanical  5/4/2017  6/1/2017    6/1/2017  APPR  BVD 
Approved by Planning Zoning  5/4/2017      8/1/2017 4:44:55 PM  NR  GSK 
Route to Planning Zoning  5/4/2017  6/1/2017    8/1/2017  NR  GSK 
Approved Revision Plumbing        7/6/2017  APPR  BVD 
Route Revision Plumbing  5/4/2017  6/1/2017    6/1/2017  CORR  BVD 
Approved Revision Structural  5/4/2017      7/6/2017  APPR  BVD 
Route Revision Structural  5/4/2017  6/1/2017    6/1/2017  CORR  BVD 
Approved by Traffic Eng.  5/4/2017      6/1/2017 6:31:53 PM  APPR  DJK 
Route to Traffic Engineering  5/4/2017  6/1/2017    6/1/2017  APPR  DJK 
Approved by Fire Department  5/4/2017      7/20/2017  APPR  408 
Route to Fire Department  5/4/2017  6/1/2017    6/1/2017  CORR  408 
Approved by Elec Engineering  6/22/2017      7/10/2017 2:14:47 PM  APPR  JJB 
Route to Elec Engineering  6/22/2017  7/11/2017    7/10/2017  APPR  JJB 
Route to Planning Zoning  6/22/2017  7/11/2017    8/1/2017  NR  GSK 
Route Revision Plumbing  6/22/2017  7/11/2017    7/6/2017  APPR  BVD 
Route Revision Structural  6/22/2017  7/11/2017    7/6/2017  APPR  BVD 
Route to Fire Department  6/22/2017  7/11/2017    7/20/2017  APPR  408 
PLM - Sewer  7/17/2017 12:54:37 PM  7/19/2017  10 AM - 2 PM  7/19/2017  BIH 
PLM - Ground/Underfloor waste  7/27/2017 7:46:08 AM  7/28/2017  10 AM - 2 PM  7/28/2017  BIH 
PLM - Ground/Underfloor waste  7/28/2017 8:21:13 AM  8/1/2017  8 AM - 12 PM  8/1/2017  BIH 
PLM - Sewer  7/28/2017  7/28/2017  10 AM - 2 PM  7/28/2017  BIH 
PLM - Ground/Underfloor water  8/17/2017 7:31:24 AM  8/18/2017  8 AM - 12 PM  8/18/2017  BIH 
Route Revision Structural  9/8/2017  9/26/2017    9/21/2017  CORR  BVD 
Approved Revision Structural  9/8/2017      12/5/2017  DONE  BVD 
Route to Elec Engineering  9/8/2017  9/26/2017    9/19/2017  APPR  CMK 
Approved by Elec Engineering  9/8/2017      9/19/2017 11:01:02 AM  APPR  CMK 
Route to Fire Department  9/8/2017  9/26/2017    10/20/2017  APPR  408 
Approved by Fire Department  9/8/2017      10/20/2017 10:57:28 AM  APPR  408 
Route Revision Electrical  9/8/2017  9/26/2017    9/21/2017  APPR  BVD 
Approved Revision Electrical        9/21/2017  DONE  BVD 
Route Revision Mechanical  9/8/2017  9/26/2017    9/21/2017  APPR  BVD 
Approved Revision Mechanical        9/21/2017  DONE  BVD 
Route to Planning Zoning  9/8/2017  9/26/2017    10/11/2017  NR  GSK 
Approved by Planning Zoning  9/8/2017      10/11/2017 4:24:48 PM  NR  GSK 
Route Revision Plumbing  9/8/2017  9/26/2017    9/21/2017  APPR  BVD 
Approved Revision Plumbing        9/21/2017  DONE  BVD 
Route to PW Develop. Services  9/8/2017  9/26/2017    10/11/2017  APPR  SXA 
Apprv. by PW Develop. Services  9/8/2017      10/11/2017 4:53:22 PM  APPR  SXA 
Route to PW Operations  9/8/2017  9/26/2017    10/10/2017  APPR  LMM 
Approved by PW Operations  9/8/2017      10/10/2017 8:43:21 AM  APPR  LMM 
Route to Traffic Engineering  9/8/2017  9/26/2017    10/3/2017  APPR  DJK 
Approved by Traffic Eng.  9/8/2017      10/3/2017 4:51:17 PM  APPR  DJK 
Route to Water Engineering  9/8/2017  9/26/2017    9/27/2017  CORR  DRS 
Approved by Water Engineering  9/8/2017      12/19/2017 10:33:39 AM  APPR  DRS 
Route to Struct/Architectual  10/26/2017  11/14/2017    11/9/2017  CORR  BVD 
Apprv. by Struct/Architectural  10/26/2017      12/26/2017 7:28:16 AM  APPR  BVD 
ELE - Underground conduit  10/27/2017 2:06:57 PM  10/30/2017  8 AM - 12 PM  10/30/2017  BIH 
ELE - Underground conduit  10/30/2017 1:57:59 PM  10/31/2017  8 AM - 12 PM  10/31/2017  BIH 
ELE - Underground conduit  10/31/2017 11:51:07 AM  11/1/2017  8 AM - 12 PM  11/1/2017  BIH 
PLM - Ground/Underfloor waste  11/8/2017 1:47:49 PM  11/9/2017  12 PM - 3 PM  11/9/2017  BIH 
PLM - Ground/Underfloor water  11/8/2017 2:07:32 PM  11/9/2017  12 PM - 3 PM  11/9/2017  BIH 
PLM - Ground/Underfloor water  11/27/2017 2:47:01 PM  11/28/2017  8 AM - 12 PM  11/28/2017  BIH 
PLM - Water Service  11/28/2017 11:44:15 AM  11/29/2017  8 AM - 12 PM  11/29/2017  BIH 
PLM - Ground/Underfloor waste  11/29/2017 9:13:01 AM  11/30/2017  8 AM - 12 PM  11/30/2017  BIH 
PLM - Ground/Underfloor waste  11/30/2017 11:20:24 AM  12/1/2017  12 PM - 3 PM  12/1/2017  BIH 
Route to Water Engineering  12/1/2017  12/19/2017    12/19/2017  APPR  DRS 
Route Revision Structural  12/1/2017  12/19/2017    12/5/2017  APPR  BVD 
PLM - Rough/Topout  12/4/2017  12/5/2017  12 PM - 3 PM  12/5/2017  BIH 
ELE - Rough Electrical  12/4/2017  12/5/2017  12 PM - 3 PM  12/5/2017  BIH 
BLD - Reinforcing Insp  12/5/2017 10:00:10 AM  12/6/2017  12 PM - 3 PM  12/6/2017  BIH 
PLM - Ground/Underfloor waste  12/6/2017 2:36:33 PM  12/7/2017  8 AM - 12 PM  12/7/2017  BIH 
ELE - Underground conduit  12/6/2017 2:38:37 PM  12/7/2017  8 AM - 12 PM  12/7/2017  BIH 
PLM - Ground/Underfloor waste  12/11/2017 8:59:59 AM  12/12/2017  8 AM - 12 PM  12/12/2017  BIH 
PLM - Ground/Underfloor waste  12/11/2017  12/12/2017  8 AM - 12 PM  12/12/2017  BIH 
PLM - Ground/Underfloor waste  12/13/2017 11:17:46 AM  12/14/2017  10 AM - 2 PM  12/14/2017  BIH 
PLM - Ground/Underfloor waste  12/14/2017 1:37:02 PM  12/15/2017  10 AM - 2 PM  12/15/2017  BIH 
Route to Struct/Architectual  12/21/2017  1/10/2018    12/26/2017  APPR  BVD 
ELE - Underground conduit  12/28/2017  12/29/2017  12 PM - 3 PM  12/29/2017  BIH 
Route to Struct/Architectual  1/4/2018  1/23/2018    1/23/2018  APPR  BVD 
Apprv. by Struct/Architectural  1/4/2018      1/23/2018 5:44:26 AM  APPR  BVD 
ELE - Underground conduit  1/4/2018 1:11:51 PM  1/5/2018  8 AM - 12 PM  1/5/2018  BIH 
BLD - Footings Insp  1/10/2018  1/11/2018  10 AM - 2 PM  1/11/2018  BIH 
PLM - Ground/Underfloor waste  1/10/2018  1/11/2018  10 AM - 2 PM  1/11/2018  BIH 
PLM - Ground/Underfloor water  1/10/2018  1/11/2018  10 AM - 2 PM  1/11/2018  BIH 
BLD - Reinforcing Insp  1/11/2018 8:25:57 AM  1/12/2018  10 AM - 2 PM  1/12/2018  BIH 
ELE - Ground Electrode/UFER  1/12/2018  1/12/2018    1/12/2018  BIH 
PLM - Ground/Underfloor waste  1/12/2018  1/12/2018    1/12/2018  BIH 
BLD - Footings Insp  1/17/2018 6:49:01 AM  1/18/2018  8 AM - 12 PM  1/18/2018  BIH 
BLD - Pre-Slab Insp  1/18/2018 11:25:56 AM  1/19/2018  10 AM - 2 PM  1/19/2018  BIH 
PLM - Ground/Underfloor waste  1/18/2018  1/18/2018  8 AM - 12 PM  1/18/2018  BIH 
ELE - Underground conduit  1/19/2018 12:46:39 PM  1/22/2018  8 AM - 12 PM  1/22/2018  BIH 
BLD - Pre-Slab Insp  1/24/2018  1/25/2018  10 AM - 2 PM  1/25/2018  BIH 
BLD - Reinforcing Insp  1/24/2018  1/26/2018  10 AM - 2 PM  1/26/2018  BIH 
ELE - Ground Electrode/UFER  1/24/2018  1/26/2018  10 AM - 2 PM  1/26/2018  BIH 
BLD - Pre-Slab Insp  1/25/2018  1/26/2018  10 AM - 2 PM  1/26/2018  BIH 
BLD - Pre-Slab Insp  1/31/2018 7:51:24 AM  2/1/2018  10 AM - 2 PM  2/1/2018  BIH 
BLD - Footings Insp  2/2/2018 11:18:18 AM  2/6/2018  8 AM - 12 PM  2/6/2018  BIH 
ELE - Ground Electrode/UFER  2/6/2018 8:23:43 AM  2/7/2018  10 AM - 2 PM  2/7/2018  BIH 
BLD - Footings Insp  2/6/2018  2/6/2018    2/6/2018  BIH 
BLD - Footings Insp  2/6/2018  2/6/2018    2/6/2018  BIH 
BLD - Framing Insp.  2/8/2018 8:36:47 AM  2/9/2018  10 AM - 2 PM  2/9/2018  BIH 
BLD - Framing Insp.  2/9/2018 1:54:04 PM  2/12/2018  10 AM - 2 PM  2/12/2018  BIH 
BLD - Pre-Slab Insp  2/12/2018 10:34:41 AM  2/13/2018  10 AM - 2 PM  2/13/2018  BIH 
BLD - Footings Insp  2/13/2018 1:39:28 PM  2/14/2018  12 PM - 3 PM  2/14/2018  BIH 
BLD - Framing Insp.  2/13/2018 3:21:17 PM  2/14/2018  12 PM - 3 PM  2/14/2018  BIH 
BLD - Framing Insp.  2/15/2018 3:11:46 PM  2/16/2018  8 AM - 12 PM  2/16/2018  JOS 
PLM - Ground/Underfloor water  2/16/2018 12:06:41 PM  2/20/2018  10 AM - 2 PM  2/20/2018  BIH 
BLD - Footings Insp  2/19/2018  2/21/2018  8 AM - 12 PM  2/21/2018  BIH 
BLD - Pre-Slab Insp  2/19/2018  2/21/2018  8 AM - 12 PM  2/21/2018  BIH 
BLD - Framing Insp.  2/19/2018  2/21/2018  8 AM - 12 PM  2/21/2018  BIH 
BLD - Pre-Slab Insp  2/20/2018  2/20/2018  10 AM - 2 PM  2/21/2018  BIH 
BLD - Footings Insp  2/20/2018  2/20/2018  10 AM - 2 PM  2/21/2018  BIH 
BLD - Framing Insp.  2/20/2018  2/20/2018  10 AM - 2 PM  2/21/2018  BIH 
ELE - Ground Electrode/UFER  2/21/2018  2/21/2018  8 AM - 12 PM  2/21/2018  BIH 
PLM - Ground/Underfloor waste  2/21/2018  2/21/2018  10 AM - 2 PM  2/21/2018  BIH 
BLD - Pre-Slab Insp  2/22/2018 2:31:20 PM  2/23/2018  10 AM - 2 PM  2/23/2018  BIH 
BLD - Footings Insp  2/22/2018 2:32:46 PM  2/23/2018  10 AM - 2 PM  2/23/2018  BIH 
BLD - Exterior Lath Insp  3/1/2018 3:02:59 PM  3/2/2018  8 AM - 12 PM  3/2/2018  BIH 
BLD - Exterior Lath Insp  3/2/2018 11:44:59 AM  3/5/2018  8 AM - 12 PM  3/5/2018  RML 
BLD - Framing Insp.  3/8/2018 3:07:16 PM  3/9/2018  10 AM - 2 PM  3/9/2018  BCJ 
BLD - Floor Nailing  3/8/2018 3:07:37 PM  3/9/2018  10 AM - 2 PM  3/9/2018  BCJ 
BLD - 1st Floor Shear Insp  3/8/2018 3:08:15 PM  3/9/2018  10 AM - 2 PM  3/9/2018  BCJ 
BLD - Drywall Inspection  3/8/2018 3:10:02 PM  3/9/2018  10 AM - 2 PM  3/9/2018  BCJ 
BLD - 1st Floor Shear Insp  3/12/2018 3:27:49 PM  3/13/2018  8 AM - 12 PM  3/13/2018  BIH 
BLD - Floor Nailing  3/12/2018 3:28:14 PM  3/13/2018  8 AM - 12 PM  3/13/2018  BIH 
BLD - 1st Floor Shear Insp  3/13/2018 3:18:29 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BIH 
BLD - Floor Nailing  3/13/2018 3:19:09 PM  3/14/2018  12 PM - 3 PM  3/14/2018  BIH 
BLD - Floor Nailing  3/15/2018 3:32:54 PM  3/16/2018  12 PM - 3 PM  3/16/2018  BIH 
BLD - 1st Floor Shear Insp  3/15/2018 3:33:39 PM  3/16/2018  12 PM - 3 PM  3/16/2018  BIH 
BLD - 1st Floor Shear Insp  3/19/2018 2:04:02 PM  3/20/2018  12 PM - 3 PM  3/20/2018  BIH 
BLD - 2nd Floor Nailing  3/19/2018 2:04:17 PM  3/20/2018  12 PM - 3 PM  3/20/2018  BIH 
BLD - Footings Insp  3/20/2018 11:43:53 AM  3/21/2018  12 PM - 3 PM  3/21/2018  BIH 
BLD - Floor Nailing  3/21/2018 4:28:10 PM  3/22/2018  10 AM - 2 PM  3/22/2018  BIH 
BLD - 1st Floor Shear Insp  3/21/2018 4:28:31 PM  3/22/2018  10 AM - 2 PM  3/22/2018  BIH 
BLD - 2nd Floor Nailing  3/22/2018  3/23/2018  8 AM - 12 PM  3/23/2018  BIH 
BLD - 1st Floor Shear Insp  3/22/2018  3/23/2018  8 AM - 12 PM  3/23/2018  BIH 
Apprv. by Struct/Architectural  3/22/2018      4/26/2018 9:52:41 AM  APPR  BVD 
Route to Struct/Architectual  3/22/2018  4/9/2018    4/3/2018  CORR  BVD 
BLD - Floor Nailing  3/23/2018 4:13:50 PM  3/26/2018  10 AM - 2 PM  3/26/2018  BIH 
BLD - 1st Floor Shear Insp  3/23/2018 4:14:05 PM  3/26/2018  10 AM - 2 PM  3/26/2018  BIH 
BLD - 1st Floor Shear Insp  3/26/2018 12:15:08 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BIH 
BLD - 1st Floor Shear Insp  3/26/2018 2:23:56 PM  3/27/2018  12 PM - 3 PM  3/27/2018  BIH 
BLD - Floor Nailing  3/26/2018 2:24:17 PM  3/27/2018  12 PM - 3 PM  3/27/2018  BIH 
BLD - Drywall Inspection  3/27/2018 3:48:34 PM  3/28/2018  8 AM - 12 PM  3/28/2018  BIH 
Apprv. by Struct/Architectural  3/28/2018      5/15/2018 6:58:01 AM  APPR  BVD 
Route to Struct/Architectual  3/28/2018  4/13/2018    4/5/2018  CORR  BVD 
BLD - Drywall Inspection  3/28/2018 3:38:50 PM  3/29/2018  10 AM - 2 PM  3/29/2018  BIH 
BLD - Drywall Inspection  3/29/2018 3:20:43 PM  3/30/2018  10 AM - 2 PM  3/30/2018  BIH 
BLD - 1st Floor Shear Insp  3/29/2018 3:37:03 PM  4/2/2018  12 PM - 3 PM  4/2/2018  BIH 
BLD - 2nd Floor Nailing  3/29/2018 3:37:24 PM  4/2/2018  12 PM - 3 PM  4/2/2018  BIH 
BLD - Floor Nailing  4/4/2018 4:26:26 PM  4/5/2018  10 AM - 2 PM  4/5/2018  BIH 
BLD - 1st Floor Shear Insp  4/4/2018 4:26:44 PM  4/5/2018  10 AM - 2 PM  4/5/2018  BIH 
BLD - Floor Nailing  4/5/2018 1:57:18 PM  4/6/2018  10 AM - 2 PM  4/6/2018  BIH 
BLD - Drywall Inspection  4/5/2018 1:57:33 PM  4/6/2018  10 AM - 2 PM  4/6/2018  BIH 
BLD - 1st Floor Shear Insp  4/5/2018 1:58:01 PM  4/6/2018  10 AM - 2 PM  4/6/2018  BIH 
BLD - 1st Floor Shear Insp  4/6/2018 2:39:10 PM  4/9/2018  8 AM - 12 PM  4/9/2018  KLA 
BLD - 2nd Floor Nailing  4/6/2018 2:39:32 PM  4/9/2018  8 AM - 12 PM  4/9/2018  KLA 
BLD - 2nd Floor Shear Insp  4/6/2018 2:39:59 PM  4/9/2018  8 AM - 12 PM  4/9/2018  KLA 
BLD - Floor Nailing  4/6/2018 2:40:15 PM  4/9/2018  8 AM - 12 PM  4/9/2018  KLA 
BLD - Drywall Inspection  4/9/2018  4/10/2018  10 AM - 2 PM  4/10/2018  BIH 
BLD - 1st Floor Shear Insp  4/9/2018 3:44:48 PM  4/10/2018  10 AM - 2 PM  4/10/2018  BIH 
BLD - Floor Nailing  4/9/2018 3:45:09 PM  4/10/2018  10 AM - 2 PM  4/10/2018  BIH 
BLD - Floor Nailing  4/10/2018 4:03:32 PM  4/11/2018  10 AM - 2 PM  4/11/2018  BIH 
BLD - 2nd Floor Shear Insp  4/10/2018 4:04:09 PM  4/11/2018  10 AM - 2 PM  4/11/2018  BIH 
BLD - Drywall Inspection  4/10/2018 4:05:57 PM  4/11/2018  10 AM - 2 PM  4/11/2018  BIH 
BLD - Drywall Inspection  4/11/2018 2:53:42 PM  4/12/2018  10 AM - 2 PM  4/12/2018  BIH 
BLD - Floor Nailing  4/11/2018 3:26:16 PM  4/12/2018  10 AM - 2 PM  4/12/2018  BIH 
BLD - Floor Nailing  4/12/2018 1:50:04 PM  4/13/2018  10 AM - 2 PM  4/13/2018  BIH 
BLD - 2nd Floor Shear Insp  4/12/2018 1:50:27 PM  4/13/2018  10 AM - 2 PM  4/13/2018  BIH 
ELE - Rough Electrical  4/12/2018 1:50:46 PM  4/13/2018  10 AM - 2 PM  4/13/2018  BIH 
Route to Fire Department  4/13/2018  5/1/2018    6/7/2018  CORR  AEG 
Approved by Planning Zoning  4/13/2018      5/9/2018 10:08:47 AM  NR  GSK 
Route to Planning Zoning  4/13/2018  5/1/2018    5/9/2018  NR  GSK 
Approved Revision Structural  4/13/2018      6/25/2018  DONE  BVD 
Route Revision Structural  4/13/2018  5/1/2018    5/1/2018  CORR  BVD 
Approved by Elec Engineering  4/13/2018      7/31/2018 9:33:58 AM  APPR  CMK 
Route to Elec Engineering  4/13/2018  5/1/2018    5/1/2018  CORR  JJB 
Approved Revision Electrical        4/26/2018  APPR  MCS 
Route Revision Electrical  4/13/2018  5/1/2018    4/26/2018  APPR  MCS 
Approved Revision Mechanical        5/2/2018  DONE  GAQ 
Route Revision Mechanical  4/13/2018  5/1/2018    5/2/2018  APPR  GAQ 
Approved Revision Plumbing        5/2/2018  DONE  GAQ 
Route Revision Plumbing  4/13/2018  5/1/2018    5/2/2018  APPR  GAQ 
BLD - Drywall Inspection  4/13/2018 12:34:06 PM  4/16/2018  10 AM - 2 PM  4/16/2018  BIH 
BLD - 1st Floor Shear Insp  4/13/2018 12:37:55 PM  4/16/2018  10 AM - 2 PM  4/16/2018  BIH 
BLD - Floor Nailing  4/13/2018 12:38:07 PM  4/16/2018  10 AM - 2 PM  4/16/2018  BIH 
BLD - Floor Nailing  4/16/2018 3:32:28 PM  4/17/2018  10 AM - 2 PM  4/17/2018  BIH 
BLD - 2nd Floor Shear Insp  4/16/2018 3:32:42 PM  4/17/2018  10 AM - 2 PM  4/17/2018  BIH 
ELE - Rough Electrical  4/16/2018 3:33:55 PM  4/17/2018  10 AM - 2 PM  4/17/2018  BIH 
BLD - Drywall Inspection  4/16/2018 4:31:59 PM  4/17/2018  10 AM - 2 PM  4/17/2018  BIH 
BLD - Drywall Inspection  4/17/2018 4:14:56 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BIH 
BLD - Drywall Inspection  4/17/2018 4:15:58 PM  4/19/2018  8 AM - 12 PM  4/19/2018  BIH 
BLD - Drywall Inspection  4/17/2018 4:16:21 PM  4/20/2018  10 AM - 2 PM  4/20/2018  BIH 
BLD - 1st Floor Shear Insp  4/17/2018 4:17:41 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BIH 
BLD - Floor Nailing  4/17/2018 4:17:55 PM  4/18/2018  12 PM - 3 PM  4/18/2018  BIH 
Route to Struct/Architectual  4/18/2018  5/4/2018    4/24/2018  CORR  BVD 
BLD - Floor Nailing  4/18/2018 3:17:23 PM  4/19/2018  8 AM - 12 PM  4/19/2018  BIH 
BLD - 2nd Floor Shear Insp  4/18/2018 3:17:36 PM  4/19/2018  8 AM - 12 PM  4/19/2018  BIH 
Route to Struct/Architectual  4/19/2018  5/7/2018    4/26/2018  APPR  BVD 
BLD - Floor Nailing  4/19/2018 4:21:39 PM  4/20/2018  10 AM - 2 PM  4/20/2018  BIH 
BLD - 2nd Floor Shear Insp  4/19/2018 4:21:48 PM  4/20/2018  10 AM - 2 PM  4/20/2018  BIH 
BLD - Floor Nailing  4/20/2018 12:06:02 PM  4/23/2018  10 AM - 2 PM  4/23/2018  BIH 
BLD - 2nd Floor Shear Insp  4/20/2018 12:06:14 PM  4/23/2018  10 AM - 2 PM  4/23/2018  BIH 
BLD - Drywall Inspection  4/20/2018 12:06:25 PM  4/23/2018  10 AM - 2 PM  4/23/2018  BIH 
BLD - Drywall Inspection  4/20/2018 3:55:22 PM  4/24/2018  12 PM - 3 PM  4/24/2018  DOM 
BLD - Floor Nailing  4/23/2018 1:53:51 PM  4/24/2018  12 PM - 3 PM  4/24/2018  DOM 
BLD - 2nd Floor Shear Insp  4/23/2018 1:54:05 PM  4/24/2018  12 PM - 3 PM  4/24/2018  DOM 
BLD - 2nd Floor Shear Insp  4/24/2018  4/25/2018  12 PM - 3 PM  4/25/2018  BIH 
BLD - Floor Nailing  4/25/2018 4:15:50 PM  4/26/2018  12 PM - 3 PM  4/26/2018  BIH 
BLD - 1st Floor Shear Insp  4/25/2018 4:16:12 PM  4/26/2018  12 PM - 3 PM  4/26/2018  BIH 
BLD - Drywall Inspection  4/25/2018 4:16:24 PM  4/26/2018  12 PM - 3 PM  4/26/2018  BIH 
BLD - Floor Nailing  4/26/2018 3:54:34 PM  4/27/2018  8 AM - 12 PM  4/27/2018  BIH 
BLD - 1st Floor Shear Insp  4/26/2018 3:54:47 PM  4/27/2018  8 AM - 12 PM  4/27/2018  BIH 
BLD - Drywall Inspection  4/26/2018 3:54:56 PM  4/27/2018  8 AM - 12 PM  4/27/2018  BIH 
BLD - Drywall Inspection  4/27/2018 2:12:58 PM  4/30/2018  12 PM - 3 PM  4/30/2018  BIH 
ELE - Rough Electrical  4/27/2018 2:14:15 PM  4/30/2018  12 PM - 3 PM  4/30/2018  BIH 
BLD - 2nd Floor Nailing  4/27/2018 2:14:52 PM  4/30/2018  12 PM - 3 PM  4/30/2018  BIH 
BLD - 1st Floor Shear Insp  4/27/2018 2:15:16 PM  4/30/2018  12 PM - 3 PM  4/30/2018  BIH 
BLD - Floor Nailing  4/30/2018 3:38:04 PM  5/1/2018  12 PM - 3 PM  5/1/2018  BIH 
BLD - 2nd Floor Shear Insp  4/30/2018 3:38:23 PM  5/1/2018  12 PM - 3 PM  5/1/2018  BIH 
ELE - Rough Electrical  4/30/2018 3:38:39 PM  5/1/2018  12 PM - 3 PM  5/1/2018  BIH 
BLD - Drywall Inspection  5/1/2018 3:16:31 PM  5/2/2018  12 PM - 3 PM  5/2/2018  BIH 
BLD - 2nd Floor Nailing  5/1/2018 3:16:48 PM  5/2/2018  12 PM - 3 PM  5/2/2018  BIH 
BLD - 2nd Floor Shear Insp  5/1/2018 3:17:09 PM  5/2/2018  12 PM - 3 PM  5/2/2018  BIH 
ELE - Rough Electrical  5/1/2018 3:17:43 PM  5/2/2018  12 PM - 3 PM  5/2/2018  BIH 
BLD - Floor Nailing  5/2/2018 3:25:26 PM  5/3/2018  12 PM - 3 PM  5/3/2018  BIH 
BLD - 2nd Floor Shear Insp  5/2/2018 3:25:35 PM  5/3/2018  12 PM - 3 PM  5/3/2018  BIH 
ELE - Rough Electrical  5/2/2018 3:25:55 PM  5/3/2018  12 PM - 3 PM  5/3/2018  BIH 
BLD - Drywall Inspection  5/2/2018 3:49:31 PM  5/3/2018  12 PM - 3 PM  5/3/2018  BIH 
BLD - Framing Insp.  5/2/2018 3:49:53 PM  5/4/2018  10 AM - 2 PM  5/4/2018  BIH 
BLD - Floor Nailing  5/3/2018 2:54:22 PM  5/4/2018  10 AM - 2 PM  5/4/2018  BIH 
BLD - 2nd Floor Shear Insp  5/3/2018 2:54:33 PM  5/4/2018  10 AM - 2 PM  5/4/2018  BIH 
BLD - Penetrations -Fire Rated  5/3/2018 2:54:52 PM  5/4/2018  10 AM - 2 PM  5/4/2018  BIH 
BLD - Drywall Inspection  5/3/2018 2:55:15 PM  5/4/2018  10 AM - 2 PM  5/4/2018  BIH 
BLD - Framing Insp.  5/4/2018 1:48:56 PM  5/7/2018  8 AM - 12 PM  5/7/2018  BIH 
BLD - Drywall Inspection  5/4/2018 1:49:14 PM  5/7/2018  8 AM - 12 PM  5/7/2018  BIH 
Route to Struct/Architectual  5/4/2018  5/22/2018    5/15/2018  APPR  BVD 
BLD - Drywall Inspection  5/4/2018  5/7/2018  8 AM - 12 PM  5/7/2018  BIH 
BLD - 2nd Floor Shear Insp  5/4/2018  5/7/2018  8 AM - 12 PM  5/7/2018  BIH 
BLD - Penetrations -Fire Rated  5/4/2018  5/7/2018  8 AM - 12 PM  5/7/2018  BIH 
BLD - Drywall Inspection  5/7/2018 3:02:35 PM  5/8/2018  10 AM - 2 PM  5/8/2018  BIH 
BLD - Insulation Insp  5/7/2018 3:03:21 PM  5/8/2018  10 AM - 2 PM  5/8/2018  BIH 
ELE - Penetrations- Fire Rated  5/7/2018 3:04:03 PM  5/8/2018  10 AM - 2 PM  5/8/2018  BIH 
BLD - Floor Nailing  5/7/2018 3:05:50 PM  5/8/2018  10 AM - 2 PM  5/8/2018  BIH 
BLD - 1st Floor Shear Insp  5/7/2018 3:06:18 PM  5/8/2018  10 AM - 2 PM  5/8/2018  BIH 
BLD - Pre-Grout Insp  5/8/2018 3:24:53 PM  5/9/2018  10 AM - 2 PM  5/9/2018  BIH 
BLD - Drywall Inspection  5/8/2018 3:25:34 PM  5/9/2018  10 AM - 2 PM  5/9/2018  BIH 
BLD - Penetrations -Fire Rated  5/8/2018 3:26:06 PM  5/9/2018  10 AM - 2 PM  5/9/2018  BIH 
ELE - Rough Electrical  5/8/2018 3:26:27 PM  5/9/2018  10 AM - 2 PM  5/9/2018  BIH 
BLD - Insulation Insp  5/9/2018  5/10/2018  12 PM - 3 PM  5/10/2018  BIH 
BLD - Floor Nailing  5/9/2018 4:30:44 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BIH 
BLD - Drywall Inspection  5/9/2018 4:31:21 PM  5/10/2018  12 PM - 3 PM  5/10/2018  BIH 
BLD - Floor Nailing  5/10/2018 4:09:50 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BIH 
BLD - Drywall Inspection  5/10/2018 4:10:25 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BIH 
BLD - 2nd Floor Shear Insp  5/10/2018 4:13:12 PM  5/11/2018  12 PM - 3 PM  5/11/2018  BIH 
BLD - Drywall Inspection  5/11/2018 1:32:07 PM  5/14/2018  12 PM - 3 PM  5/14/2018  BIH 
BLD - Floor Nailing  5/11/2018 1:32:34 PM  5/14/2018  12 PM - 3 PM  5/14/2018  BIH 
BLD - 2nd Floor Shear Insp  5/11/2018 1:33:08 PM  5/14/2018  12 PM - 3 PM  5/14/2018  BIH 
BLD - Insulation Insp  5/11/2018 1:40:30 PM  5/14/2018  12 PM - 3 PM  5/14/2018  BIH 
BLD - Drywall Inspection  5/16/2018 9:57:44 AM  5/17/2018  12 PM - 3 PM  5/17/2018  BIH 
BLD - Floor Nailing  5/16/2018 9:57:57 AM  5/17/2018  12 PM - 3 PM  5/17/2018  BIH 
BLD - 1st Floor Shear Insp  5/16/2018 9:58:13 AM  5/17/2018  12 PM - 3 PM  5/17/2018  BIH 
PLM - Rough/Topout  5/16/2018 2:36:36 PM  5/17/2018  12 PM - 3 PM  5/17/2018  BIH 
BLD - Drywall Inspection  5/17/2018 3:21:09 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BIH 
PLM - Rough/Topout  5/17/2018 3:22:30 PM  5/18/2018  12 PM - 3 PM  5/18/2018  BIH 
PLM - Water Service  5/18/2018 12:33:28 PM  5/21/2018  8 AM - 12 PM  5/21/2018  MMO 
BLD - Insulation Insp  5/18/2018 3:11:20 PM  5/21/2018  8 AM - 12 PM  5/21/2018  MMO 
BLD - Drywall Inspection  5/18/2018 3:12:10 PM  5/21/2018  8 AM - 12 PM  5/21/2018  MMO 
BLD - Drywall Inspection  5/21/2018 3:41:29 PM  5/22/2018  12 PM - 3 PM  5/22/2018  JOS 
BLD - Floor Nailing  5/22/2018 3:15:01 PM  5/23/2018    5/23/2018  JOS 
BLD - 2nd Floor Shear Insp  5/22/2018 3:15:10 PM  5/23/2018    5/23/2018  JOS 
BLD - Insulation Insp  5/22/2018 4:00:21 PM  5/23/2018    5/23/2018  JOS 
BLD - 1st Floor Shear Insp  5/22/2018 4:01:07 PM  5/23/2018    5/23/2018  JOS 
BLD - Floor Nailing  5/23/2018 2:39:19 PM  5/24/2018  10 AM - 2 PM  5/24/2018  JOS 
BLD - 2nd Floor Shear Insp  5/23/2018 2:39:33 PM  5/24/2018  10 AM - 2 PM  5/24/2018  JOS 
BLD - Insulation Insp  5/23/2018 2:50:10 PM  5/24/2018  10 AM - 2 PM  5/24/2018  JOS 
BLD - Floor Nailing  5/24/2018 2:47:31 PM  5/25/2018  8 AM - 12 PM  5/25/2018  JOS 
BLD - 2nd Floor Shear Insp  5/24/2018 2:47:42 PM  5/25/2018  8 AM - 12 PM  5/25/2018  JOS 
PLM - Rough/Topout  5/24/2018 2:48:14 PM  5/25/2018  8 AM - 12 PM  5/25/2018  JOS 
BLD - Insulation Insp  5/25/2018 2:19:28 PM  5/29/2018  12 PM - 3 PM  5/29/2018  BIH 
BLD - Floor Nailing  5/25/2018 2:24:40 PM  5/29/2018  12 PM - 3 PM  5/29/2018  BIH 
BLD - 2nd Floor Shear Insp  5/25/2018 2:24:54 PM  5/29/2018  12 PM - 3 PM  5/29/2018  BIH 
PLM - Rough/Topout  5/25/2018 2:25:42 PM  5/29/2018  12 PM - 3 PM  5/29/2018  BIH 
PLM - Gas Test  5/25/2018 2:25:56 PM  5/29/2018  12 PM - 3 PM  5/29/2018  BIH 
BLD - Floor Nailing  5/29/2018 9:53:16 AM  5/30/2018  12 PM - 3 PM  5/30/2018  BIH 
BLD - 2nd Floor Shear Insp  5/29/2018 9:53:27 AM  5/30/2018  12 PM - 3 PM  5/30/2018  BIH 
BLD - Penetrations -Fire Rated  5/29/2018 9:54:21 AM  5/30/2018  12 PM - 3 PM  5/30/2018  BIH 
PLM - Gas Test  5/29/2018 3:30:01 PM  5/30/2018  12 PM - 3 PM  5/30/2018  BIH 
BLD - Insulation Insp  5/29/2018 3:30:32 PM  5/30/2018  12 PM - 3 PM  5/30/2018  BIH 
BLD - Floor Nailing  5/30/2018 4:04:38 PM  5/31/2018  12 PM - 3 PM  5/31/2018  BIH 
BLD - 2nd Floor Nailing  5/30/2018 4:04:48 PM  5/31/2018  12 PM - 3 PM  5/31/2018  BIH 
BLD - Penetrations -Fire Rated  5/30/2018 4:05:17 PM  5/31/2018  12 PM - 3 PM  5/31/2018  BIH 
PLM - Rough/Topout  5/30/2018 4:05:57 PM  5/31/2018  12 PM - 3 PM  5/31/2018  BIH 
BLD - 2nd Floor Shear Insp  5/30/2018 4:07:08 PM  5/31/2018  12 PM - 3 PM  5/31/2018  BIH 
BLD - Penetrations -Fire Rated  5/31/2018 3:04:43 PM  6/1/2018  10 AM - 2 PM  6/1/2018  BIH 
BLD - Drywall Inspection  5/31/2018 3:05:00 PM  6/1/2018  10 AM - 2 PM  6/1/2018  BIH 
BLD - Floor Nailing  5/31/2018 3:05:11 PM  6/1/2018  10 AM - 2 PM  6/1/2018  BIH 
BLD - 2nd Floor Shear Insp  5/31/2018 3:05:27 PM  6/1/2018  10 AM - 2 PM  6/1/2018  BIH 
PLM - Gas Test  5/31/2018 3:07:07 PM  6/1/2018  10 AM - 2 PM  6/1/2018  BIH 
BLD - Floor Nailing  6/1/2018 2:25:30 PM  6/4/2018  12 PM - 3 PM  6/4/2018  BIH 
BLD - 2nd Floor Shear Insp  6/1/2018 2:25:47 PM  6/4/2018  12 PM - 3 PM  6/4/2018  BIH 
PLM - Gas Test  6/1/2018 2:26:39 PM  6/4/2018  12 PM - 3 PM  6/4/2018  BIH 
PLM - Rough/Topout  6/1/2018 2:27:24 PM  6/4/2018  12 PM - 3 PM  6/4/2018  BIH 
BLD - Insulation Insp  6/4/2018 8:13:42 AM  6/5/2018  12 PM - 3 PM  6/5/2018  BIH 
PLM - Water Service  6/4/2018 2:23:29 PM  6/5/2018  12 PM - 3 PM  6/5/2018  BIH 
BLD - Floor Nailing  6/4/2018 2:43:52 PM  6/5/2018  12 PM - 3 PM  6/5/2018  BIH 
BLD - 2nd Floor Nailing  6/4/2018 2:44:20 PM  6/5/2018  12 PM - 3 PM  6/5/2018  BIH 
BLD - Insulation Insp  6/5/2018 2:46:54 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
PLM - Water Service  6/5/2018 3:30:48 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
PLM - Rough/Topout  6/5/2018 3:31:08 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
PLM - Gas Test  6/5/2018 3:31:33 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
BLD - Floor Nailing  6/5/2018 3:33:13 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
BLD - 2nd Floor Shear Insp  6/5/2018 3:33:29 PM  6/6/2018  12 PM - 3 PM  6/6/2018  BIH 
Route to Elec Engineering  6/7/2018  6/25/2018    6/28/2018  APPR  CMK 
Route Revision Structural  6/7/2018  6/25/2018    6/25/2018  APPR  BVD 
BLD - Drywall Inspection  6/7/2018 1:13:09 PM  6/8/2018  10 AM - 2 PM  6/8/2018  BIH 
BLD - Floor Nailing  6/9/2018 10:17:39 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
BLD - Drywall Inspection  6/9/2018 10:18:01 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
BLD - Insulation Insp  6/9/2018 10:18:12 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
BLD - 2nd Floor Shear Insp  6/9/2018 10:18:56 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
BLD - Penetrations -Fire Rated  6/9/2018 10:19:10 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
PLM - Water Service  6/9/2018 10:19:38 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
PLM - Rough/Topout  6/9/2018 10:19:52 AM  6/11/2018  12 PM - 3 PM  6/11/2018  MMO 
BLD - Floor Nailing  6/11/2018 2:30:34 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
BLD - 2nd Floor Shear Insp  6/11/2018 2:30:48 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
PLM - Gas Test  6/11/2018 2:31:46 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
PLM - Water Service  6/11/2018 2:32:12 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
BLD - Insulation Insp  6/11/2018 3:13:16 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
PLM - Penetrations Fire -Rated  6/11/2018 4:03:53 PM  6/12/2018  12 PM - 3 PM  6/12/2018  BIH 
PLM - Water Service  6/12/2018 3:49:27 PM  6/13/2018  12 PM - 3 PM  6/13/2018  BIH 
PLM - Gas Test  6/12/2018 3:50:37 PM  6/13/2018  12 PM - 3 PM  6/13/2018  BIH 
BLD - Insulation Insp  6/12/2018 3:54:31 PM  6/13/2018  12 PM - 3 PM  6/13/2018  BIH 
BLD - Penetrations -Fire Rated  6/12/2018 3:54:43 PM  6/13/2018  12 PM - 3 PM  6/13/2018  BIH 
BLD - 1st Floor Shear Insp  6/12/2018 3:55:18 PM  6/13/2018  12 PM - 3 PM  6/13/2018  BIH 
BLD - Floor Nailing  6/13/2018 2:32:21 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
BLD - 2nd Floor Shear Insp  6/13/2018 2:32:42 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
PLM - Gas Test  6/13/2018 2:34:14 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
PLM - Rough/Topout  6/13/2018 2:34:37 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
PLM -Temporary Gas  6/13/2018 2:35:10 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
BLD - Penetrations -Fire Rated  6/13/2018 2:35:45 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
PLM - Water Service  6/13/2018 2:36:21 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
BLD - Insulation Insp  6/13/2018 3:55:12 PM  6/14/2018  12 PM - 3 PM  6/14/2018  BIH 
PLM - Rough/Topout  6/14/2018 3:07:04 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
PLM - Water Service  6/14/2018 3:07:29 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
PLM - Gas Test  6/14/2018 3:08:33 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
BLD - Floor Nailing  6/14/2018 3:17:34 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
BLD - 2nd Floor Shear Insp  6/14/2018 3:27:23 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
BLD - Insulation Insp  6/14/2018 3:32:39 PM  6/15/2018  12 PM - 3 PM  6/15/2018  BIH 
PLM - Water Service  6/15/2018 2:29:40 PM  6/18/2018  12 PM - 3 PM  6/18/2018  BIH 
BLD - Floor Nailing  6/15/2018 2:30:30 PM  6/18/2018  12 PM - 3 PM  6/18/2018  BIH 
BLD - 2nd Floor Shear Insp  6/15/2018 2:30:56 PM  6/18/2018  12 PM - 3 PM  6/18/2018  BIH 
BLD - Insulation Insp  6/18/2018 3:42:13 PM  6/19/2018  12 PM - 3 PM  6/19/2018  BIH 
BLD - Penetrations -Fire Rated  6/18/2018 4:00:57 PM  6/19/2018  12 PM - 3 PM  6/19/2018  BIH 
BLD - Insulation Insp  6/19/2018 2:07:35 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
PLM - Water Service  6/19/2018 2:54:10 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
BLD - Drywall Inspection  6/19/2018 2:54:47 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
BLD - Floor Nailing  6/19/2018 2:55:55 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
BLD - 2nd Floor Shear Insp  6/19/2018 2:56:09 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
BLD - Reinforcing Insp  6/19/2018 3:01:25 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
BLD - Interior Lath  6/19/2018 3:55:28 PM  6/20/2018  10 AM - 2 PM  6/20/2018  BIH 
PLM - Rough/Topout  6/20/2018 3:21:44 PM  6/21/2018  8 AM - 12 PM  6/21/2018  BIH 
BLD - Reinforcing Insp  6/20/2018 3:26:20 PM  6/21/2018  8 AM - 12 PM  6/21/2018  BIH 
BLD - 1st Floor Shear Insp  6/20/2018 3:26:52 PM  6/21/2018  8 AM - 12 PM  6/21/2018  BIH 
BLD - Insulation Insp  6/20/2018 3:39:38 PM  6/21/2018  8 AM - 12 PM  6/21/2018  BIH 
BLD - Drywall Inspection  6/20/2018 3:40:26 PM  6/21/2018  8 AM - 12 PM  6/21/2018  BIH 
BLD - Insulation Insp  6/21/2018 1:33:42 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BIH 
BLD - Reinforcing Insp  6/21/2018 3:27:42 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BIH 
BLD - 1st Floor Shear Insp  6/21/2018 3:29:08 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BIH 
BLD - Drywall Inspection  6/21/2018 3:30:20 PM  6/22/2018  12 PM - 3 PM  6/22/2018  BIH 
PLM - Rough/Topout  6/22/2018 1:56:57 PM  6/25/2018  10 AM - 2 PM  6/25/2018  BIH 
BLD - Drywall Inspection  6/22/2018 1:57:21 PM  6/25/2018  10 AM - 2 PM  6/25/2018  BIH 
BLD - Floor Nailing  6/25/2018 1:15:23 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
BLD - 2nd Floor Shear Insp  6/25/2018 1:15:49 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
BLD - Insulation Insp  6/25/2018 1:16:18 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
BLD - Reinforcing Insp  6/25/2018 1:16:45 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
BLD - 1st Floor Shear Insp  6/25/2018 1:17:35 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
BLD - Drywall Inspection  6/25/2018 1:18:02 PM  6/26/2018  10 AM - 2 PM  6/26/2018  BIH 
PLM - Water Service  6/26/2018 1:01:00 PM  6/27/2018  10 AM - 2 PM  6/27/2018  BIH 
BLD - Insulation Insp  6/26/2018 2:06:06 PM  6/27/2018  10 AM - 2 PM  6/27/2018  BIH 
ELE - Rough Electrical  6/26/2018 2:06:42 PM  6/27/2018  10 AM - 2 PM  6/27/2018  BIH 
BLD - Drywall Inspection  6/27/2018 3:03:04 PM  6/28/2018  10 AM - 2 PM  6/28/2018  BIH 
BLD - Insulation Insp  6/28/2018 12:08:04 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
BLD - Framing Insp.  6/28/2018 12:08:20 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
BLD - Drywall Inspection  6/28/2018 12:08:48 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
ELE - Rough Electrical  6/28/2018 12:09:07 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
BLD - 1st Floor Shear Insp  6/28/2018 1:12:33 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
BLD - 2nd Floor Shear Insp  6/28/2018 1:13:06 PM  6/29/2018  12 PM - 3 PM  6/29/2018  BIH 
Route to Struct/Architectual  6/29/2018  7/18/2018    7/17/2018  APPR  BVD 
Apprv. by Struct/Architectural  6/29/2018      7/17/2018 6:02:53 AM  APPR  BVD 
BLD - Drywall Inspection  6/29/2018 3:39:41 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - 1st Floor Shear Insp  6/29/2018 3:39:52 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - 2nd Floor Shear Insp  6/29/2018 3:40:04 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
ELE - Rough Electrical  6/29/2018 3:40:42 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - Framing Insp.  6/29/2018 3:41:00 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - Insulation Insp  6/29/2018 3:41:08 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - 2nd Floor Nailing  6/29/2018 3:42:02 PM  7/2/2018  12 PM - 3 PM  7/2/2018  BIH 
BLD - 1st Floor Shear Insp  7/2/2018 3:45:50 PM  7/3/2018  10 AM - 2 PM  7/3/2018  BIH 
BLD - 2nd Floor Shear Insp  7/2/2018 3:46:02 PM  7/3/2018  10 AM - 2 PM  7/3/2018  BIH 
BLD - Drywall Inspection  7/2/2018 4:17:16 PM  7/3/2018  10 AM - 2 PM  7/3/2018  BIH 
ELE - Rough Electrical  7/2/2018 4:17:50 PM  7/3/2018  10 AM - 2 PM  7/3/2018  BIH 
BLD - Framing Insp.  7/3/2018  7/5/2018  10 AM - 2 PM  7/5/2018  BIH 
BLD - Drywall Inspection  7/3/2018 2:40:49 PM  7/5/2018  10 AM - 2 PM  7/5/2018  BIH 
BLD - Floor Nailing  7/3/2018 4:03:47 PM  7/5/2018  10 AM - 2 PM  7/5/2018  BIH 
BLD - 2nd Floor Shear Insp  7/3/2018 4:04:05 PM  7/5/2018  10 AM - 2 PM  7/5/2018  BIH 
ELE - Rough Electrical  7/5/2018  7/6/2018  8 AM - 12 PM  7/6/2018  BIH 
BLD - Floor Nailing  7/5/2018 2:27:16 PM  7/6/2018  8 AM - 12 PM  7/6/2018  BIH 
BLD - 2nd Floor Shear Insp  7/5/2018 2:27:45 PM  7/6/2018  8 AM - 12 PM  7/6/2018  BIH 
BLD - Insulation Insp  7/6/2018  7/9/2018  10 AM - 2 PM  7/9/2018  BIH 
BLD - Penetrations -Fire Rated  7/7/2018 12:14:27 PM  7/9/2018  10 AM - 2 PM  7/9/2018  BIH 
BLD - Floor Nailing  7/7/2018 12:15:27 PM  7/9/2018  10 AM - 2 PM  7/9/2018  BIH 
BLD - 2nd Floor Shear Insp  7/7/2018 12:15:45 PM  7/9/2018  10 AM - 2 PM  7/9/2018  BIH 
BLD - Drywall Inspection  7/9/2018 1:25:31 PM  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
BLD - 1st Floor Shear Insp  7/9/2018 1:27:01 PM  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
BLD - Floor Nailing  7/9/2018 1:27:59 PM  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
BLD - Insulation Insp  7/9/2018 1:30:04 PM  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
PLM - Rough/Topout  7/9/2018 1:54:10 PM  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
BLD - Framing Insp.  7/9/2018  7/10/2018  10 AM - 2 PM  7/10/2018  BIH 
BLD - 1st Floor Shear Insp  7/10/2018 3:17:53 PM  7/11/2018  10 AM - 2 PM  7/11/2018  BIH 
BLD - 2nd Floor Shear Insp  7/10/2018 3:18:26 PM  7/11/2018  10 AM - 2 PM  7/11/2018  BIH 
BLD - Insulation Insp  7/11/2018 9:32:48 AM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
PLM - Water Service  7/11/2018 9:33:54 AM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
BLD - Penetrations -Fire Rated  7/11/2018 9:34:56 AM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
BLD - Floor Nailing  7/11/2018 9:38:17 AM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
BLD - 2nd Floor Shear Insp  7/11/2018 9:38:52 AM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
PLM - Gas Test  7/11/2018 1:07:49 PM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
BLD - 1st Floor Shear Insp  7/11/2018 2:01:52 PM  7/12/2018  10 AM - 2 PM  7/12/2018  BIH 
BLD - Framing Insp.  7/12/2018  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
PLM - Rough/Topout  7/12/2018 2:46:05 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
BLD - 2nd Floor Nailing  7/12/2018 2:46:25 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
BLD - 2nd Floor Shear Insp  7/12/2018 2:46:39 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
BLD - Roof Sheathing Insp.  7/12/2018 2:47:09 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
BLD - Drywall Inspection  7/12/2018 2:48:17 PM  7/13/2018  12 PM - 3 PM  7/13/2018  BIH 
BLD - Framing Insp.  7/13/2018 9:11:40 AM  7/16/2018  8 AM - 12 PM  7/16/2018  BIH 
BLD - 1st Floor Shear Insp  7/13/2018 1:59:33 PM  7/16/2018  8 AM - 12 PM  7/16/2018  BIH 
BLD - 2nd Floor Shear Insp  7/13/2018 2:02:43 PM  7/16/2018  8 AM - 12 PM  7/16/2018  BIH 
BLD - Drywall Inspection  7/13/2018 2:08:32 PM  7/16/2018  8 AM - 12 PM  7/16/2018  BIH 
BLD - 1st Floor Shear Insp  7/16/2018 11:34:10 AM  7/17/2018  12 PM - 3 PM  7/17/2018  BIH 
BLD - Drywall Inspection  7/16/2018 11:36:15 AM  7/17/2018  12 PM - 3 PM  7/17/2018  BIH 
BLD - Reinforcing Insp  7/16/2018 4:09:31 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BIH 
PLM - Rough/Topout  7/16/2018 4:10:16 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BIH 
BLD - 2nd Floor Shear Insp  7/16/2018 4:10:50 PM  7/17/2018  12 PM - 3 PM  7/17/2018  BIH 
BLD - Framing Insp.  7/17/2018 2:26:22 PM  7/18/2018  10 AM - 2 PM  7/18/2018  BIH 
PLM - Underfloor Gas  7/17/2018 2:38:08 PM  7/18/2018  10 AM - 2 PM  7/18/2018  BIH 
BLD - 2nd Floor Nailing  7/17/2018 2:38:33 PM  7/18/2018  10 AM - 2 PM  7/18/2018  BIH 
BLD - 2nd Floor Shear Insp  7/17/2018 2:39:16 PM  7/18/2018  10 AM - 2 PM  7/18/2018  BIH 
BLD - Drywall Inspection  7/18/2018 7:46:06 AM  7/19/2018    7/19/2018  MMO 
Route to Struct/Architectual  7/18/2018  8/3/2018    7/31/2018  CORR  BVD 
PLM - Water Service  7/19/2018 2:44:51 PM  7/20/2018  10 AM - 2 PM  7/20/2018  BIH 
MEC - Rough Duct  7/19/2018 2:45:19 PM  7/20/2018  10 AM - 2 PM  7/20/2018  BIH 
BLD - Floor Nailing  7/19/2018 2:45:56 PM  7/20/2018  10 AM - 2 PM  7/20/2018  BIH 
BLD - 2nd Floor Shear Insp  7/19/2018 2:48:10 PM  7/20/2018  10 AM - 2 PM  7/20/2018  BIH 
BLD - Drywall Inspection  7/19/2018 3:01:12 PM  7/20/2018  10 AM - 2 PM  7/20/2018  BIH 
Apprv. by Struct/Architectural  7/20/2018      8/6/2018 5:38:09 AM  APPR  BVD 
Route to Struct/Architectual  7/20/2018  8/7/2018    8/6/2018  APPR  BVD 
BLD - Drywall Inspection  7/20/2018 3:15:41 PM  7/23/2018  8 AM - 12 PM  7/23/2018  BIH 
BLD - 2nd Floor Shear Insp  7/20/2018 3:16:14 PM  7/23/2018  8 AM - 12 PM  7/23/2018  BIH 
PLM - Water Service  7/20/2018 3:16:36 PM  7/23/2018  8 AM - 12 PM  7/23/2018  BIH 
MEC - Rough Duct  7/20/2018 3:17:02 PM  7/23/2018  8 AM - 12 PM  7/23/2018  BIH 
BLD - Floor Nailing  7/23/2018 2:43:05 PM  7/24/2018  12 PM - 3 PM  7/24/2018  BIH 
BLD - 2nd Floor Shear Insp  7/23/2018 2:43:17 PM  7/24/2018  12 PM - 3 PM  7/24/2018  BIH 
PLM - Water Service  7/23/2018 2:43:33 PM  7/24/2018  12 PM - 3 PM  7/24/2018  BIH 
BLD - Drywall Inspection  7/23/2018 2:44:00 PM  7/24/2018  12 PM - 3 PM  7/24/2018  BIH 
MEC - Rough Duct  7/23/2018 2:44:58 PM  7/24/2018  12 PM - 3 PM  7/24/2018  BIH 
BLD - Drywall Inspection  7/24/2018 6:53:08 AM  7/23/2018    8/24/2018  BIH 
ELE - Rough Electrical  7/24/2018 3:17:15 PM  7/25/2018  10 AM - 2 PM  7/25/2018  BIH 
BLD - Drywall Inspection  7/24/2018 3:17:43 PM  7/25/2018  10 AM - 2 PM  7/25/2018  BIH 
BLD - Floor Nailing  7/24/2018 3:18:20 PM  7/25/2018  10 AM - 2 PM  7/25/2018  BIH 
BLD - 2nd Floor Shear Insp  7/24/2018 3:18:44 PM  7/25/2018  10 AM - 2 PM  7/25/2018  BIH 
BLD - Drywall Inspection  7/25/2018 11:04:25 AM  7/26/2018  12 PM - 3 PM  7/27/2018  BIH 
ELE - Rough Electrical  7/25/2018 1:43:53 PM  7/26/2018  12 PM - 3 PM  7/26/2018  BIH 
BLD - 2nd Floor Nailing  7/25/2018 1:44:52 PM  7/26/2018  12 PM - 3 PM  7/26/2018  BIH 
BLD - Insulation Insp  7/25/2018 1:45:44 PM  7/26/2018  12 PM - 3 PM  7/26/2018  BIH 
BLD - 2nd Floor Shear Insp  7/26/2018 12:34:26 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BIH 
BLD - Roof Sheathing Insp.  7/26/2018 12:35:01 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BIH 
ELE - Rough Electrical  7/26/2018 12:35:29 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BIH 
BLD - Insulation Insp  7/26/2018 12:35:52 PM  7/27/2018  12 PM - 3 PM  7/27/2018  BIH 
BLD - Insulation Insp  7/27/2018 2:36:31 PM  7/30/2018  10 AM - 2 PM  7/30/2018  BIH 
ELE - Rough Electrical  7/27/2018 2:41:00 PM  7/30/2018  10 AM - 2 PM  7/30/2018  BIH 
BLD - Framing Insp.  7/27/2018 2:44:55 PM  7/30/2018  10 AM - 2 PM  7/30/2018  BIH 
BLD - Drywall Inspection  7/27/2018 2:50:28 PM  7/30/2018  10 AM - 2 PM  7/30/2018  BIH 
BLD - Floor Nailing  7/30/2018 4:04:24 PM  7/31/2018  10 AM - 2 PM  7/31/2018  BIH 
ELE - Rough Electrical  7/30/2018 4:07:05 PM  7/31/2018  10 AM - 2 PM  7/31/2018  BIH 
BLD - Insulation Insp  7/30/2018 4:09:46 PM  7/31/2018  10 AM - 2 PM  7/31/2018  BIH 
PLM - Gas Test  7/31/2018 2:04:18 PM  8/1/2018  10 AM - 2 PM  8/1/2018  BIH 
PLM - Water Service  7/31/2018 2:06:04 PM  8/1/2018  10 AM - 2 PM  8/1/2018  BIH 
BLD - Insulation Insp  7/31/2018 3:27:33 PM  8/1/2018  10 AM - 2 PM  8/1/2018  BIH 
PLM - Rough/Topout  7/31/2018 3:28:57 PM  8/1/2018  10 AM - 2 PM  8/1/2018  BIH 
ELE - Rough Electrical  7/31/2018 3:30:10 PM  8/1/2018  10 AM - 2 PM  8/1/2018  BIH 
BLD - Framing Insp.  8/1/2018 3:00:34 PM  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
ELE - Rough Electrical  8/1/2018 3:02:04 PM  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
BLD - 1st Floor Shear Insp  8/1/2018  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
BLD - 2nd Floor Shear Insp  8/1/2018  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
ELE - Rough Electrical  8/1/2018  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
PLM - Rough/Topout  8/1/2018 3:27:38 PM  8/2/2018  10 AM - 2 PM  8/2/2018  BIH 
BLD - Framing Insp.  8/2/2018 8:46:19 AM  8/3/2018  10 AM - 2 PM  8/3/2018  BIH 
ELE - Rough Electrical  8/2/2018 8:47:26 AM  8/3/2018  10 AM - 2 PM  8/3/2018  BIH 
BLD - Insulation Insp  8/2/2018 8:49:31 AM  8/3/2018  10 AM - 2 PM  8/3/2018  BIH 
BLD - 2nd Floor Shear Insp  8/2/2018 2:57:57 PM  8/3/2018  10 AM - 2 PM  8/3/2018  BIH 
ELE - Rough Electrical  8/4/2018 9:41:46 AM  8/6/2018  12 PM - 3 PM  8/6/2018  BIH 
PLM - Rough/Topout  8/4/2018 9:43:47 AM  8/6/2018  12 PM - 3 PM  8/6/2018  BIH 
BLD - Drywall Inspection  8/4/2018 9:46:07 AM  8/6/2018  12 PM - 3 PM  8/6/2018  BIH 
BLD - Insulation Insp  8/4/2018 9:47:12 AM  8/6/2018  12 PM - 3 PM  8/6/2018  BIH 
BLD - Insulation Insp  8/6/2018 5:12:12 PM  8/7/2018  12 PM - 3 PM  8/7/2018  BIH 
MEC - Rough Duct  8/6/2018 5:14:12 PM  8/7/2018  12 PM - 3 PM  8/7/2018  BIH 
BLD - Framing Insp.  8/7/2018 2:50:09 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BIH 
PLM - Water Service  8/7/2018 2:52:08 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BIH 
BLD - Drywall Inspection  8/7/2018 2:53:39 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BIH 
BLD - 2nd Floor Shear Insp  8/7/2018 2:55:57 PM  8/8/2018  10 AM - 2 PM  8/8/2018  BIH 
BLD - Drywall Inspection  8/9/2018 3:27:25 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BIH 
BLD - Penetrations -Fire Rated  8/9/2018 3:27:50 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BIH 
BLD - 2nd Floor Shear Insp  8/9/2018 3:29:22 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BIH 
PLM - Rough/Topout  8/9/2018 3:29:56 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BIH 
PLM - Gas Test  8/9/2018 3:30:20 PM  8/10/2018  12 PM - 3 PM  8/10/2018  BIH 
Route to Struct/Architectual  8/10/2018  8/28/2018    8/21/2018  APPR  BVD 
PLM - Rough/Topout  8/11/2018 9:01:50 AM  8/13/2018  12 PM - 3 PM  8/13/2018  BIH 
BLD - Drywall Inspection  8/11/2018 9:02:04 AM  8/13/2018  12 PM - 3 PM  8/13/2018  BIH 
PLM - Water Service  8/11/2018 9:02:27 AM  8/13/2018  12 PM - 3 PM  8/13/2018  BIH 
BLD - 2nd Floor Shear Insp  8/11/2018 9:03:06 AM  8/13/2018  12 PM - 3 PM  8/13/2018  BIH 
BLD - 1st Floor Shear Insp  8/14/2018  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
PLM - Gas Test  8/14/2018 3:23:50 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
PLM - Rough/Topout  8/14/2018 3:24:04 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
PLM - Water Service  8/14/2018 3:24:13 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
BLD - Insulation Insp  8/14/2018 3:24:28 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
BLD - Drywall Inspection  8/14/2018 3:24:38 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
ELE - Rough Electrical  8/14/2018 3:24:59 PM  8/15/2018  10 AM - 2 PM  8/15/2018  BIH 
BLD - Framing Insp.  8/15/2018 12:03:53 PM  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
BLD - Roof Sheathing Insp.  8/15/2018 12:08:30 PM  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
PLM - Rough/Topout  8/15/2018  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
ELE - Rough Electrical  8/15/2018 2:31:01 PM  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
BLD - Penetrations -Fire Rated  8/15/2018 2:32:28 PM  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
BLD - 2nd Floor Shear Insp  8/15/2018 2:32:55 PM  8/16/2018  10 AM - 2 PM  8/16/2018  BIH 
Apprv. by Struct/Architectural  8/10/2018      8/21/2018 8:54:57 AM  APPR  BVD 
BLD - Drywall Inspection  8/17/2018 12:40:56 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
BLD - 1st Floor Shear Insp  8/17/2018 12:41:17 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
PLM - Water Service  8/17/2018 12:41:37 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
PLM - Rough/Topout  8/17/2018 12:41:53 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
ELE - Rough Electrical  8/17/2018 12:42:13 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
PLM - Gas Test  8/17/2018 12:44:25 PM  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
BLD - Insulation Insp  8/17/2018  8/20/2018  12 PM - 3 PM  8/20/2018  BIH 
BLD - Framing Insp.  8/20/2018 10:35:33 AM  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
BLD - Insulation Insp  8/20/2018 10:36:45 AM  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
BLD - Drywall Inspection  8/20/2018 3:30:59 PM  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
PLM - Gas Test  8/20/2018 3:31:31 PM  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
PLM - Water Service  8/20/2018 3:31:45 PM  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
BLD - 1st Floor Shear Insp  8/20/2018  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
BLD - 2nd Floor Shear Insp  8/20/2018  8/21/2018  12 PM - 3 PM  8/21/2018  BIH 
ELE - Rough Electrical  8/21/2018 1:49:14 PM  8/22/2018  12 PM - 3 PM  8/22/2018  BIH 
BLD - 2nd Floor Shear Insp  8/21/2018 1:49:53 PM  8/22/2018  12 PM - 3 PM  8/22/2018  BIH 
BLD - Roof Sheathing Insp.  8/21/2018 2:51:50 PM  8/22/2018  12 PM - 3 PM  8/22/2018  BIH 
BLD - Drywall Inspection  8/22/2018 3:08:49 PM  8/23/2018  10 AM - 2 PM  8/23/2018  BIH 
BLD - 2nd Floor Shear Insp  8/22/2018 3:09:52 PM  8/23/2018  10 AM - 2 PM  8/23/2018  BIH 
ELE - Rough Electrical  8/22/2018 3:10:26 PM  8/23/2018  10 AM - 2 PM  8/23/2018  BIH 
ELE - Rough Electrical  8/22/2018  8/23/2018  10 AM - 2 PM  8/23/2018  BIH 
BLD - Insulation Insp  8/23/2018 2:38:53 PM  8/24/2018  12 PM - 3 PM  8/24/2018  BIH 
ELE - Rough Electrical  8/23/2018 2:39:37 PM  8/24/2018  12 PM - 3 PM  8/24/2018  BIH 
PLM - Underground gas  8/23/2018 2:41:46 PM  8/24/2018  12 PM - 3 PM  8/24/2018  BIH 
PLM - Water Service  8/23/2018 2:42:06 PM  8/24/2018  12 PM - 3 PM  8/24/2018  BIH 
BLD - 2nd Floor Shear Insp  8/24/2018 2:24:48 PM  8/27/2018  12 PM - 3 PM  8/27/2018  BIH 
BLD - Drywall Inspection  8/24/2018 2:25:00 PM  8/27/2018  12 PM - 3 PM  8/27/2018  BIH 
BLD - Roof Sheathing Insp.  8/24/2018 2:25:44 PM  8/27/2018  12 PM - 3 PM  8/27/2018  BIH 
ELE - Rough Electrical  8/24/2018 2:26:24 PM  8/27/2018  12 PM - 3 PM  8/27/2018  BIH 
BLD - 2nd Floor Nailing  8/27/2018 3:23:22 PM  8/28/2018  12 PM - 3 PM  8/28/2018  BIH 
BLD - Drywall Inspection  8/27/2018 3:23:41 PM  8/28/2018  12 PM - 3 PM  8/28/2018  BIH 
PLM - Rough/Topout  8/27/2018 3:24:34 PM  8/28/2018  12 PM - 3 PM  8/28/2018  BIH 
ELE - Rough Electrical  8/27/2018 3:25:19 PM  8/28/2018  12 PM - 3 PM  8/28/2018  BIH 
BLD - Insulation Insp  8/28/2018 2:00:00 PM  8/29/2018  10 AM - 2 PM  8/29/2018  BIH 
BLD - 2nd Floor Nailing  8/28/2018 2:00:23 PM  8/29/2018  10 AM - 2 PM  8/29/2018  BIH 
ELE - Rough Electrical  8/28/2018 2:00:57 PM  8/29/2018  10 AM - 2 PM  8/29/2018  BIH 
BLD - Drywall Inspection  8/28/2018 2:54:37 PM  8/29/2018  10 AM - 2 PM  8/29/2018  BIH 
ELE - Rough Electrical  8/29/2018  8/30/2018  12 PM - 3 PM  8/31/2018  BIH 
Route to Struct/Architectual  8/30/2018  9/18/2018    9/4/2018  CORR  BVD 
Apprv. by Struct/Architectural  8/30/2018      11/26/2018 12:52:49 PM  APPR  BVD 
BLD - Drywall Inspection  8/30/2018  8/31/2018  10 AM - 2 PM  8/31/2018  BIH 
PLM - Rough/Topout  8/30/2018  8/31/2018  10 AM - 2 PM  8/31/2018  BIH 
BLD - 2nd Floor Shear Insp  8/30/2018 9:16:39 PM  8/31/2018  10 AM - 2 PM  8/31/2018  BIH 
BLD - Roof Sheathing Insp.  8/30/2018 9:16:58 PM  8/31/2018  10 AM - 2 PM  8/31/2018  BIH 
BLD - Misc. Inspection  9/4/2018  9/5/2018  12 PM - 3 PM  9/5/2018  BIH 
BLD - 2nd Floor Shear Insp  9/4/2018 2:49:28 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BIH 
MEC - Rough Mechanical  9/4/2018 2:49:56 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BIH 
BLD - Drywall Inspection  9/4/2018 2:50:09 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BIH 
BLD - Insulation Insp  9/4/2018 2:53:22 PM  9/5/2018  12 PM - 3 PM  9/5/2018  BIH 
BLD - 2nd Floor Shear Insp  9/5/2018 2:02:30 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BIH 
BLD - Drywall Inspection  9/5/2018 2:02:46 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BIH 
MEC - Rough Duct  9/5/2018 2:03:03 PM  9/6/2018  12 PM - 3 PM  9/6/2018  BIH 
BLD - Insulation Insp  9/7/2018  9/10/2018  12 PM - 3 PM  9/10/2018  BIH 
BLD - Drywall Inspection  9/7/2018  9/10/2018  12 PM - 3 PM  9/10/2018  BIH 
BLD - 2nd Floor Shear Insp  9/7/2018  9/10/2018  12 PM - 3 PM  9/10/2018  BIH 
MEC - Rough Duct  9/7/2018  9/10/2018  12 PM - 3 PM  9/10/2018  BIH 
ELE - Rough Electrical  9/10/2018  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
MEC - Rough Mechanical  9/10/2018  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
MEC - Rough Duct  9/10/2018  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
PLM - Rough/Topout  9/10/2018  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
PLM - Gas Test  9/10/2018 10:23:58 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
PLM - Water Service  9/10/2018 10:24:19 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
BLD - Drywall Inspection  9/10/2018 10:24:49 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
BLD - Insulation Insp  9/10/2018 10:25:00 PM  9/11/2018  12 PM - 3 PM  9/11/2018  BIH 
BLD - Roof Sheathing Insp.  9/11/2018 10:32:34 PM  9/12/2018  10 AM - 2 PM  9/12/2018  BIH 
BLD - Insulation Insp  9/11/2018 10:32:52 PM  9/12/2018  10 AM - 2 PM  9/12/2018  BIH 
BLD - Drywall Inspection  9/11/2018 10:33:14 PM  9/12/2018  10 AM - 2 PM  9/12/2018  BIH 
ELE - Rough Electrical  9/11/2018 10:33:54 PM  9/12/2018  10 AM - 2 PM  9/12/2018  BIH 
PLM - Water Service  9/11/2018 10:35:36 PM  9/12/2018  10 AM - 2 PM  9/12/2018  BIH 
ELE - Rough Electrical  9/12/2018  9/19/2018    9/19/2018  BIH 
MEC - Rough Mechanical  9/12/2018  9/19/2018    9/19/2018  BIH 
PLM - Rough/Topout  9/12/2018  9/19/2018    9/19/2018  BIH 
ELE - Rough Electrical  9/12/2018  9/14/2018    9/14/2018  BIH 
MEC - Rough Mechanical  9/12/2018  9/14/2018    9/14/2018  BIH 
PLM - Rough/Topout  9/12/2018  9/14/2018    9/14/2018  BIH 
BLD - Insulation Insp  9/14/2018  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
ELE - Rough Electrical  9/14/2018  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
BLD - Roof Sheathing Insp.  9/14/2018  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
BLD - Roof Sheathing Insp.  9/16/2018 8:58:43 PM  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
PLM - Water Service  9/16/2018 8:59:08 PM  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
PLM - Rough/Topout  9/16/2018 8:59:22 PM  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
PLM - Gas Test  9/16/2018 8:59:42 PM  9/17/2018  12 PM - 3 PM  9/17/2018  BIH 
BLD - 2nd Floor Shear Insp  9/17/2018 1:14:56 PM  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
ELE - Rough Electrical  9/17/2018 1:16:23 PM  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
BLD - Drywall Inspection  9/17/2018 1:16:33 PM  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
PLM - Underfloor Gas  9/17/2018 3:11:32 PM  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
PLM - Water Service  9/17/2018 3:11:41 PM  9/18/2018  10 AM - 2 PM  9/18/2018  BIH 
ELE - Rough Electrical  9/19/2018  9/20/2018    9/20/2018  BIH 
MEC - Rough Mechanical  9/19/2018  9/20/2018    9/20/2018  BIH 
PLM - Rough/Topout  9/19/2018  9/20/2018    9/20/2018  BIH 
PLM - Rough/Topout  9/19/2018  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
MEC - Rough Mechanical  9/19/2018  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
ELE - Rough Electrical  9/19/2018  9/21/2018  12 PM - 3 PM  9/20/2018  BIH 
BLD - 2nd Floor Shear Insp  9/19/2018 9:13:45 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BIH 
PLM - Water Service  9/19/2018 9:14:30 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BIH 
PLM - Gas Test  9/19/2018 9:14:59 PM  9/20/2018  8 AM - 12 PM  9/20/2018  BIH 
PLM - Water Service  9/20/2018 12:53:57 PM  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
PLM - Gas Test  9/20/2018 12:54:11 PM  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
BLD - Insulation Insp  9/20/2018 12:54:20 PM  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
BLD - 2nd Floor Shear Insp  9/20/2018 12:54:30 PM  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
BLD - Drywall Inspection  9/20/2018 12:54:49 PM  9/21/2018  12 PM - 3 PM  9/21/2018  MMO 
ELE - Rough Electrical  9/21/2018  9/24/2018  12 PM - 3 PM  9/21/2018  MMO 
MEC - Rough Duct  9/21/2018  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
PLM - Rough/Topout  9/21/2018  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
BLD - 2nd Floor Shear Insp  9/23/2018 9:52:36 PM  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
BLD - Insulation Insp  9/23/2018 9:52:56 PM  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
BLD - Drywall Inspection  9/23/2018 9:53:10 PM  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
ELE - Rough Electrical  9/23/2018 9:54:05 PM  9/24/2018  12 PM - 3 PM  9/24/2018  BIH 
BLD - 2nd Floor Shear Insp  9/24/2018 8:37:06 PM  9/25/2018  10 AM - 2 PM  9/25/2018  BIH 
BLD - Drywall Inspection  9/24/2018 8:37:22 PM  9/25/2018  10 AM - 2 PM  9/25/2018  BIH 
BLD - Insulation Insp  9/24/2018 8:37:31 PM  9/25/2018  10 AM - 2 PM  9/25/2018  BIH 
ELE - Rough Electrical  9/24/2018 8:37:56 PM  9/25/2018  10 AM - 2 PM  9/25/2018  BIH 
PLM - Rough/Topout  9/24/2018 8:38:10 PM  9/25/2018  10 AM - 2 PM  9/25/2018  BIH 
BLD - Insulation Insp  9/25/2018  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
BLD - Drywall Inspection  9/25/2018  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
ELE - Rough Electrical  9/25/2018  9/26/2018  8 AM - 12 PM  9/28/2018  BIH 
MEC - Rough Mechanical  9/25/2018  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
PLM - Rough/Topout  9/25/2018  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
BLD - 2nd Floor Shear Insp  9/25/2018 2:18:10 PM  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
PLM - Water Service  9/25/2018 2:19:00 PM  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
BLD - Roof Sheathing Insp.  9/25/2018 2:19:11 PM  9/26/2018  8 AM - 12 PM  9/26/2018  BIH 
BLD - Drywall Inspection  9/26/2018 10:43:07 PM  9/27/2018    9/27/2018  MMO 
BLD - Insulation Insp  9/26/2018 10:43:31 PM  9/27/2018    9/27/2018  MMO 
ELE - Rough Electrical  9/27/2018  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
MEC - Rough Mechanical  9/27/2018  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
PLM - Rough/Topout  9/27/2018  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
BLD - Insulation Insp  9/27/2018  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
BLD - Drywall Inspection  9/27/2018  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
ELE - Rough Electrical  9/27/2018  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
MEC - Rough Mechanical  9/27/2018  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
PLM - Rough/Topout  9/27/2018  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
BLD - 2nd Floor Shear Insp  9/27/2018 9:14:06 PM  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
BLD - Drywall Inspection  9/27/2018 9:14:37 PM  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
PLM - Water Service  9/27/2018 9:15:12 PM  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
PLM - Gas Test  9/27/2018 9:15:51 PM  9/28/2018  8 AM - 12 PM  9/28/2018  BIH 
BLD - 2nd Floor Shear Insp  9/30/2018 8:41:26 PM  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
MEC - Underground Duct  9/30/2018 8:42:25 PM  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
ELE - Penetrations- Fire Rated  9/30/2018 8:42:54 PM  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
BLD - Underfloor Insulation   9/30/2018 8:43:12 PM  10/1/2018  12 PM - 3 PM  10/1/2018  BIH 
ELE - Rough Electrical  10/1/2018  10/2/2018    10/2/2018  BIH 
MEC - Rough Mechanical  10/1/2018  10/2/2018    10/2/2018  BIH 
PLM - Rough/Topout  10/1/2018  10/2/2018    10/2/2018  BIH 
ELE - Rough Electrical  10/2/2018  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
ELE - Rough Electrical  10/2/2018  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
MEC - Rough Mechanical  10/2/2018  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
MEC - Rough Mechanical  10/2/2018  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
PLM - Rough/Topout  10/2/2018  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
PLM - Rough/Topout  10/2/2018  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
ELE - Temporary Power  10/3/2018 1:39:01 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
PLM - Water Service  10/3/2018 1:40:02 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
PLM - Gas Test  10/3/2018 1:40:21 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
PLM - Penetrations Fire -Rated  10/3/2018 1:41:26 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
BLD - 2nd Floor Shear Insp  10/3/2018 1:41:55 PM  10/4/2018  8 AM - 12 PM  10/4/2018  BIH 
ELE - Rough Electrical  10/4/2018  10/8/2018  12 PM - 3 PM  10/8/2018  BIH 
ELE - Rough Electrical  10/4/2018  10/9/2018  10 AM - 2 PM  10/9/2018  BIH 
MEC - Rough Mechanical  10/4/2018  10/8/2018  12 PM - 3 PM  10/8/2018  BIH 
MEC - Rough Mechanical  10/4/2018  10/9/2018  10 AM - 2 PM  10/10/2018  BIH 
PLM - Rough/Topout  10/4/2018  10/8/2018  12 PM - 3 PM  10/8/2018  BIH 
PLM - Rough/Topout  10/4/2018  10/9/2018  10 AM - 2 PM  10/10/2018  BIH 
PLM - Water Service  10/4/2018 9:28:52 PM  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
PLM - Sewer  10/4/2018 9:29:21 PM  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
PLM - Gas Test  10/4/2018 9:29:39 PM  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
ELE - Temporary Power  10/4/2018 9:29:55 PM  10/5/2018  12 PM - 3 PM  10/5/2018  BIH 
ELE - Rough Electrical  10/5/2018  10/10/2018  10 AM - 2 PM  10/10/2018  BIH 
ELE - Rough Electrical  10/5/2018  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
MEC - Rough Mechanical  10/5/2018  10/10/2018  10 AM - 2 PM  10/10/2018  BIH 
MEC - Rough Mechanical  10/5/2018  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
PLM - Rough/Topout  10/5/2018  10/10/2018  10 AM - 2 PM  10/10/2018  BIH 
PLM - Rough/Topout  10/5/2018  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
BLD - Exterior Lath Insp  10/7/2018 8:46:35 PM  10/8/2018  12 PM - 3 PM  10/8/2018  BIH 
BLD - 2nd Floor Shear Insp  10/7/2018 8:47:43 PM  10/8/2018  12 PM - 3 PM  10/8/2018  BIH 
BLD - Drywall Inspection  10/8/2018 11:51:49 AM  10/9/2018  10 AM - 2 PM  10/9/2018  BIH 
BLD - 1st Floor Shear Insp  10/8/2018 11:52:06 AM  10/9/2018  10 AM - 2 PM  10/9/2018  BIH 
BLD - Drywall Inspection  10/10/2018 11:36:11 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
BLD - 1st Floor Shear Insp  10/10/2018 11:36:27 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
BLD - Insulation Insp  10/10/2018 11:36:43 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
PLM - Water Service  10/10/2018 11:36:57 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
PLM - Gas Test  10/10/2018 11:37:12 PM  10/11/2018  8 AM - 12 PM  10/11/2018  BIH 
ELE - Penetrations- Fire Rated  10/11/2018 12:25:31 PM  10/12/2018  8 AM - 12 PM  10/12/2018  BIH 
MEC - Rough Duct  10/11/2018 12:26:08 PM  10/12/2018  8 AM - 12 PM  10/12/2018  BIH 
BLD - Drywall Inspection  10/11/2018 12:26:32 PM  10/12/2018  8 AM - 12 PM  10/12/2018  BIH 
PLM - Rough/Topout  10/11/2018 12:26:49 PM  10/12/2018  8 AM - 12 PM  10/12/2018  BIH 
PLM - Penetrations Fire -Rated  10/11/2018 12:27:56 PM  10/12/2018  8 AM - 12 PM  10/12/2018  BIH 
BLD - Roof Sheathing Insp.  10/14/2018 8:15:13 PM  10/15/2018  10 AM - 2 PM  10/15/2018  BIH 
BLD - Drywall Inspection  10/14/2018 8:15:44 PM  10/15/2018  10 AM - 2 PM  10/15/2018  BIH 
PLM - Water Service  10/14/2018 8:16:05 PM  10/15/2018  10 AM - 2 PM  10/15/2018  BIH 
PLM - Rough/Topout  10/14/2018 8:16:16 PM  10/15/2018  10 AM - 2 PM  10/15/2018  BIH 
PLM - Misc. Inspection  10/15/2018  10/17/2018    10/18/2018  BIH 
BLD - Roof Sheathing Insp.  10/16/2018 11:26:42 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BIH 
BLD - 2nd Floor Shear Insp  10/16/2018 11:27:07 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BIH 
BLD - Drywall Inspection  10/16/2018 11:27:38 AM  10/17/2018  12 PM - 3 PM  10/17/2018  BIH 
BLD - Drywall Inspection  10/17/2018  10/22/2018    10/22/2018  JOS 
BLD - Drywall Inspection  10/17/2018  10/23/2018    10/24/2018  BIH 
PLM - Rough/Topout  10/17/2018 6:46:45 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BIH 
PLM - Water Service  10/17/2018 6:47:15 PM  10/18/2018  8 AM - 12 PM  10/18/2018  BIH 
BLD - Drywall Inspection  10/18/2018  10/29/2018  8 AM - 12 PM  10/29/2018  JOS 
BLD - Drywall Inspection  10/18/2018  10/30/2018  10 AM - 2 PM  10/30/2018  BIH 
BLD - Drywall Inspection  10/18/2018  10/31/2018  8 AM - 12 PM  10/31/2018  JOS 
BLD - Drywall Inspection  10/18/2018  11/2/2018  8 AM - 12 PM  11/2/2018  JOS 
BLD - 2nd Floor Shear Insp  10/18/2018 8:59:23 PM  10/19/2018  12 PM - 3 PM  10/19/2018  BIH 
PLM - Rough/Topout  10/18/2018 8:59:49 PM  10/19/2018  12 PM - 3 PM  10/19/2018  BIH 
PLM - Water Service  10/18/2018 9:00:08 PM  10/19/2018  12 PM - 3 PM  10/19/2018  BIH 
BLD - Roof Sheathing Insp.  10/18/2018 9:00:48 PM  10/19/2018  12 PM - 3 PM  10/19/2018  BIH 
BLD - Roof Sheathing Insp.  10/21/2018 10:00:26 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
PLM - Rough/Topout  10/21/2018 10:01:27 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
PLM - Water Service  10/21/2018 10:01:44 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
PLM - Gas Test  10/21/2018 10:02:02 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
ELE - Rough Electrical  10/21/2018 10:02:17 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
BLD - Insulation Insp  10/21/2018 10:02:43 PM  10/22/2018  12 PM - 3 PM  10/22/2018  BIH 
Apprv. by Struct/Architectural  10/23/2018      12/11/2018 8:46:04 AM  APPR  BVD 
Route to Struct/Architectual  10/23/2018  11/8/2018    11/6/2018  APPR  BVD 
BLD - Roof Sheathing Insp.  10/23/2018 2:27:10 PM  10/24/2018  12 PM - 3 PM  10/24/2018  BIH 
BLD - Insulation Insp  10/23/2018 2:27:34 PM  10/24/2018  12 PM - 3 PM  10/24/2018  BIH 
ELE - Rough Electrical  10/23/2018 2:27:46 PM  10/24/2018  12 PM - 3 PM  10/24/2018  BIH 
ELE - Rough Electrical  10/24/2018  10/25/2018    10/26/2018  JOS 
MEC - Rough Mechanical  10/24/2018  10/25/2018    10/26/2018  JOS 
PLM - Rough/Topout  10/24/2018  10/25/2018    10/26/2018  JOS 
ELE - Rough Electrical  10/24/2018  11/7/2018    11/7/2018  BIH 
ELE - Rough Electrical  10/24/2018  11/8/2018  8 AM - 12 PM  11/8/2018  JOS 
ELE - Rough Electrical  10/24/2018  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
ELE - Rough Electrical  10/24/2018  11/16/2018  8 AM - 12 PM  11/16/2018  JOS 
ELE - Rough Electrical  10/24/2018  11/21/2018    11/21/2018  JOS 
ELE - Rough Electrical  10/24/2018  11/26/2018    11/26/2018  BIH 
ELE - Rough Electrical  10/24/2018  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
MEC - Rough Mechanical  10/24/2018  11/7/2018    11/7/2018  BIH 
MEC - Rough Mechanical  10/24/2018  11/8/2018  8 AM - 12 PM  11/8/2018  JOS 
MEC - Rough Mechanical  10/24/2018  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
MEC - Rough Mechanical  10/24/2018  11/16/2018  8 AM - 12 PM  11/16/2018  JOS 
MEC - Rough Mechanical  10/24/2018  11/21/2018    11/21/2018  JOS 
MEC - Rough Mechanical  10/24/2018  11/26/2018    11/26/2018  BIH 
MEC - Rough Mechanical  10/24/2018  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
PLM - Rough/Topout  10/24/2018  11/7/2018    11/7/2018  BIH 
PLM - Rough/Topout  10/24/2018  11/8/2018  8 AM - 12 PM  11/8/2018  JOS 
PLM - Rough/Topout  10/24/2018  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
PLM - Rough/Topout  10/24/2018  11/16/2018  8 AM - 12 PM  11/16/2018  JOS 
PLM - Rough/Topout  10/24/2018  11/21/2018    11/21/2018  JOS 
PLM - Rough/Topout  10/24/2018  11/26/2018    11/26/2018  BIH 
PLM - Rough/Topout  10/24/2018  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
BLD - Insulation Insp  10/24/2018 1:44:27 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BIH 
BLD - Drywall Inspection  10/24/2018 1:44:48 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BIH 
ELE - Penetrations- Fire Rated  10/24/2018 1:45:50 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BIH 
PLM - Penetrations Fire -Rated  10/24/2018 1:46:00 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BIH 
MEC - Penetrations- Fire Rated  10/24/2018 1:46:13 PM  10/25/2018  8 AM - 12 PM  10/25/2018  BIH 
BLD - Exterior Lath Insp  10/28/2018 10:25:28 PM  10/29/2018  10 AM - 2 PM  10/29/2018  BIH 
BLD - Exterior Brown Coat Insp  10/28/2018 10:26:10 PM  10/29/2018  10 AM - 2 PM  10/29/2018  BIH 
BLD - 2nd Floor Shear Insp  10/29/2018 10:04:57 PM  10/30/2018  10 AM - 2 PM  10/30/2018  BIH 
ELE - Penetrations- Fire Rated  10/29/2018 10:05:12 PM  10/30/2018  10 AM - 2 PM  10/30/2018  BIH 
PLM - Rough/Topout  10/29/2018 10:05:41 PM  10/30/2018  10 AM - 2 PM  10/30/2018  BIH 
PLM - Penetrations Fire -Rated  10/30/2018 9:51:44 PM  10/31/2018  10 AM - 2 PM  10/31/2018  BIH 
ELE - Penetrations- Fire Rated  10/30/2018 9:52:01 PM  10/31/2018  10 AM - 2 PM  10/31/2018  BIH 
ELE - Rough Electrical  10/30/2018 9:52:30 PM  10/31/2018  10 AM - 2 PM  10/31/2018  BIH 
MEC - Penetrations- Fire Rated  10/30/2018 9:53:12 PM  10/31/2018  10 AM - 2 PM  10/31/2018  BIH 
BLD - 2nd Floor Shear Insp  10/30/2018 9:54:13 PM  10/31/2018  10 AM - 2 PM  10/31/2018  BIH 
BLD - 2nd Floor Shear Insp  10/31/2018 3:28:55 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BIH 
BLD - Drywall Inspection  10/31/2018 3:29:32 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BIH 
PLM - Penetrations Fire -Rated  10/31/2018 3:29:54 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BIH 
ELE - Penetrations- Fire Rated  10/31/2018 3:30:04 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BIH 
MEC - Penetrations- Fire Rated  10/31/2018 3:30:15 PM  11/1/2018  8 AM - 12 PM  11/1/2018  BIH 
PLM - Rough/Topout  10/31/2018  10/31/2018    10/31/2018  JOS 
PLM - Rough/Topout  10/31/2018  10/31/2018    10/31/2018  JOS 
BLD - 2nd Floor Shear Insp  11/1/2018 10:00:16 PM  11/2/2018  10 AM - 2 PM  11/2/2018  BIH 
BLD - Penetrations -Fire Rated  11/1/2018 10:00:58 PM  11/2/2018  10 AM - 2 PM  11/2/2018  BIH 
BLD - 2nd Floor Shear Insp  11/4/2018 6:19:19 PM  11/5/2018  10 AM - 2 PM  11/5/2018  BIH 
BLD - Drywall Inspection  11/4/2018 6:19:52 PM  11/5/2018  10 AM - 2 PM  11/5/2018  BIH 
ELE - Rough Electrical  11/4/2018 6:20:15 PM  11/5/2018  10 AM - 2 PM  11/5/2018  BIH 
MEC - Rough Mechanical  11/4/2018 6:20:35 PM  11/5/2018  10 AM - 2 PM  11/5/2018  BIH 
ELE - Rough Electrical  11/5/2018 10:23:55 PM  11/6/2018  8 AM - 12 PM  11/6/2018  BIH 
MEC - Rough Duct  11/5/2018 10:24:19 PM  11/6/2018  8 AM - 12 PM  11/6/2018  BIH 
BLD - Drywall Inspection  11/5/2018 10:24:35 PM  11/6/2018  8 AM - 12 PM  11/6/2018  BIH 
ELE - Rough Electrical  11/6/2018  11/17/2018  8 AM - 12 PM  11/19/2018  BIH 
MEC - Rough Mechanical  11/6/2018  11/17/2018  8 AM - 12 PM  11/19/2018  BIH 
PLM - Rough/Topout  11/6/2018  11/17/2018  8 AM - 12 PM  11/19/2018  BIH 
BLD - Exterior Lath Insp  11/8/2018 1:05:55 PM  11/9/2018    11/8/2018  GGO 
BLD - Drywall Inspection  11/8/2018 1:06:38 PM  11/9/2018    11/8/2018  GGO 
BLD - Insulation Insp  11/8/2018 1:07:13 PM  11/9/2018    11/8/2018  GGO 
BLD - 2nd Floor Shear Insp  11/8/2018 1:07:46 PM  11/9/2018    11/8/2018  GGO 
ELE - Rough Electrical  11/8/2018 1:08:23 PM  11/9/2018    11/8/2018  GGO 
MEC - Rough Duct  11/8/2018 1:08:59 PM  11/9/2018    11/8/2018  GGO 
BLD - Penetrations -Fire Rated  11/8/2018  11/9/2018    11/8/2018  GGO 
BLD - Exterior Brown Coat Insp  11/12/2018 7:54:40 AM  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
PLM - Ground/Underfloor waste  11/12/2018 7:56:41 AM  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
PLM - Gas Test  11/12/2018 7:56:52 AM  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
PLM - Water Service  11/12/2018 7:57:11 AM  11/14/2018  12 PM - 3 PM  11/14/2018  BIH 
PLM - Water Service  11/14/2018 10:34:39 PM  11/15/2018  8 AM - 12 PM  11/15/2018  BIH 
PLM - Penetrations Fire -Rated  11/14/2018 10:35:12 PM  11/15/2018  8 AM - 12 PM  11/15/2018  BIH 
ELE - Penetrations- Fire Rated  11/14/2018 10:35:39 PM  11/15/2018  8 AM - 12 PM  11/15/2018  BIH 
MEC - Penetrations- Fire Rated  11/14/2018 10:36:07 PM  11/15/2018  8 AM - 12 PM  11/15/2018  BIH 
Apprv. by Struct/Architectural  11/15/2018      1/10/2019  APPR  BVD 
Route to Struct/Architectual  11/15/2018  12/5/2018    11/29/2018  CORR  BVD 
BLD - Underfloor Insulation   11/15/2018 10:03:11 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BIH 
ELE - Penetrations- Fire Rated  11/15/2018 10:04:00 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BIH 
PLM - Water Service  11/15/2018 10:04:44 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BIH 
PLM - Penetrations Fire -Rated  11/15/2018 10:05:17 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BIH 
MEC - Fire Dampers  11/15/2018 10:05:39 PM  11/16/2018  8 AM - 12 PM  11/16/2018  BIH 
Route to Struct/Architectual  11/16/2018  12/6/2018    11/26/2018  APPR  BVD 
BLD - Exterior Lath Insp  11/19/2018 12:50:20 PM  11/20/2018  12 PM - 3 PM  11/20/2018  BIH 
PLM - Water Service  11/19/2018 12:51:09 PM  11/20/2018  12 PM - 3 PM  11/20/2018  BIH 
PLM - Rough/Topout  11/19/2018 12:51:19 PM  11/20/2018  12 PM - 3 PM  11/20/2018  BIH 
PLM - Gas Test  11/19/2018 12:53:08 PM  11/20/2018  12 PM - 3 PM  11/20/2018  BIH 
BLD - Insulation Insp  11/19/2018 9:38:25 PM  11/20/2018  12 PM - 3 PM  11/20/2018  BIH 
Route to Struct/Architectual  11/26/2018  12/12/2018    12/11/2018  APPR  BVD 
PLM - Penetrations Fire -Rated  11/26/2018 4:20:12 PM  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
ELE - Penetrations- Fire Rated  11/26/2018 4:20:34 PM  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
MEC - Fire Dampers  11/26/2018 4:20:54 PM  11/27/2018  12 PM - 3 PM  11/27/2018  BIH 
BLD - Exterior Lath Insp  11/26/2018 4:21:28 PM  11/28/2018  10 AM - 2 PM  11/28/2018  BIH 
BLD - Exterior Brown Coat Insp  11/26/2018 4:21:52 PM  11/28/2018  10 AM - 2 PM  11/28/2018  BIH 
PLM - Rough/Topout  11/29/2018  11/30/2018    11/30/2018  JOS 
BLD - Insulation Insp  11/29/2018 9:41:43 PM  11/30/2018  8 AM - 12 PM  11/30/2018  BIH 
BLD - Drywall Inspection  11/29/2018 9:42:09 PM  11/30/2018  8 AM - 12 PM  11/30/2018  BIH 
ELE - Rough Electrical  11/29/2018 9:43:08 PM  11/30/2018  8 AM - 12 PM  11/30/2018  BIH 
MEC - Rough Duct  11/29/2018 9:43:30 PM  11/30/2018  8 AM - 12 PM  11/30/2018  BIH 
BLD - 2nd Floor Shear Insp  12/2/2018 9:05:37 PM  12/3/2018  8 AM - 12 PM  12/3/2018  BIH 
ELE - Rough Electrical  12/2/2018 9:06:06 PM  12/3/2018  8 AM - 12 PM  12/3/2018  BIH 
PLM - Penetrations Fire -Rated  12/3/2018 1:21:09 PM  12/4/2018  10 AM - 2 PM  12/4/2018  BIH 
ELE - Penetrations- Fire Rated  12/3/2018 1:21:27 PM  12/4/2018  10 AM - 2 PM  12/4/2018  BIH 
MEC - Penetrations- Fire Rated  12/3/2018 1:21:39 PM  12/4/2018  10 AM - 2 PM  12/4/2018  BIH 
ELE - Rough Electrical  12/4/2018  12/5/2018    12/5/2018  BIH 
ELE - Rough Electrical  12/4/2018  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
MEC - Rough Mechanical  12/4/2018  12/5/2018    12/5/2018  BIH 
MEC - Rough Mechanical  12/4/2018  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
PLM - Rough/Topout  12/4/2018  12/5/2018    12/5/2018  BIH 
PLM - Rough/Topout  12/4/2018  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
Route to Fire Department  12/5/2018  12/21/2018    12/31/2018  APPR  EPO 
Approved by Fire Department  12/5/2018      12/31/2018 7:34:27 AM  APPR  EPO 
BLD - Drywall Inspection  12/5/2018 10:20:23 PM  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
BLD - Insulation Insp  12/5/2018 10:20:58 PM  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
ELE - Penetrations- Fire Rated  12/5/2018 10:21:30 PM  12/6/2018  8 AM - 12 PM  12/6/2018  JOS 
ELE - Rough Electrical  12/6/2018  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
ELE - Rough Electrical  12/6/2018  12/13/2018  8 AM - 12 PM  12/13/2018  JOS 
ELE - Rough Electrical  12/6/2018  12/14/2018  8 AM - 12 PM  12/14/2018  BIH 
ELE - Rough Electrical  12/6/2018  12/19/2018    12/19/2018  JOS 
ELE - Rough Electrical  12/6/2018  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
ELE - Rough Electrical  12/6/2018  12/26/2018  8 AM - 12 PM  12/26/2018  BIH 
ELE - Rough Electrical  12/6/2018  12/27/2018  10 AM - 2 PM  12/27/2018  BIH 
ELE - Rough Electrical  12/6/2018  12/28/2018    12/28/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/13/2018  8 AM - 12 PM  12/13/2018  JOS 
MEC - Rough Mechanical  12/6/2018  12/14/2018  8 AM - 12 PM  12/14/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/19/2018    12/19/2018  JOS 
MEC - Rough Mechanical  12/6/2018  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/26/2018  8 AM - 12 PM  12/26/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/27/2018  10 AM - 2 PM  12/27/2018  BIH 
MEC - Rough Mechanical  12/6/2018  12/28/2018    12/28/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/13/2018  8 AM - 12 PM  12/13/2018  JOS 
PLM - Rough/Topout  12/6/2018  12/14/2018  8 AM - 12 PM  12/14/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/19/2018    12/19/2018  JOS 
PLM - Rough/Topout  12/6/2018  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/26/2018  8 AM - 12 PM  12/26/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/27/2018  10 AM - 2 PM  12/31/2018  BIH 
PLM - Rough/Topout  12/6/2018  12/28/2018    12/28/2018  BIH 
ELE - Electrical Service/Meter  12/6/2018 8:43:56 PM  12/7/2018  8 AM - 12 PM  12/7/2018  BIH 
BLD - Temp Elec Consideration  12/10/2018  12/11/2018  10 AM - 2 PM  12/11/2018  BIH 
ELE - Penetrations- Fire Rated  12/10/2018 8:55:01 PM  12/11/2018  10 AM - 2 PM  12/11/2018  BIH 
PLM - Penetrations Fire -Rated  12/10/2018 8:55:20 PM  12/11/2018  10 AM - 2 PM  12/11/2018  BIH 
MEC - Penetrations- Fire Rated  12/10/2018 8:55:35 PM  12/11/2018  10 AM - 2 PM  12/11/2018  BIH 
BLD - Drywall Inspection  12/11/2018  12/15/2018  8 AM - 12 PM  12/18/2018  BIH 
BLD - Interior Lath  12/11/2018  12/15/2018  8 AM - 12 PM  12/18/2018  BIH 
BLD - Exterior Brown Coat Insp  12/11/2018  12/15/2018  8 AM - 12 PM  12/18/2018  BIH 
BLD - Exterior Lath Insp  12/11/2018  12/15/2018  8 AM - 12 PM  12/18/2018  BIH 
ELE - Rough Electrical  12/11/2018  12/15/2018  8 AM - 12 PM  12/18/2018  BIH 
BLD - Insulation Insp  12/11/2018 10:12:37 PM  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
ELE - Penetrations- Fire Rated  12/11/2018 10:12:56 PM  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
MEC - Penetrations- Fire Rated  12/11/2018 10:13:10 PM  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
MEC - Fire Dampers  12/11/2018 10:14:00 PM  12/12/2018  10 AM - 2 PM  12/12/2018  BIH 
BLD - Drywall Inspection  12/12/2018  12/22/2018  8 AM - 12 PM  12/24/2018  BIH 
BLD - Interior Lath  12/12/2018  12/22/2018  8 AM - 12 PM  12/24/2018  BIH 
BLD - Exterior Lath Insp  12/12/2018  12/22/2018  8 AM - 12 PM  12/24/2018  BIH 
BLD - Exterior Brown Coat Insp  12/12/2018  12/22/2018  8 AM - 12 PM  12/24/2018  BIH 
ELE - Rough Electrical  12/12/2018  12/22/2018  8 AM - 12 PM  12/24/2018  BIH 
BLD - Insulation Insp  12/17/2018 2:06:40 PM  12/18/2018  10 AM - 2 PM  12/18/2018  BIH 
BLD - Drywall Inspection  12/17/2018 2:08:07 PM  12/18/2018  10 AM - 2 PM  12/18/2018  BIH 
BLD - 2nd Floor Shear Insp  12/17/2018 2:20:54 PM  12/18/2018  10 AM - 2 PM  12/18/2018  BIH 
ELE - Electrical Service/Meter  12/18/2018  12/18/2018  8 AM - 12 PM  12/18/2018  BIH 
PLM - Penetrations Fire -Rated  12/18/2018 9:31:09 PM  12/19/2018  8 AM - 12 PM  12/19/2018  BIH 
ELE - Penetrations- Fire Rated  12/18/2018 9:31:56 PM  12/19/2018  8 AM - 12 PM  12/19/2018  BIH 
ELE - T-Bar Electrical  12/18/2018 9:32:31 PM  12/19/2018  8 AM - 12 PM  12/19/2018  BIH 
PLM - Penetrations Fire -Rated  12/19/2018 10:04:15 PM  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
ELE - Penetrations- Fire Rated  12/19/2018 10:04:30 PM  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
MEC - Penetrations- Fire Rated  12/19/2018 10:04:46 PM  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
BLD - Insulation Insp  12/19/2018 10:05:33 PM  12/20/2018  10 AM - 2 PM  12/20/2018  BIH 
BLD - Insulation Insp  12/20/2018 8:11:39 PM  12/21/2018  10 AM - 2 PM  12/21/2018  BIH 
BLD - Exterior Brown Coat Insp  12/20/2018 8:12:07 PM  12/21/2018  10 AM - 2 PM  12/21/2018  BIH 
BLD - 2nd Floor Shear Insp  12/20/2018 8:12:41 PM  12/21/2018  10 AM - 2 PM  12/21/2018  BIH 
ELE - Penetrations- Fire Rated  12/25/2018 9:56:48 PM  12/26/2018  8 AM - 12 PM  12/26/2018  BIH 
MEC - Penetrations- Fire Rated  12/26/2018 10:01:50 PM  12/27/2018  10 AM - 2 PM  12/27/2018  BIH 
BLD - Drywall Inspection  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
BLD - Drywall Inspection  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
BLD - Interior Lath  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
BLD - Interior Lath  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
BLD - Exterior Lath Insp  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
BLD - Exterior Lath Insp  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
BLD - Exterior Brown Coat Insp  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
BLD - Exterior Brown Coat Insp  12/27/2018  1/2/2019  10 AM - 2 PM  1/4/2019  BIH 
ELE - Rough Electrical  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
ELE - Rough Electrical  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
MEC - Rough Mechanical  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
MEC - Rough Mechanical  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
PLM - Rough/Topout  12/27/2018  12/29/2018  8 AM - 12 PM  12/31/2018  BIH 
PLM - Rough/Topout  12/27/2018  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
PLM - Underground gas  12/27/2018 9:43:38 PM  12/28/2018    12/28/2018  BIH 
ELE - Penetrations- Fire Rated  12/27/2018 9:44:33 PM  12/28/2018    12/28/2018  BIH 
Inspection by Fire Department  12/31/2018  1/17/2019    10/3/2019  DONE  MGA 
ELE - Penetrations- Fire Rated  1/1/2019 6:45:19 PM  1/2/2019  10 AM - 2 PM  1/2/2019  BIH 
BLD - Drywall Inspection  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
BLD - Interior Lath  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
BLD - Exterior Lath Insp  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
BLD - Exterior Brown Coat Insp  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
ELE - Rough Electrical  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
MEC - Rough Mechanical  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
PLM - Rough/Topout  1/2/2019  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
BLD - Drywall Inspection  1/2/2019  1/10/2019    1/9/2019  MSM 
BLD - Drywall Inspection  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Drywall Inspection  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
BLD - Interior Lath  1/2/2019  1/10/2019    1/9/2019  MSM 
BLD - Interior Lath  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Interior Lath  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
BLD - Exterior Lath Insp  1/2/2019  1/10/2019    1/9/2019  MSM 
BLD - Exterior Lath Insp  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Exterior Lath Insp  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
BLD - Exterior Brown Coat Insp  1/2/2019  1/10/2019    1/9/2019  MSM 
BLD - Exterior Brown Coat Insp  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Exterior Brown Coat Insp  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
ELE - Rough Electrical  1/2/2019  1/10/2019    1/9/2019  MSM 
ELE - Rough Electrical  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
ELE - Rough Electrical  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
MEC - Rough Mechanical  1/2/2019  1/10/2019    1/9/2019  MSM 
MEC - Rough Mechanical  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
MEC - Rough Mechanical  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
PLM - Rough/Topout  1/2/2019  1/10/2019    1/9/2019  MSM 
PLM - Rough/Topout  1/2/2019  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
PLM - Rough/Topout  1/2/2019  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
BLD - Insulation Insp  1/2/2019 8:27:50 PM  1/3/2019  12 PM - 3 PM  1/3/2019  JOS 
BLD - Reinforcing Insp  1/3/2019 9:38:28 AM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
MEC - Rough Mechanical  1/3/2019 2:52:56 PM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
ELE - Rough Electrical  1/3/2019 2:53:21 PM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
PLM - Rough/Topout  1/3/2019 2:53:48 PM  1/4/2019  12 PM - 3 PM  1/7/2019  BIH 
BLD - Insulation Insp  1/3/2019 9:14:18 PM  1/4/2019  12 PM - 3 PM  1/7/2019  BIH 
PLM - Penetrations Fire -Rated  1/3/2019 9:15:54 PM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
ELE - Penetrations- Fire Rated  1/3/2019 9:16:20 PM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
MEC - Penetrations- Fire Rated  1/3/2019 9:16:46 PM  1/4/2019  12 PM - 3 PM  1/4/2019  BIH 
BLD - Drywall Inspection  1/6/2019 10:02:45 PM  1/7/2019  10 AM - 2 PM  1/7/2019  BIH 
PLM - Penetrations Fire -Rated  1/6/2019 10:03:07 PM  1/7/2019  10 AM - 2 PM  1/7/2019  BIH 
ELE - Penetrations- Fire Rated  1/6/2019 10:03:31 PM  1/7/2019  10 AM - 2 PM  1/7/2019  BIH 
MEC - Penetrations- Fire Rated  1/6/2019 10:03:52 PM  1/7/2019  10 AM - 2 PM  1/7/2019  BIH 
ELE - Rough Electrical  1/6/2019 10:04:26 PM  1/7/2019  10 AM - 2 PM  1/7/2019  BIH 
BLD - Insulation Insp  1/7/2019 7:57:46 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BIH 
BLD - Drywall Inspection  1/7/2019 7:58:04 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BIH 
PLM - Penetrations Fire -Rated  1/7/2019 7:58:22 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BIH 
ELE - Penetrations- Fire Rated  1/7/2019 7:58:57 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BIH 
ELE - Rough Electrical  1/7/2019 7:59:26 PM  1/8/2019  8 AM - 12 PM  1/8/2019  BIH 
BLD - Insulation Insp  1/8/2019 9:56:55 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Penetrations -Fire Rated  1/8/2019 9:58:05 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
PLM - Penetrations Fire -Rated  1/8/2019 9:58:45 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
ELE - Penetrations- Fire Rated  1/8/2019 9:59:22 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
MEC - Penetrations- Fire Rated  1/8/2019 10:00:11 PM  1/9/2019  12 PM - 3 PM  1/9/2019  BIH 
BLD - Drywall Inspection  1/9/2019  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
BLD - Drywall Inspection  1/9/2019  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
ELE - Rough Electrical  1/9/2019  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
ELE - Rough Electrical  1/9/2019  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
MEC - Rough Mechanical  1/9/2019  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
MEC - Rough Mechanical  1/9/2019  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
PLM - Rough/Topout  1/9/2019  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
PLM - Rough/Topout  1/9/2019  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
BLD - Interior Lath  1/9/2019  1/12/2019  8 AM - 12 PM  1/14/2019  BIH 
BLD - Exterior Lath Insp  1/9/2019  1/12/2019  8 AM - 12 PM  1/14/2019  BIH 
ELE - Underground conduit  1/9/2019 2:07:24 PM  1/10/2019  10 AM - 2 PM  1/10/2019  PJJ 
Route to Struct/Architectual  1/9/2019  1/28/2019    1/10/2019  APPR  BVD 
ELE - Underground conduit  1/10/2019 11:59:27 AM  1/11/2019  8 AM - 12 PM  1/11/2019  BIH 
PLM - Penetrations Fire -Rated  1/13/2019 5:09:06 PM  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
ELE - Penetrations- Fire Rated  1/13/2019 5:09:26 PM  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
MEC - Penetrations- Fire Rated  1/13/2019 5:09:46 PM  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
BLD - Insulation Insp  1/13/2019 5:10:11 PM  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
ELE - Electrical Service/Meter  1/13/2019 11:41:33 PM  1/14/2019  8 AM - 12 PM  1/14/2019  BIH 
BLD - Penetrations -Fire Rated  1/14/2019 8:31:10 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
BLD - 2nd Floor Shear Insp  1/14/2019 8:31:59 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
PLM - Penetrations Fire -Rated  1/14/2019 8:32:46 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
ELE - Penetrations- Fire Rated  1/14/2019 8:33:24 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
MEC - Penetrations- Fire Rated  1/14/2019 8:33:42 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
ELE - Electrical Service/Meter  1/14/2019 8:34:39 PM  1/15/2019  10 AM - 2 PM  1/15/2019  BIH 
BLD - Temp Elec Consideration  1/15/2019  1/16/2019  10 AM - 2 PM  1/16/2019  BIH 
BLD - Drywall Inspection  1/15/2019 8:19:26 PM  1/16/2019  10 AM - 2 PM  1/16/2019  BIH 
BLD - 2nd Floor Shear Insp  1/15/2019 8:20:19 PM  1/16/2019  10 AM - 2 PM  1/16/2019  BIH 
BLD - 2nd Floor Shear Insp  1/17/2019 9:26:02 PM  1/18/2019  10 AM - 2 PM  1/18/2019  BIH 
BLD - Drywall Inspection  1/17/2019 9:26:45 PM  1/18/2019  10 AM - 2 PM  1/18/2019  BIH 
Electrical Final Insp Request  1/21/2019 10:10:43 AM  1/22/2019  10 AM - 2 PM  1/22/2019  BIH 
PLM - Penetrations Fire -Rated  1/21/2019 11:56:44 AM  1/22/2019  10 AM - 2 PM  1/22/2019  BIH 
ELE - Penetrations- Fire Rated  1/21/2019 11:56:57 AM  1/22/2019  10 AM - 2 PM  1/22/2019  BIH 
MEC - Penetrations- Fire Rated  1/21/2019 11:57:06 AM  1/22/2019  10 AM - 2 PM  1/22/2019  BIH 
BLD - Drywall Inspection  1/21/2019 11:57:33 AM  1/22/2019  10 AM - 2 PM  1/22/2019  BIH 
BLD - Drywall Inspection  1/22/2019 9:40:21 PM  1/23/2019  10 AM - 2 PM  1/23/2019  BIH 
PLM - Penetrations Fire -Rated  1/22/2019 9:40:47 PM  1/23/2019  10 AM - 2 PM  1/23/2019  BIH 
ELE - Penetrations- Fire Rated  1/22/2019 9:41:05 PM  1/23/2019  10 AM - 2 PM  1/23/2019  BIH 
MEC - Penetrations- Fire Rated  1/22/2019 9:41:20 PM  1/23/2019  10 AM - 2 PM  1/23/2019  BIH 
BLD - Exterior Brown Coat Insp  1/23/2019 9:21:22 PM  1/24/2019  12 PM - 3 PM  1/24/2019  JOS 
BLD - Insulation Insp  1/23/2019 9:21:50 PM  1/24/2019  12 PM - 3 PM  1/24/2019  JOS 
BLD - Exterior Lath Insp  1/23/2019 9:22:19 PM  1/24/2019  12 PM - 3 PM  1/24/2019  JOS 
PLM - Penetrations Fire -Rated  1/24/2019 10:02:37 PM  1/25/2019  12 PM - 3 PM  1/25/2019  JOS 
ELE - Penetrations- Fire Rated  1/24/2019 10:02:54 PM  1/25/2019  12 PM - 3 PM  1/25/2019  JOS 
MEC - Penetrations- Fire Rated  1/24/2019 10:03:25 PM  1/25/2019  12 PM - 3 PM  1/25/2019  JOS 
BLD - Penetrations -Fire Rated  1/24/2019 10:03:46 PM  1/25/2019  12 PM - 3 PM  1/25/2019  JOS 
BLD - Exterior Lath Insp  1/27/2019 9:36:45 PM  1/28/2019  10 AM - 2 PM  1/28/2019  BIH 
PLM - Rough/Topout  1/27/2019 9:37:41 PM  1/28/2019  10 AM - 2 PM  1/28/2019  BIH 
ELE - Rough Electrical  1/27/2019 9:38:06 PM  1/28/2019  10 AM - 2 PM  1/28/2019  BIH 
MEC - Rough Mechanical  1/27/2019 9:38:47 PM  1/28/2019  10 AM - 2 PM  1/28/2019  BIH 
BLD - Drywall Inspection  1/27/2019 9:39:26 PM  1/28/2019  10 AM - 2 PM  1/28/2019  BIH 
BLD - Footings Insp  1/28/2019 10:16:14 AM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
PLM - Rough/Topout  1/28/2019 9:17:02 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
ELE - Rough Electrical  1/28/2019 9:17:15 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
MEC - Rough Mechanical  1/28/2019 9:17:26 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
BLD - Insulation Insp  1/28/2019 9:17:43 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
BLD - 2nd Floor Shear Insp  1/28/2019 9:19:11 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
BLD - Drywall Inspection  1/28/2019 9:19:54 PM  1/29/2019  10 AM - 2 PM  1/29/2019  BIH 
BLD - Insulation Insp  1/29/2019 8:38:02 PM  1/30/2019  10 AM - 2 PM  1/30/2019  BIH 
BLD - Drywall Inspection  1/29/2019 8:38:16 PM  1/30/2019  10 AM - 2 PM  1/30/2019  BIH 
BLD - 2nd Floor Shear Insp  1/29/2019 8:39:50 PM  1/30/2019  10 AM - 2 PM  1/30/2019  BIH 
BLD - 2nd Floor Shear Insp  1/30/2019 10:19:20 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BIH 
PLM - Rough/Topout  1/30/2019 10:19:40 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BIH 
ELE - Rough Electrical  1/30/2019 10:19:58 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BIH 
MEC - Rough Mechanical  1/30/2019 10:20:20 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BIH 
BLD - Drywall Inspection  1/30/2019 10:20:54 PM  1/31/2019  8 AM - 12 PM  1/31/2019  BIH 
BLD - Exterior Brown Coat Insp  2/3/2019 8:23:33 PM  2/4/2019  10 AM - 2 PM  2/4/2019  BIH 
PLM - Rough/Topout  2/3/2019 8:24:38 PM  2/4/2019  10 AM - 2 PM  2/4/2019  BIH 
ELE - Rough Electrical  2/3/2019 8:24:50 PM  2/4/2019  10 AM - 2 PM  2/4/2019  BIH 
MEC - Rough Duct  2/3/2019 8:25:10 PM  2/4/2019  10 AM - 2 PM  2/4/2019  BIH 
ELE - Electrical Service/Meter  2/4/2019 2:12:00 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BIH 
BLD - Drywall Inspection  2/4/2019 2:12:45 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BIH 
BLD - Insulation Insp  2/4/2019 2:13:47 PM  2/5/2019  10 AM - 2 PM  2/5/2019  BIH 
PLM - Rough/Topout  2/5/2019 9:16:58 PM  2/6/2019  10 AM - 2 PM  2/6/2019  BIH 
ELE - Rough Electrical  2/5/2019 9:17:11 PM  2/6/2019  10 AM - 2 PM  2/6/2019  BIH 
MEC - Rough Mechanical  2/5/2019 9:17:26 PM  2/6/2019  10 AM - 2 PM  2/6/2019  BIH 
BLD - Drywall Inspection  2/5/2019 9:19:27 PM  2/6/2019  10 AM - 2 PM  2/6/2019  BIH 
ELE - Electrical Service/Meter  2/6/2019 2:17:13 PM  2/7/2019  10 AM - 2 PM  2/7/2019  BIH 
BLD - Drywall Inspection  2/6/2019 11:27:47 PM  2/7/2019  10 AM - 2 PM  2/7/2019  BIH 
PLM - Rough/Topout  2/6/2019 11:28:32 PM  2/7/2019  10 AM - 2 PM  2/7/2019  BIH 
ELE - Rough Electrical  2/6/2019 11:28:59 PM  2/7/2019  10 AM - 2 PM  2/7/2019  BIH 
MEC - Rough Mechanical  2/6/2019 11:29:15 PM  2/7/2019  10 AM - 2 PM  2/7/2019  BIH 
ELE - Electrical Service/Meter  2/7/2019 9:06:26 AM  2/11/2019  10 AM - 2 PM  2/11/2019  BIH 
ELE - Electrical Service/Meter  2/7/2019 9:07:05 AM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
ELE - Electrical Service/Meter  2/7/2019 9:07:34 AM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
BLD - Insulation Insp  2/7/2019 9:25:51 PM  2/8/2019  12 PM - 3 PM  2/8/2019  JOS 
BLD - Drywall Inspection  2/7/2019 9:26:08 PM  2/8/2019  12 PM - 3 PM  2/8/2019  JOS 
BLD - Drywall Inspection  2/10/2019 6:28:02 PM  2/11/2019  10 AM - 2 PM  2/11/2019  BIH 
PLM - Rough/Topout  2/10/2019 6:29:19 PM  2/11/2019  10 AM - 2 PM  2/11/2019  BIH 
ELE - Rough Electrical  2/10/2019 6:29:41 PM  2/11/2019  10 AM - 2 PM  2/11/2019  BIH 
MEC - Rough Mechanical  2/10/2019 6:30:12 PM  2/11/2019  10 AM - 2 PM  2/11/2019  BIH 
ELE - Electrical Service/Meter  2/11/2019 11:43:38 AM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
BLD - Exterior Brown Coat Insp  2/11/2019 9:39:26 PM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
ELE - Rough Electrical  2/11/2019 9:39:41 PM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
PLM - Rough/Topout  2/11/2019 9:39:51 PM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
MEC - Rough Mechanical  2/11/2019 9:40:10 PM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
BLD - Drywall Inspection  2/11/2019 9:41:18 PM  2/12/2019  12 PM - 3 PM  2/12/2019  BIH 
BLD - Insulation Insp  2/12/2019 10:10:53 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
PLM - Gas Test  2/12/2019 10:12:00 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
PLM - Rough/Topout  2/12/2019 10:15:11 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
ELE - Penetrations- Fire Rated  2/12/2019 10:15:32 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
ELE - Rough Electrical  2/12/2019 10:16:00 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
MEC - Rough Mechanical  2/12/2019 10:17:02 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
ELE - Underground conduit  2/12/2019 10:19:03 PM  2/13/2019  10 AM - 2 PM  2/13/2019  BIH 
BLD - Insulation Insp  2/13/2019 11:36:09 PM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
BLD - Drywall Inspection  2/13/2019 11:36:38 PM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
PLM - Rough/Topout  2/13/2019 11:37:05 PM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
ELE - Rough Electrical  2/13/2019 11:37:36 PM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
MEC - Rough Mechanical  2/13/2019 11:37:54 PM  2/14/2019  10 AM - 2 PM  2/14/2019  BIH 
BLD - Temp Elec Consideration  2/14/2019  2/20/2019  8 AM - 12 PM  2/21/2019  BIH 
ELE - Electrical Service/Meter  2/14/2019  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
BLD - Insulation Insp  2/14/2019 9:39:58 PM  2/15/2019  12 PM - 3 PM  2/15/2019  JOS 
BLD - Drywall Inspection  2/14/2019 9:40:24 PM  2/15/2019  12 PM - 3 PM  2/15/2019  JOS 
BLD - Insulation Insp  2/18/2019 9:40:37 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
BLD - Drywall Inspection  2/18/2019 9:40:54 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
PLM - Gas Test  2/18/2019 9:41:48 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
PLM - Rough/Topout  2/18/2019 9:42:26 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
ELE - Rough Electrical  2/18/2019 9:42:46 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
MEC - Rough Mechanical  2/18/2019 9:43:14 PM  2/19/2019  12 PM - 3 PM  2/19/2019  BIH 
BLD - Drywall Inspection  2/19/2019 9:12:31 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
BLD - Insulation Insp  2/19/2019 9:12:47 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
PLM - Rough/Topout  2/19/2019 9:13:01 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
ELE - Rough Electrical  2/19/2019 9:13:12 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
MEC - Rough Mechanical  2/19/2019 9:13:29 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
PLM - Gas Test  2/19/2019 9:15:08 PM  2/20/2019  8 AM - 12 PM  2/20/2019  BIH 
BLD - Temp Gas Consideration  2/20/2019  2/21/2019  10 AM - 2 PM  2/21/2019  BIH 
BLD - Insulation Insp  2/20/2019 7:16:52 PM  2/21/2019  10 AM - 2 PM  2/21/2019  BIH 
BLD - Drywall Inspection  2/20/2019 7:17:05 PM  2/21/2019  10 AM - 2 PM  2/21/2019  BIH 
ELE - Electrical Service/Meter  2/20/2019 7:17:47 PM  2/21/2019  10 AM - 2 PM  2/21/2019  BIH 
PLM - Gas Test  2/20/2019 7:18:48 PM  2/21/2019  10 AM - 2 PM  2/21/2019  BIH 
BLD - Drywall Inspection  2/21/2019 8:52:21 PM  2/22/2019  12 PM - 3 PM  2/22/2019  JOS 
BLD - Footings Insp  2/22/2019 2:10:24 PM  2/25/2019  12 PM - 3 PM  2/25/2019  BIH 
BLD - Drywall Inspection  2/25/2019 6:46:00 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
BLD - Insulation Insp  2/25/2019 6:46:10 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
PLM - Rough/Topout  2/25/2019 6:46:33 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
ELE - Rough Electrical  2/25/2019 6:46:52 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
MEC - Rough Mechanical  2/25/2019 6:47:08 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
ELE - Electrical Service/Meter  2/25/2019 6:47:43 AM  2/26/2019  12 PM - 3 PM  2/26/2019  BIH 
BLD - Framing Insp.  2/26/2019 9:22:42 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
BLD - Insulation Insp  2/26/2019 9:22:57 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
PLM - Rough/Topout  2/26/2019 9:23:23 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
ELE - Rough Electrical  2/26/2019 9:23:43 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
MEC - Rough Mechanical  2/26/2019 9:24:07 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
BLD - Drywall Inspection  2/26/2019 9:24:40 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
ELE - Electrical Service/Meter  2/26/2019 9:25:17 PM  2/27/2019  10 AM - 2 PM  2/27/2019  BIH 
BLD - Temp Gas Consideration  2/27/2019  2/28/2019  10 AM - 2 PM  2/28/2019  BIH 
PLM - Gas Test  2/27/2019  2/28/2019  10 AM - 2 PM  2/28/2019  BIH 
BLD - Drywall Inspection  2/27/2019 9:24:23 PM  2/28/2019  10 AM - 2 PM  2/28/2019  BIH 
ELE - Electrical Service/Meter  2/27/2019 9:25:07 PM  2/28/2019  10 AM - 2 PM  2/28/2019  BIH 
Route for Phasing Plan  2/26/2019  4/2/2019    2/28/2019  CORR  DAL2 
Approved Phasing Plan  2/26/2019      5/22/2019  APPR  MSM 
BLD - Temp Gas Consideration  3/1/2019  3/4/2019  10 AM - 2 PM  3/4/2019  MSM 
PLM - Gas Test  3/1/2019  3/4/2019  10 AM - 2 PM  3/4/2019  MSM 
BLD - Temp Gas Consideration  3/4/2019  3/5/2019  8 AM - 12 PM  3/5/2019  PJJ 
PLM - Gas Test  3/4/2019  3/5/2019  8 AM - 12 PM  3/5/2019  PJJ 
BLD - Footings Insp  3/5/2019  3/5/2019    3/7/2019  PJJ 
BLD - Exterior Lath Insp  3/10/2019 9:28:06 PM  3/11/2019  12 PM - 3 PM  3/11/2019  BIH 
PLM - Gas Test  3/10/2019 9:29:33 PM  3/11/2019  12 PM - 3 PM  3/11/2019  BIH 
BLD - Reinforcing Insp  3/11/2019 8:57:58 AM  3/12/2019  8 AM - 12 PM  3/12/2019  BIH 
ELE - Underground conduit  3/11/2019 11:56:53 AM  3/12/2019  8 AM - 12 PM  3/12/2019  BIH 
BLD - Reinforcing Insp  3/12/2019 2:32:48 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BIH 
ELE - Electrical Service/Meter  3/12/2019 2:33:26 PM  3/13/2019  12 PM - 3 PM  3/13/2019  BIH 
ELE - Electrical Service/Meter  3/12/2019 2:34:07 PM  3/14/2019  10 AM - 2 PM  3/14/2019  BIH 
BLD - Temp Gas Consideration  3/12/2019  3/13/2019  12 PM - 3 PM  3/13/2019  BIH 
BLD - Footings Insp  3/13/2019 2:30:48 PM  3/14/2019  10 AM - 2 PM  3/14/2019  BIH 
ELE - Electrical Service/Meter  3/13/2019 2:32:02 PM  3/18/2019  10 AM - 2 PM  3/18/2019  BIH 
BLD - Drywall Inspection  3/13/2019 6:36:35 PM  3/14/2019  10 AM - 2 PM  3/14/2019  DONE  BIH 
BLD - Exterior Lath Insp  3/13/2019 6:37:12 PM  3/14/2019  10 AM - 2 PM  3/14/2019  BIH 
BLD - Footings Insp  3/15/2019 9:36:42 AM  3/18/2019  10 AM - 2 PM  3/18/2019  BIH 
ELE - Electrical Service/Meter  3/15/2019 9:37:24 AM  3/19/2019  10 AM - 2 PM  3/19/2019  BIH 
MEC - Rough Mechanical  3/15/2019 1:51:53 PM  3/18/2019  10 AM - 2 PM  3/18/2019  BIH 
PLM - Gas Test  3/17/2019 9:21:41 PM  3/18/2019  10 AM - 2 PM  3/18/2019  BIH 
BLD - Exterior Lath Insp  3/17/2019 9:22:13 PM  3/18/2019  10 AM - 2 PM  3/18/2019  BIH 
ELE - Underground conduit  3/18/2019 9:47:37 AM  3/19/2019  10 AM - 2 PM  3/19/2019  BIH 
BLD - Reinforcing Insp  3/18/2019 9:48:25 AM  3/19/2019  10 AM - 2 PM  3/19/2019  BIH 
PLM - Underfloor Gas  3/18/2019 2:44:16 PM  3/19/2019  10 AM - 2 PM  3/19/2019  BIH 
BLD - Temp Gas Consideration  3/19/2019  3/20/2019  10 AM - 2 PM  3/20/2019  BIH 
PLM - Gas Test  3/19/2019  3/20/2019  10 AM - 2 PM  3/20/2019  BIH 
ELE - Electrical Service/Meter  3/19/2019 10:03:01 PM  3/20/2019  10 AM - 2 PM  3/20/2019  BIH 
ELE - Electrical Service/Meter  3/25/2019 10:01:18 PM  3/26/2019  10 AM - 2 PM  3/26/2019  BIH 
ELE - Electrical Service/Meter  3/29/2019 10:18:55 AM  4/1/2019  10 AM - 2 PM       
ELE - Electrical Service/Meter  3/29/2019 10:19:24 AM  4/2/2019  10 AM - 2 PM  4/2/2019  PJJ 
ELE - Electrical Service/Meter  3/29/2019 10:19:42 AM  4/3/2019  12 PM - 3 PM  4/3/2019  JOS 
ELE - Electrical Service/Meter  3/29/2019 10:20:04 AM  4/4/2019  10 AM - 2 PM  4/4/2019  BIH 
ELE - Electrical Service/Meter  4/1/2019 2:41:55 PM  4/5/2019  12 PM - 3 PM  4/5/2019  JOS 
ELE - Underground conduit  4/5/2019 12:14:17 PM  4/8/2019  10 AM - 2 PM  4/8/2019  BIH 
BLD - 2nd Floor Shear Insp  4/7/2019 9:34:11 PM  4/8/2019  10 AM - 2 PM  4/8/2019  BIH 
BLD - 1st Floor Shear Insp  4/8/2019 12:42:44 PM  4/9/2019  10 AM - 2 PM  4/9/2019  BIH 
ELE - Underground conduit  4/10/2019 12:01:09 PM  4/11/2019  12 PM - 3 PM  4/11/2019  BIH 
ELE - Underground conduit  4/11/2019 2:22:37 PM  4/12/2019  10 AM - 2 PM  4/12/2019  NA  JOS 
Electrical Final Insp Request  4/11/2019 2:24:20 PM  4/15/2019  8 AM - 12 PM  4/15/2019  BIH 
Plumbing Final Insp Request  4/11/2019 2:25:09 PM  4/15/2019  8 AM - 12 PM  4/15/2019  BIH 
Mechanical Final Insp Request  4/11/2019 2:25:28 PM  4/15/2019  8 AM - 12 PM  4/15/2019  BIH 
BLD - Drywall Inspection  4/14/2019 12:42:05 PM  4/15/2019  8 AM - 12 PM  4/15/2019  BIH 
ELE - Electrical Service/Meter  4/14/2019 10:53:24 PM  4/15/2019  8 AM - 12 PM  4/15/2019  BIH 
Plumbing Final Insp Request  4/15/2019 6:50:37 AM  4/16/2019  12 PM - 3 PM  4/16/2019  BIH 
Electrical Final Insp Request  4/15/2019 6:50:53 AM  4/16/2019  12 PM - 3 PM  4/16/2019  BIH 
Mechanical Final Insp Request  4/15/2019 6:51:19 AM  4/16/2019  12 PM - 3 PM  4/16/2019  BIH 
ELE - Electrical Service/Meter  4/15/2019 6:51:43 AM  4/16/2019  12 PM - 3 PM  4/16/2019  BIH 
Plumbing Final Insp Request  4/17/2019 12:55:59 PM  4/18/2019  12 PM - 3 PM  4/18/2019  BIH 
Electrical Final Insp Request  4/17/2019 12:56:26 PM  4/18/2019  12 PM - 3 PM  4/18/2019  BIH 
Mechanical Final Insp Request  4/17/2019 1:11:27 PM  4/18/2019  12 PM - 3 PM  4/18/2019  BIH 
ELE - Electrical Service/Meter  4/17/2019 1:12:29 PM  4/18/2019  12 PM - 3 PM  4/18/2019  BIH 
BLD - Exterior Lath Insp  4/21/2019 9:41:03 PM  4/22/2019  8 AM - 12 PM  4/22/2019  BIH 
ELE - Electrical Service/Meter  4/21/2019 9:41:52 PM  4/22/2019  8 AM - 12 PM  4/22/2019  BIH 
Plumbing Final Insp Request  4/21/2019 9:42:25 PM  4/22/2019  8 AM - 12 PM  4/22/2019  BIH 
Electrical Final Insp Request  4/21/2019 9:42:51 PM  4/22/2019  8 AM - 12 PM  4/22/2019  BIH 
Mechanical Final Insp Request  4/21/2019 9:43:22 PM  4/22/2019  8 AM - 12 PM  4/22/2019  BIH 
Plumbing Final Insp Request  4/22/2019 6:44:08 AM  4/23/2019  8 AM - 12 PM  4/23/2019  BIH 
Electrical Final Insp Request  4/22/2019 6:44:36 AM  4/23/2019  8 AM - 12 PM  4/23/2019  BIH 
Mechanical Final Insp Request  4/22/2019 6:44:59 AM  4/23/2019  8 AM - 12 PM  4/23/2019  BIH 
Plumbing Final Insp Request  4/22/2019 6:45:25 AM  4/24/2019  10 AM - 2 PM  4/25/2019  BIH 
Electrical Final Insp Request  4/22/2019 6:45:52 AM  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
Mechanical Final Insp Request  4/22/2019 6:46:48 AM  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
Plumbing Final Insp Request  4/22/2019 6:47:19 AM  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
Electrical Final Insp Request  4/22/2019 6:47:36 AM  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
Mechanical Final Insp Request  4/22/2019 6:48:09 AM  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
ELE - Electrical Service/Meter  4/22/2019 6:51:17 AM  4/26/2019    4/26/2019  MMO 
Plumbing Final Insp Request  4/22/2019 6:51:35 AM  4/26/2019    4/26/2019  MMO 
Electrical Final Insp Request  4/22/2019 6:51:54 AM  4/26/2019    4/26/2019  MMO 
Mechanical Final Insp Request  4/22/2019 6:52:21 AM  4/26/2019    4/26/2019  MMO 
Plumbing Final Insp Request  4/22/2019 6:52:35 AM  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
Electrical Final Insp Request  4/22/2019 6:52:50 AM  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
Mechanical Final Insp Request  4/22/2019 6:53:09 AM  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
ELE - Electrical Service/Meter  4/22/2019 6:53:31 AM  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
BLD - Misc. Inspection  4/23/2019  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
BLD - Misc. Inspection  4/23/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
ELE - Misc. Inspection  4/23/2019  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
ELE - Misc. Inspection  4/23/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
MEC - Misc. Inspection  4/23/2019  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
MEC - Misc. Inspection  4/23/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
PLM - Misc. Inspection  4/23/2019  4/24/2019  10 AM - 2 PM  4/25/2019  BIH 
PLM - Misc. Inspection  4/23/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
ELE - Electrical Service/Meter  4/23/2019  4/24/2019  10 AM - 2 PM  4/24/2019  BIH 
ELE - Electrical Service/Meter  4/23/2019  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
BLD - Reinforcing Insp  4/24/2019 11:41:23 AM  4/25/2019  8 AM - 12 PM  4/25/2019  BIH 
BLD - Misc. Inspection  4/26/2019  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
BLD - Misc. Inspection  4/26/2019  4/29/2019  8 AM - 12 PM  4/29/2019  JOS 
BLD - Misc. Inspection  4/26/2019  4/30/2019    5/1/2019  JOS 
BLD - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
BLD - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
BLD - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
ELE - Misc. Inspection  4/26/2019  4/29/2019  8 AM - 12 PM  4/29/2019  JOS 
ELE - Misc. Inspection  4/26/2019  4/30/2019    5/1/2019  JOS 
ELE - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
ELE - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
ELE - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
MEC - Misc. Inspection  4/26/2019  4/29/2019  8 AM - 12 PM  4/29/2019  JOS 
MEC - Misc. Inspection  4/26/2019  4/30/2019    5/1/2019  JOS 
MEC - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
MEC - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
MEC - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
PLM - Misc. Inspection  4/26/2019  4/29/2019  8 AM - 12 PM  4/29/2019  JOS 
PLM - Misc. Inspection  4/26/2019  4/30/2019    5/1/2019  JOS 
PLM - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
PLM - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
PLM - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  4/29/2019  8 AM - 12 PM  4/29/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  4/30/2019    5/1/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
BLD - Misc. Inspection  4/26/2019  4/30/2019  10 AM - 2 PM  4/30/2019  GCT 
BLD - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
BLD - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
BLD - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
ELE - Misc. Inspection  4/26/2019  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
ELE - Misc. Inspection  4/26/2019  4/30/2019  10 AM - 2 PM  4/30/2019  GCT 
ELE - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
ELE - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
ELE - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
MEC - Misc. Inspection  4/26/2019  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
MEC - Misc. Inspection  4/26/2019  4/30/2019  10 AM - 2 PM  4/30/2019  GCT 
MEC - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
MEC - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
MEC - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
PLM - Misc. Inspection  4/26/2019  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
PLM - Misc. Inspection  4/26/2019  4/30/2019  10 AM - 2 PM  4/30/2019  GCT 
PLM - Misc. Inspection  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
PLM - Misc. Inspection  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
PLM - Misc. Inspection  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  4/29/2019  10 AM - 2 PM  4/29/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  4/30/2019  10 AM - 2 PM  4/30/2019  GCT 
ELE - Electrical Service/Meter  4/26/2019  5/1/2019  12 PM - 3 PM  5/1/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  5/2/2019  12 PM - 3 PM  5/2/2019  JOS 
ELE - Electrical Service/Meter  4/26/2019  5/3/2019  12 PM - 3 PM  5/3/2019  JOS 
BLD - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/10/2019    5/13/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/10/2019    5/1/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/10/2019    5/10/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/9/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/10/2019    5/10/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/10/2019    5/10/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/7/2019  8 AM - 12 PM  5/7/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
BLD - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/7/2019  8 AM - 12 PM  5/7/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
ELE - Electrical Service/Meter  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/7/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/7/2019  8 AM - 12 PM  5/7/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
ELE - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/7/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/7/2019  8 AM - 12 PM  5/7/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
MEC - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/6/2019  10 AM - 2 PM  5/6/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/7/2019  8 AM - 12 PM  5/7/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/8/2019  8 AM - 12 PM  5/8/2019  BIH 
PLM - Misc. Inspection  5/3/2019  5/9/2019  10 AM - 2 PM  5/9/2019  BIH 
BLD - Misc. Inspection  5/8/2019  5/10/2019    5/10/2019  MMO 
ELE - Electrical Service/Meter  5/8/2019  5/10/2019    5/10/2019  MMO 
ELE - Misc. Inspection  5/8/2019  5/10/2019    5/10/2019  MMO 
MEC - Misc. Inspection  5/8/2019  5/10/2019    5/10/2019  MMO 
PLM - Misc. Inspection  5/8/2019  5/10/2019    5/10/2019  MMO 
BLD - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/16/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/15/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/13/2019  10 AM - 2 PM  5/13/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/15/2019  12 PM - 3 PM  5/16/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/16/2019  12 PM - 3 PM  5/16/2019  BIH 
BLD - Misc. Inspection  5/10/2019  5/14/2019  12 PM - 3 PM  5/14/2019  BIH 
ELE - Electrical Service/Meter  5/10/2019  5/14/2019  12 PM - 3 PM  5/14/2019  BIH 
ELE - Misc. Inspection  5/10/2019  5/14/2019  12 PM - 3 PM  5/14/2019  BIH 
MEC - Misc. Inspection  5/10/2019  5/14/2019  12 PM - 3 PM  5/14/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/14/2019  12 PM - 3 PM  5/14/2019  BIH 
PLM - Misc. Inspection  5/10/2019  5/17/2019    5/17/2019  JOS 
MEC - Misc. Inspection  5/10/2019  5/17/2019    5/17/2019  JOS 
ELE - Misc. Inspection  5/10/2019  5/17/2019    5/17/2019  JOS 
ELE - Electrical Service/Meter  5/10/2019  5/17/2019    5/17/2019  JOS 
BLD - Misc. Inspection  5/10/2019  5/17/2019    5/17/2019  JOS 
BLD - Misc. Inspection  5/13/2019  5/14/2019    5/15/2019  JOS 
BLD - Misc. Inspection  5/13/2019  5/17/2019  12 PM - 3 PM  5/17/2019  JOS 
ELE - Electrical Service/Meter  5/13/2019  5/14/2019    5/15/2019  JOS 
ELE - Electrical Service/Meter  5/13/2019  5/17/2019  12 PM - 3 PM  5/17/2019  JOS 
ELE - Misc. Inspection  5/13/2019  5/14/2019    5/15/2019  JOS 
ELE - Misc. Inspection  5/13/2019  5/17/2019  12 PM - 3 PM  5/17/2019  JOS 
MEC - Misc. Inspection  5/13/2019  5/14/2019    5/15/2019  JOS 
MEC - Misc. Inspection  5/13/2019  5/17/2019  12 PM - 3 PM  5/17/2019  JOS 
PLM - Misc. Inspection  5/13/2019  5/14/2019    5/15/2019  JOS 
PLM - Misc. Inspection  5/13/2019  5/17/2019  12 PM - 3 PM  5/17/2019  JOS 
Approved Phasing Plan  6/13/2019      6/19/2019  APPR  BIH 
Route for Phasing Plan  5/16/2019  6/3/2019    5/22/2019  APPR  472 
Electrical Final Insp Request  5/17/2019  5/20/2019  10 AM - 2 PM  5/20/2019  BIH 
Mechanical Final Insp Request  5/17/2019  5/20/2019  10 AM - 2 PM  5/20/2019  BIH 
Plumbing Final Insp Request  5/17/2019  5/20/2019  10 AM - 2 PM  5/20/2019  BIH 
BLD - TCO App Consideration  5/17/2019  5/20/2019  10 AM - 2 PM  5/20/2019  BIH 
PLM - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
MEC - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
ELE - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
ELE - Electrical Service/Meter  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
BLD - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
BLD - Misc. Inspection  5/17/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
BLD - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
ELE - Electrical Service/Meter  5/17/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
ELE - Electrical Service/Meter  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
ELE - Misc. Inspection  5/17/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
ELE - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
MEC - Misc. Inspection  5/17/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
MEC - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
PLM - Misc. Inspection  5/17/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
PLM - Misc. Inspection  5/17/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
Plumbing Final Insp Request  5/20/2019 1:43:16 PM  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
Electrical Final Insp Request  5/20/2019 1:43:34 PM  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
Mechanical Final Insp Request  5/20/2019 1:43:45 PM  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
Plumbing Final Insp Request  5/20/2019 1:44:28 PM  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
Electrical Final Insp Request  5/20/2019 1:44:48 PM  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
Mechanical Final Insp Request  5/20/2019 1:44:58 PM  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
BLD - TCO App Consideration  5/20/2019  5/21/2019  12 PM - 3 PM  5/21/2019  BIH 
BLD - TCO App Consideration  5/20/2019  5/22/2019  12 PM - 3 PM  5/22/2019  BIH 
Plumbing Final Insp Request  5/22/2019 2:04:45 PM  5/23/2019  10 AM - 2 PM  5/23/2019  BIH 
Electrical Final Insp Request  5/22/2019 2:05:00 PM  5/23/2019  10 AM - 2 PM  5/23/2019  BIH 
Mechanical Final Insp Request  5/22/2019 2:05:19 PM  5/23/2019  10 AM - 2 PM  5/23/2019  BIH 
ELE - Electrical Service/Meter  5/22/2019 2:05:29 PM  5/23/2019  10 AM - 2 PM  5/23/2019  BIH 
BLD - Misc. Inspection  5/24/2019  5/28/2019  12 PM - 3 PM  5/28/2019  BIH 
ELE - Misc. Inspection  5/24/2019  5/28/2019  12 PM - 3 PM  5/28/2019  BIH 
BLD - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
ELE - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
MEC - Misc. Inspection  5/24/2019  5/28/2019  12 PM - 3 PM  5/28/2019  BIH 
MEC - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
PLM - Misc. Inspection  5/24/2019  5/28/2019  12 PM - 3 PM  5/28/2019  BIH 
PLM - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
ELE - Electrical Service/Meter  5/24/2019  5/28/2019  12 PM - 3 PM  5/28/2019  BIH 
ELE - Electrical Service/Meter  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
ELE - Electrical Service/Meter  5/24/2019  5/28/2019    5/28/2019  JOS 
ELE - Electrical Service/Meter  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
BLD - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
ELE - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
MEC - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
PLM - Misc. Inspection  5/24/2019  5/29/2019  10 AM - 2 PM  5/29/2019  BIH 
Electrical Final Insp Request  5/29/2019 10:39:35 AM  5/30/2019  10 AM - 2 PM  5/30/2019  BIH 
Plumbing Final Insp Request  5/29/2019 10:39:59 AM  5/30/2019  10 AM - 2 PM  5/30/2019  BIH 
Mechanical Final Insp Request  5/29/2019 10:40:22 AM  5/30/2019  10 AM - 2 PM  5/30/2019  BIH 
Plumbing Final Insp Request  5/29/2019 10:40:53 AM  6/3/2019  12 PM - 3 PM  6/3/2019  JOS 
Electrical Final Insp Request  5/29/2019 10:41:11 AM  6/3/2019  12 PM - 3 PM  6/3/2019  JOS 
Mechanical Final Insp Request  5/29/2019 10:41:31 AM  6/3/2019  12 PM - 3 PM  6/3/2019  JOS 
Plumbing Final Insp Request  5/29/2019 10:42:02 AM  6/4/2019  8 AM - 12 PM  6/4/2019  BIH 
Electrical Final Insp Request  5/29/2019 10:42:23 AM  6/4/2019  8 AM - 12 PM  6/4/2019  BIH 
Mechanical Final Insp Request  5/29/2019 10:42:38 AM  6/4/2019  8 AM - 12 PM  6/4/2019  BIH 
ELE - Electrical Service/Meter  5/30/2019 2:57:42 PM  6/3/2019  12 PM - 3 PM  6/3/2019  JOS 
ELE - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
MEC - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
PLM - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
ELE - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
MEC - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
PLM - Misc. Inspection  5/31/2019  6/5/2019  10 AM - 2 PM  6/5/2019  BIH 
Plumbing Final Insp Request  6/5/2019 11:17:36 AM  6/6/2019  10 AM - 2 PM  6/6/2019  BIH 
Electrical Final Insp Request  6/5/2019 11:17:45 AM  6/6/2019  10 AM - 2 PM  6/6/2019  BIH 
Mechanical Final Insp Request  6/5/2019 11:17:53 AM  6/6/2019  10 AM - 2 PM  6/6/2019  BIH 
Plumbing Final Insp Request  6/5/2019 11:18:09 AM  6/10/2019  10 AM - 2 PM  6/10/2019  BIH 
Electrical Final Insp Request  6/5/2019 11:18:24 AM  6/10/2019  10 AM - 2 PM  6/10/2019  BIH 
Mechanical Final Insp Request  6/5/2019 11:18:33 AM  6/10/2019  10 AM - 2 PM  6/10/2019  BIH 
Plumbing Final Insp Request  6/5/2019 11:18:50 AM  6/11/2019  10 AM - 2 PM  6/11/2019  BIH 
Electrical Final Insp Request  6/5/2019 11:19:14 AM  6/11/2019  10 AM - 2 PM  6/11/2019  BIH 
Mechanical Final Insp Request  6/5/2019 11:19:27 AM  6/11/2019  10 AM - 2 PM  6/11/2019  BIH 
Electrical Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
Electrical Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
Mechanical Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
Mechanical Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
Plumbing Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
Plumbing Final Insp Request  6/6/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
BLD - TCO App Consideration  6/6/2019  6/10/2019  10 AM - 2 PM  6/10/2019  BIH 
Plumbing Final Insp Request  6/11/2019 10:44:44 AM  6/13/2019  8 AM - 12 PM  6/13/2019  BIH 
Electrical Final Insp Request  6/11/2019 10:44:57 AM  6/13/2019  8 AM - 12 PM  6/13/2019  BIH 
Mechanical Final Insp Request  6/11/2019 10:45:08 AM  6/13/2019  8 AM - 12 PM  6/13/2019  BIH 
Plumbing Final Insp Request  6/11/2019 10:45:19 AM  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
Electrical Final Insp Request  6/11/2019 10:45:30 AM  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
Mechanical Final Insp Request  6/11/2019 10:45:42 AM  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
Plumbing Final Insp Request  6/11/2019 10:45:54 AM  6/18/2019  10 AM - 2 PM  6/18/2019  BIH 
Electrical Final Insp Request  6/11/2019 10:46:04 AM  6/18/2019  10 AM - 2 PM  6/18/2019  BIH 
Mechanical Final Insp Request  6/11/2019 10:46:14 AM  6/18/2019  10 AM - 2 PM  6/18/2019  BIH 
BLD - TCO App Consideration  6/11/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
BLD - TCO App Consideration  6/11/2019  6/12/2019  10 AM - 2 PM  6/12/2019  BIH 
BLD - TCO App Consideration  6/12/2019  6/13/2019  8 AM - 12 PM  6/13/2019  BIH 
BLD - TCO App Consideration  6/12/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
BLD - TCO App Consideration  6/12/2019  6/18/2019  10 AM - 2 PM  6/18/2019  BIH 
BLD - TCO App Consideration  6/12/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
BLD - TCO App Consideration  6/12/2019  6/20/2019  10 AM - 2 PM  6/20/2019  BIH 
BLD - TCO App Consideration  6/13/2019  6/17/2019  10 AM - 2 PM  6/13/2019  BIH 
BLD - TCO App Consideration  6/13/2019  6/19/2019  8 AM - 12 PM  6/13/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
MEC - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
MEC - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
PLM - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
PLM - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/20/2019  BIH 
MEC - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
MEC - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
PLM - Misc. Inspection  6/13/2019  6/17/2019  10 AM - 2 PM  6/17/2019  BIH 
PLM - Misc. Inspection  6/13/2019  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/18/2019  10 AM - 2 PM  6/18/2019  BIH 
ELE - Misc. Inspection  6/13/2019  6/20/2019  10 AM - 2 PM  6/20/2019  BIH 
Plumbing Final Insp Request  6/14/2019 7:10:22 AM  6/20/2019  10 AM - 2 PM  6/20/2019  BIH 
Electrical Final Insp Request  6/14/2019 7:10:36 AM  6/20/2019  10 AM - 2 PM  6/20/2019  BIH 
Mechanical Final Insp Request  6/14/2019 7:10:47 AM  6/20/2019  10 AM - 2 PM  6/20/2019  BIH 
Plumbing Final Insp Request  6/14/2019 7:11:02 AM  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
Electrical Final Insp Request  6/14/2019 7:11:15 AM  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
Mechanical Final Insp Request  6/14/2019 7:11:28 AM  6/19/2019  8 AM - 12 PM  6/19/2019  BIH 
Route for Phasing Plan  6/13/2019  7/1/2019    6/13/2019  APPR  BIH 
Approved Phasing Plan  6/13/2019      6/13/2019  APPR  BIH 
Plumbing Final Insp Request  6/21/2019 11:06:22 AM  6/24/2019  8 AM - 12 PM  6/24/2019  BIH 
Electrical Final Insp Request  6/21/2019 11:06:45 AM  6/24/2019  8 AM - 12 PM  6/24/2019  BIH 
Mechanical Final Insp Request  6/21/2019 11:06:56 AM  6/24/2019  8 AM - 12 PM  6/24/2019  BIH 
Plumbing Final Insp Request  6/24/2019 12:37:15 PM  6/25/2019  10 AM - 2 PM  6/25/2019  BIH 
Electrical Final Insp Request  6/24/2019 12:37:24 PM  6/25/2019  10 AM - 2 PM  6/25/2019  BIH 
Mechanical Final Insp Request  6/24/2019 12:37:31 PM  6/25/2019  10 AM - 2 PM  6/25/2019  BIH 
Plumbing Final Insp Request  7/2/2019 7:48:21 AM  7/8/2019  10 AM - 2 PM  7/8/2019  BIH 
Electrical Final Insp Request  7/2/2019 7:48:44 AM  7/8/2019  10 AM - 2 PM  7/8/2019  BIH 
Mechanical Final Insp Request  7/2/2019 7:48:54 AM  7/8/2019  10 AM - 2 PM  7/8/2019  BIH 
Plumbing Final Insp Request  7/2/2019 7:49:05 AM  7/9/2019  10 AM - 2 PM  7/9/2019  BIH 
Electrical Final Insp Request  7/2/2019 7:49:22 AM  7/9/2019  10 AM - 2 PM  7/9/2019  BIH 
Mechanical Final Insp Request  7/2/2019 7:49:35 AM  7/9/2019  10 AM - 2 PM  7/9/2019  BIH 
Plumbing Final Insp Request  7/2/2019 7:49:50 AM  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
Electrical Final Insp Request  7/2/2019 7:50:00 AM  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
Mechanical Final Insp Request  7/2/2019 7:50:15 AM  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
BLD - Misc. Inspection  7/3/2019  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
ELE - Misc. Inspection  7/3/2019  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
MEC - Misc. Inspection  7/3/2019  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
PLM - Misc. Inspection  7/3/2019  7/10/2019  10 AM - 2 PM  7/10/2019  BIH 
Plumbing Final Insp Request  7/3/2019 11:01:19 AM  7/11/2019  10 AM - 2 PM  7/11/2019  BIH 
Electrical Final Insp Request  7/3/2019 11:01:32 AM  7/11/2019  10 AM - 2 PM  7/11/2019  BIH 
Mechanical Final Insp Request  7/3/2019 11:01:43 AM  7/11/2019  10 AM - 2 PM  7/11/2019  BIH 
Plumbing Final Insp Request  7/9/2019 8:57:12 AM  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
Electrical Final Insp Request  7/9/2019 8:57:24 AM  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
Mechanical Final Insp Request  7/9/2019 8:59:15 AM  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
Plumbing Final Insp Request  7/9/2019 8:59:23 AM  7/16/2019  10 AM - 2 PM  7/16/2019  BIH 
Electrical Final Insp Request  7/9/2019 8:59:35 AM  7/16/2019  10 AM - 2 PM  7/16/2019  BIH 
Mechanical Final Insp Request  7/9/2019 8:59:47 AM  7/16/2019  10 AM - 2 PM  7/16/2019  BIH 
BLD - Misc. Inspection  7/9/2019  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
BLD - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
BLD - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/17/2019  BIH 
BLD - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/17/2019  BIH 
BLD - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
ELE - Misc. Inspection  7/9/2019  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
ELE - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/17/2019  BIH 
ELE - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
ELE - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
ELE - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
MEC - Misc. Inspection  7/9/2019  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
MEC - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
MEC - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
MEC - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/17/2019  BIH 
MEC - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
PLM - Misc. Inspection  7/9/2019  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
PLM - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/17/2019  BIH 
PLM - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/15/2019  BIH 
PLM - Misc. Inspection  7/9/2019  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
PLM - Misc. Inspection  7/9/2019  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
Plumbing Final Insp Request  7/10/2019 4:11:02 PM  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
Electrical Final Insp Request  7/10/2019 4:11:15 PM  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
Mechanical Final Insp Request  7/10/2019 4:11:33 PM  7/17/2019  10 AM - 2 PM  7/18/2019  BIH 
Plumbing Final Insp Request  7/11/2019 10:34:37 AM  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
Electrical Final Insp Request  7/11/2019 10:34:48 AM  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
Mechanical Final Insp Request  7/11/2019 10:34:56 AM  7/18/2019  10 AM - 2 PM  7/18/2019  BIH 
BLD - TCO App Consideration  7/12/2019  7/15/2019  10 AM - 2 PM  7/15/2019  BIH 
Electrical Final Insp Request  7/22/2019  7/23/2019  10 AM - 2 PM  7/23/2019  BIH 
Electrical Final Insp Request  7/22/2019  7/24/2019  8 AM - 12 PM  7/24/2019  BIH 
Electrical Final Insp Request  7/22/2019  7/25/2019  10 AM - 2 PM  7/25/2019  BIH 
Mechanical Final Insp Request  7/22/2019  7/23/2019  10 AM - 2 PM  7/23/2019  BIH 
Mechanical Final Insp Request  7/22/2019  7/24/2019  8 AM - 12 PM  7/24/2019  BIH 
Mechanical Final Insp Request  7/22/2019  7/25/2019  10 AM - 2 PM  7/25/2019  BIH 
Plumbing Final Insp Request  7/22/2019  7/23/2019  10 AM - 2 PM  7/23/2019  BIH 
Plumbing Final Insp Request  7/22/2019  7/24/2019  8 AM - 12 PM  7/24/2019  BIH 
Plumbing Final Insp Request  7/22/2019  7/25/2019  10 AM - 2 PM  7/25/2019  BIH 
BLD - TCO App Consideration  7/24/2019  7/25/2019  10 AM - 2 PM  7/25/2019  BIH 
Plumbing Final Insp Request  7/25/2019 7:20:47 AM  7/29/2019  12 PM - 3 PM  7/29/2019  BIH 
Electrical Final Insp Request  7/25/2019 7:21:26 AM  7/29/2019  12 PM - 3 PM  7/29/2019  BIH 
Mechanical Final Insp Request  7/25/2019 7:21:45 AM  7/29/2019  12 PM - 3 PM  7/29/2019  BIH 
Plumbing Final Insp Request  7/25/2019 7:22:03 AM  7/30/2019  10 AM - 2 PM  7/30/2019  BIH 
Electrical Final Insp Request  7/25/2019 7:22:21 AM  7/30/2019  10 AM - 2 PM  7/30/2019  BIH 
Mechanical Final Insp Request  7/25/2019 7:22:40 AM  7/30/2019  10 AM - 2 PM  7/30/2019  BIH 
Plumbing Final Insp Request  7/25/2019 7:23:08 AM  7/31/2019  8 AM - 12 PM  7/31/2019  BIH 
Electrical Final Insp Request  7/25/2019 7:23:25 AM  7/31/2019  8 AM - 12 PM  7/31/2019  BIH 
Mechanical Final Insp Request  7/25/2019 7:23:37 AM  7/31/2019  8 AM - 12 PM  7/31/2019  BIH 
Plumbing Final Insp Request  7/25/2019 7:23:53 AM  8/1/2019  8 AM - 12 PM  8/1/2019  BIH 
Electrical Final Insp Request  7/25/2019 7:24:09 AM  8/1/2019  8 AM - 12 PM  8/1/2019  BIH 
Mechanical Final Insp Request  7/25/2019 7:24:29 AM  8/1/2019  8 AM - 12 PM  8/1/2019  BIH 
BLD - TCO App Consideration  7/26/2019  7/29/2019  12 PM - 3 PM  7/29/2019  BIH 
Plumbing Final Insp Request  7/31/2019 7:27:40 AM  8/5/2019  8 AM - 12 PM  8/5/2019  BIH 
Electrical Final Insp Request  7/31/2019 7:27:53 AM  8/5/2019  8 AM - 12 PM  8/5/2019  BIH 
Mechanical Final Insp Request  7/31/2019 7:28:02 AM  8/5/2019  8 AM - 12 PM  8/5/2019  BIH 
Plumbing Final Insp Request  7/31/2019 7:28:14 AM  8/6/2019  10 AM - 2 PM  8/6/2019  BIH 
Electrical Final Insp Request  7/31/2019 7:28:23 AM  8/6/2019  10 AM - 2 PM  8/6/2019  BIH 
Mechanical Final Insp Request  7/31/2019 7:28:32 AM  8/6/2019  10 AM - 2 PM  8/6/2019  BIH 
Plumbing Final Insp Request  7/31/2019 7:28:44 AM  8/7/2019  8 AM - 12 PM  8/7/2019  BIH 
Electrical Final Insp Request  7/31/2019 7:28:52 AM  8/7/2019  8 AM - 12 PM  8/7/2019  BIH 
Mechanical Final Insp Request  7/31/2019 7:29:02 AM  8/7/2019  8 AM - 12 PM  8/7/2019  BIH 
Plumbing Final Insp Request  8/1/2019 8:33:48 AM  8/8/2019  8 AM - 12 PM  8/8/2019  DONE  BIH 
Electrical Final Insp Request  8/1/2019 8:33:58 AM  8/8/2019  8 AM - 12 PM  8/8/2019  DONE  BIH 
Mechanical Final Insp Request  8/1/2019 8:34:08 AM  8/8/2019  8 AM - 12 PM  8/8/2019  DONE  BIH 
Plumbing Final Insp Request  8/10/2019 7:29:15 PM  8/12/2019  10 AM - 2 PM  8/12/2019  BIH 
Electrical Final Insp Request  8/10/2019 7:29:51 PM  8/12/2019  10 AM - 2 PM  8/12/2019  BIH 
Mechanical Final Insp Request  8/10/2019 7:30:03 PM  8/12/2019  10 AM - 2 PM  8/12/2019  BIH 
Plumbing Final Insp Request  8/10/2019 7:30:25 PM  8/13/2019  8 AM - 12 PM  8/13/2019  BIH 
Electrical Final Insp Request  8/10/2019 7:30:41 PM  8/13/2019  8 AM - 12 PM  8/13/2019  BIH 
Mechanical Final Insp Request  8/10/2019 7:30:53 PM  8/13/2019  8 AM - 12 PM  8/13/2019  BIH 
Plumbing Final Insp Request  8/14/2019 8:12:12 AM  8/19/2019  8 AM - 12 PM  8/19/2019  BIH 
Electrical Final Insp Request  8/14/2019 8:12:21 AM  8/19/2019  8 AM - 12 PM  8/19/2019  BIH 
Mechanical Final Insp Request  8/14/2019 8:12:32 AM  8/19/2019  8 AM - 12 PM  8/19/2019  BIH 
Plumbing Final Insp Request  8/14/2019 8:13:01 AM  8/20/2019  8 AM - 12 PM  8/20/2019  BIH 
Electrical Final Insp Request  8/14/2019 8:13:14 AM  8/20/2019  8 AM - 12 PM  8/20/2019  BIH 
Mechanical Final Insp Request  8/14/2019 8:13:23 AM  8/20/2019  8 AM - 12 PM  8/20/2019  BIH 
Plumbing Final Insp Request  8/14/2019 8:13:39 AM  8/21/2019  8 AM - 12 PM  8/21/2019  BIH 
Electrical Final Insp Request  8/14/2019 8:13:48 AM  8/21/2019  8 AM - 12 PM  8/21/2019  BIH 
Mechanical Final Insp Request  8/14/2019 8:13:58 AM  8/21/2019  8 AM - 12 PM  8/21/2019  BIH 
BLD - TCO App Consideration  8/14/2019  8/20/2019  8 AM - 12 PM  8/19/2019  MSM 
Plumbing Final Insp Request  8/15/2019 8:15:07 AM  8/22/2019  8 AM - 12 PM  8/22/2019  BIH 
Electrical Final Insp Request  8/15/2019 8:15:19 AM  8/22/2019  8 AM - 12 PM  8/22/2019  BIH 
Mechanical Final Insp Request  8/15/2019 8:15:37 AM  8/22/2019  8 AM - 12 PM  8/22/2019  BIH 
Electrical Final Insp Request  8/23/2019  8/29/2019  8 AM - 12 PM  8/29/2019  BIH 
Mechanical Final Insp Request  8/23/2019  8/29/2019  8 AM - 12 PM  8/29/2019  BIH 
Plumbing Final Insp Request  8/23/2019  8/26/2019  10 AM - 2 PM  8/26/2019  BIH 
ELE - Electrical Service/Meter  8/23/2019  8/29/2019  8 AM - 12 PM  8/29/2019  BIH 
Plumbing Final Insp Request  8/23/2019 8:36:06 PM  8/29/2019  8 AM - 12 PM  8/29/2019  BIH 
BLD - TCO App Consideration  8/27/2019  8/29/2019  8 AM - 12 PM  8/29/2019  BIH 
BLD - TCO App Consideration  8/30/2019  9/4/2019  10 AM - 2 PM  9/4/2019  BIH 
Plumbing Final Insp Request  9/4/2019 3:17:39 PM  9/10/2019  10 AM - 2 PM  9/10/2019  BIH 
Electrical Final Insp Request  9/4/2019 3:17:54 PM  9/10/2019  10 AM - 2 PM  9/10/2019  BIH 
Mechanical Final Insp Request  9/4/2019 3:18:04 PM  9/10/2019  10 AM - 2 PM  9/10/2019  BIH 
Plumbing Final Insp Request  9/4/2019 3:18:19 PM  9/11/2019  10 AM - 2 PM  9/11/2019  BIH 
Electrical Final Insp Request  9/4/2019 3:18:33 PM  9/11/2019  10 AM - 2 PM  9/11/2019  BIH 
Mechanical Final Insp Request  9/4/2019 3:18:43 PM  9/11/2019  10 AM - 2 PM  9/11/2019  BIH 
Plumbing Final Insp Request  9/5/2019 7:30:40 AM  9/12/2019  8 AM - 12 PM  9/9/2019  GGO 
Electrical Final Insp Request  9/5/2019 7:30:49 AM  9/12/2019  8 AM - 12 PM  9/9/2019  GGO 
Mechanical Final Insp Request  9/5/2019 7:30:59 AM  9/12/2019  8 AM - 12 PM  9/9/2019  GGO 
Electrical Final Insp Request  9/16/2019  9/25/2019  10 AM - 2 PM  9/25/2019  BIH 
Mechanical Final Insp Request  9/16/2019  9/25/2019  10 AM - 2 PM  9/25/2019  BIH 
Plumbing Final Insp Request  9/16/2019  9/25/2019  10 AM - 2 PM  9/25/2019  BIH 
Electrical Final Insp Request  9/16/2019  9/26/2019    9/25/2019  GGO 
Mechanical Final Insp Request  9/16/2019  9/26/2019    9/25/2019  GGO 
Plumbing Final Insp Request  9/16/2019  9/26/2019    9/25/2019  GGO 
Plumbing Final Insp Request  10/1/2019 1:53:00 PM  10/8/2019  8 AM - 12 PM  10/8/2019  BIH 
Electrical Final Insp Request  10/1/2019 1:53:12 PM  10/8/2019  8 AM - 12 PM  10/8/2019  BIH 
Mechanical Final Insp Request  10/1/2019 1:53:21 PM  10/8/2019  8 AM - 12 PM  10/8/2019  BIH 
Plumbing Final Insp Request  10/8/2019 10:44:02 AM  10/9/2019  8 AM - 12 PM  10/9/2019  BIH 
Electrical Final Insp Request  10/8/2019 10:44:15 AM  10/9/2019  8 AM - 12 PM  10/9/2019  BIH 
Mechanical Final Insp Request  10/8/2019 10:44:24 AM  10/9/2019  8 AM - 12 PM  10/9/2019  BIH 
Electrical Final Insp Request  10/9/2019 2:37:44 PM  10/10/2019  10 AM - 2 PM  10/10/2019  BIH 
Electrical Final        10/9/2019    BIH 
Plumbing Final        10/9/2019    BIH 
Mechanical Final        10/9/2019    BIH 
Building Final Insp Request  10/9/2019  10/10/2019  10 AM - 2 PM  10/10/2019  BIH 
Electrical Final        10/10/2019    BIH 
Planning GIS - Building Change  10/10/2019 2:43:11 PM      10/11/2019  DONE  HXN 
Building Final        10/10/2019    BIH 

 